June 2016
Using a Programmatic Permitting Approach to Move Through the Corps' - - PowerPoint PPT Presentation
Using a Programmatic Permitting Approach to Move Through the Corps' - - PowerPoint PPT Presentation
Using a Programmatic Permitting Approach to Move Through the Corps' Regulatory Process On Time and Under Budget June 2016 Overview for T odays Discussion Permitting Background Programmatic Permitting ESA Compliance In-Lieu Fee Programs
Overview for T
- day’s Discussion
Programmatic Permitting In-Lieu Fee Programs Permitting Background ESA Compliance
PERMITTING BACKGROUND
- Corps Regulatory Program Goals
Provide strong protection to the Nation’s aquatic environment, including wetlands Enhance the efficiency of the Corps administration of its regulatory program Ensure that the Corps provides the regulated public with fair and reasonable decisions
Jurisdiction
- Navigable waters of the United States are those waters
subject to the ebb and flow of the tide and/or are presently used, or have been used in the past, or may be susceptible for use to transport interstate or foreign commerce.
- Ocean and coastal waters to 3 nautical miles seaward of
baseline
- Tidal waters shoreward to MHW
- Non-tidal waters to OHWM and upstream to head of
navigation and adjacent wetlands
Jurisdiction – Section 10
Jurisdiction – Activities Regulated Under Section 10
Structures: Weirs, utility/power lines, tunnels, piers, wharves, dolphins, breakwaters, booms, bulkheads, revetments, riprap, jetties, permanent mooring structures, aids to navigation, permanently moored floating facilities, pilings Structures or work in,
- ver, or under navigable
waters of the U.S. (§ 10 of Rivers and Harbors Act of 1899) Work: Excavation, dredging, filling, or modification
Includes all navigable waters of the U.S.
Plus
– Adjacent wetlands – Extent of jurisdiction
- Territorial seas – from baseline seaward to three nautical miles
- Tidal waters of the U.S. – landward limits extend to high tide line
- r to limit of adjacent wetlands
- Non-tidal waters of the U.S. – jurisdiction extends to ordinary
high water mark or to limit of adjacent wetlands
Jurisdiction – Section 404
Jurisdiction – Activities Regulated Under Section 404
Discharge of dredged material means any addition of dredged material into, including redeposit of dredged material other than incidental fallback within, waters of the US. Discharge of fill material means material placed in waters of the United States where the material has the effect of: i.Replacing any portion of a water of the US with dry land; or ii.Changing the bottom elevation of any portion of a water of the US.
Discharges of dredged or fill material into all waters of the U.S. (§ 404 of the Clean Water Act of 1972)
Sequential approach to decision making:
- General Permits
– Regional/Programmatic General Permit (MOST EFFICIENT) – Nationwide Permit (impacts minimal, supposed to be timely)
- LOP/Abbreviated Individual Permit Process
(MOST EFFICIENT)
- Standard Individual Permit (a “one-off” permit,
least simple, most time consuming)
Permitting Process
- Nationwide Permits.
– Corps estimates 45 Days to process. – Are supposed to allow certain activities with little delay and paperwork. – Read the PCN timing fine print.
- Individual Permits.
– Corps estimates 2-3 months to process a routine application involving a public notice. – Process in120 days.
Project Review Timelines
How long will it take?
Standard Permitting Review Process
PROGRAMMATIC PERMITTING
Programmatic Permitting Advantages
Saves Money
- Eliminates redundancies
- Studies and other project-by-project
costs
- Economies of scale with consolidated
mitigation
- Advanced mitigation lowers ratios
Saves time (timeline certainty!)
- Reduce agency review with pre-
screening
- Ground rules already established
- Mitigation identified
Programmatic Permitting Advantages
- –
– –
- –
– –
Provides outcome certainty! Helps regulatory agencies
- Efficiency
- Time to spend on larger projects
- Better documentation and tracking
Better for the environment
- Planning at a watershed scale
- Better project outcomes
- Better mitigation outcomes
Think about: – Proposed activities – Geographic area – Which Permit(s)? (LOP or RGP or PGP) – What other agency permits? – CEQA and other technical studies
Setting Up a Programmatic Permit
ENDANGERED SPECIES ACT COMPLIANCE
- Protection of endangered and threatened
species and their habitats
- Unlawful to “take” a listed animal without
a permit.
- Section 7 = for federal agencies
- Section 10 (HCP) = non-federal landowners
Endangered Species Act
ESA Coverage for Programmatic Permit
Integration with Habitat Conservation Plan Programmatic Section 7 Consultation
OR
Programmatic Determination of Not Likely to Adversely Affect (NLAA)
- Establishes procedures and project criteria for the
purposes of streamlining typical project-by-project ESA review for projects with negligible effects on listed species
- r designated Critical Habitat
- USFWS/NMFS concurrence that projects complying with
an agreed-upon set of criteria will be “not likely to adversely affect” – Applies to projects where effects are expected to be discountable, insignificant, or completely beneficial
- No need for initiation of consultation on a project-by-
project basis; programmatic concurrence, with advance notifications to USFWS/NMFS and annual reporting
- Activity-specific conditions (e.g., project design criteria)
and species-specific conditions must be met
- Impact thresholds are pre-determined and generally within
the range of General Permits
- Renewable on a 5-year basis
Programmatic Section 7 Consultation Options
Programmatic Biological Opinion
- Provides a framework to streamline ESA approval of projects
involving a federal permit, funding or action and where such projects “may adversely affect” listed species or critical habitat
- Establishes pre-determined project design criteria and impact
thresholds that must be met in order to qualify for coverage
- Can be used for all types of projects and provides applicants up-front information to
design projects to avoid affects on listed species
- Generally addresses effects of multiple activities at larger scales and promotes more
consistent application of conservation measures
- Increases certainty in the following:
- 1. timeframes for project approval
- 2. project cost
- 3. overall conservation benefits/outcomes
- Reduces regulatory burden and allows for more efficient use of
agency staff time when compared to project-by-project approach
Programmatic Section 7 Consultation Options (continued)
- Programmatic permits, such as RGPs and PGPs, when developed in concert with
HCPs can provide streamlined approval for covered activities under the HCP that also have impacts on waters of the U.S.
- Applies only to covered activities in waters of the U.S. within the plan area
- Covered activities must comply with thresholds, terms and conditions established
under RGP/PGP and requirements of HCP
- Avoids the often redundant regulatory process typically involved with Section 7
consultations triggered by the necessity of obtaining a 404 permit in an HCP area
- Ensures consistency in mitigation approach and requirements from the Corps
- Allows for coordinated restoration, enhancement and conservation of waters of the
U.S. and associated functions at a landscape scale in conjunction with HCP conservation actions
Integration with Habitat Conservation Plans
- Section 106 of
the National Historic Preservation Act
- Coastal Zone
Management Act
Compliance with Other Laws
IN-LIEU FEE PROGRAMS
Mitigation Planning – the 3 Ms
- Sequence:
– Avoidance – Minimization – Compensatory Mitigation
- Incorporate pre-identified
compensatory mitigation planning
- ILF well-suited to
programmatic permitting
What is compensatory mitigation to the Corps?
- Corps’ Mitigation Rule finalized April 2008
- Outcome-based mitigation to offset unavoidable impacts
to waters of the United States
- Mitigation measured by aquatic functions
Restoration (Re-establishment/Rehabilitation)
- Returning natural or historic functions to a degraded or
former aquatic resource
Establishment (a.k.a. creation)
- Manipulate an upland site to create an aquatic resource
Enhancement
- Manipulate an existing resource to increase one or more specific
functions
Preservation
- Remove a threat to an existing aquatic resource and
provide management
Mitigation Policy Background
What is an ILF?
- Program involving restoration, establishment,
enhancement, and/or preservation of aquatic resources through the collection of fees to satisfy mitigation requirements of permits
Sponsors
- Government or Non-Profit natural resources
management entity can be sponsors; assumes responsibility for successful implementation of compensatory mitigation
Use of Fees
- Fees must be used to plan, design, and implement
compensatory mitigation projects
Introducing In Lieu Fee
THE PREFERENCE HIERARCHY Mitigation Bank
- Commercial entity for profit or a single user for practicality
- Single project sites where larger compensatory mitigation project is done
- Permittees purchase credits from sponsor
- Sponsor assumes responsibility for providing the mitigation
In-Lieu Fee Program
- Government or non-profit natural resource management entity
- Consolidates fees to provide strategic compensatory mitigation projects
with greater ecological benefits
- Sponsor assumes responsibility for providing mitigation
Permittee-responsible
- On-site, Off-site (in watershed) and/or in-kind
Types of Mitigation Programs
- Greater ecological benefits
- Focus on watershed needs
- Increase capacity for local,
ecologically-appropriate habitat improvement projects
- Develop self-sustaining revenue
source to fund mitigation projects
- Create and strengthen local
community partnerships
In-Lieu Fee Overview
- Only the Corps authorizes ILFs
- Other agencies can authorize use on
a case-by-case basis
- In-Lieu Fee credit sales are market driven
- Mitigation Credit Sales fund project
planning, design, implementation and long term management.
- Mitigation projects are normally required
to be implemented within 3 years of selling credits
In Lieu Fee Program Basics
Permittee Benefits:
- Compensatory Mitigation availability
- Mitigation certainty
- Cost savings
Permittee/Sponsor Benefits
Sponsor Benefits:
- Provide funding for
strategically important restoration projects
- Increased capacity: can
become the local source of mitigation credits
- Consolidated projects with
greater ecological benefits
- Enhance more important
wetlands and stream corridors
EXAMPLE – SUISUN MARSH
Example – Suisun Marsh
- Suisun Marsh: largest contiguous brackish
water marsh on the west coast of North America (over 50,000 acres).
- Suisun Marsh Management Plan: balance tidal
wetland restoration, ESA habitat, managed wetlands, public use, upland habitat.
- Suisun Marsh: resting and feeding ground
for thousands of migrating birds on the Pacific Flyway; tidal rearing ground for salmonids; 200 miles of levees help manage salinity in the Sacramento- San Joaquin River Delta (Delta).
- Recreation: 158 private duck clubs; CDFW
lands; other recreation
Suisun Marsh Challenges
RESOURCE PROTECTION CHALLENGES:
- Water management practices
and operations
- Managed wetlands operations
and management
- Habitat protection for multiple
special status species PEOPLE CHALLENGES:
- Seven State and Federal
Agency Stakeholders
- Hundreds of private
landowner Stakeholders
- Public landowners
(DWR, Bureau of Reclamation, CDFW)
- All must integrate
competing uses into beneficial uses to restore and protect Suisun Marsh
Regional General Permit 3 (RGP3)
- Applicants: Suisun RCD; CDFW; CDWR; U.S. Bureau of Reclamation
- Authorizes Operations and Maintenance Activities:
- ditch maintenance; placement of rip-rap; exterior and interior levee
maintenance; bulkhead repair; grading work; duck blind placement; salinity monitoring equipment; coffer dams; water control structures work; fish screen maintenance and repair; salinity station maintenance/repair/replacement
- RGP3 administered by Suisun RCD
- 30 day authorization process by Corps
- Conditional 401 Cert covers all RGP3 activities
- Programmatic BOs from USFWS, NMFS covers all RGP3 activities
- Annual report summarize amounts and locations of activities
- Mitigation completed as part of a 30 year plan to protect Suisun Marsh
Suisun Marsh Letter of Permission (LOP)
- Applicants: Suisun RCD; CDFW; CDWR; U.S. Bureau of Reclamation
- Authorizes up to 100,000 cubic yards of material, and up to 19.83 acres
- r 90,446 linear feet (17.13 linear miles) to be dredged from:
- Bays the border Suisun Marsh Managed Wetlands
- Major Sloughs in the Suisun Marsh
- Minor Sloughs in the Suisun Marsh
- Dredger Cuts in the Suisun Marsh
- 1,000,000 cubic yards authorized over 10 years
- 401 Cert coverage
- Programmatic BOs from USFWS, NMFS coverage
- Annual report summarize amounts and locations of dredging
- Mitigation completed as part of a 30 year plan to protect Suisun Marsh
Suisun Marsh Programmatic Permitting Benefits
PERMITTEE BENEFITS
- Saves time! 100s of permit applications are
processed with timeline certainty (30 days)
- Permit submittal consistency (Suisun RCD
handles permitting for landowners).
- Avoidance, minimization, mitigation
requirements known. No surprises.
- Saves money (everything is already
completed: CEQA, environmental studies, permit application process, mitigation). AGENCY BENEFITS
- Agencies aren’t “papered.”
- Better environmental protection
- Better monitoring
- Agencies can track, monitor, understand
individual and cumulative impacts
EXAMPLE – South Sacramento HCP
Example – South Sacramento HCP
- SSHCP provides a landscape-level approach to
protection of important biological resources
- Plan Area – 317,655 acres within south
Sacramento County
- 28 Covered Species of plants and wildlife
- New conservation of 33,796 acres
- Urbanization Covered Activities occur within
Urban Development Area
- Need = Aquatic Permits Integration!
- Aquatic Resources Program (ARP) developed
in coordination with SSHCP
SSHP Plan Area Urban Development Area (UDA) Preserve Planning Units (PPU) Galt City Limits Rancho Cordova Limits
SSHCP Aquatic Resources Program
HCP/Aquatic Resources integration is possible
T
- Make it Work:
- Need to bring all agencies together
- Need correct terminology
- Need to understand all agencies’ concerns
SSHCP Aquatic Resources Program
- ARP provides a regulatory framework
for projects in SSHCP to comply with federal, state, and local laws that protect aquatic resources
- Multidisciplinary, programmatic
approach to obtain permits for impacts to aquatic resources (404, 401, 1600)
- Permitting process has
pre-identified avoidance and minimization requirements
- Comprehensive compensatory
mitigation strategy
Aquatic Resources Permitting Strategy
- Programmatic General Permit
- Regional General Permit
- Letter of Permission procedure
- Abbreviated Standard Permit Procedure
Plus
- In-Lieu Fee Program
- EXAMPLE – 2013 USACE/NMFS NLAA PROGRAM
- Developed by USACE and NMFS for USACE-permitted projects
in San Francisco and Sacramento Districts
- Intended to streamline approval of 7 types of projects via
programmatic determination of “not likely to adversely affect”
- Addresses 20 listed species, distinct population segments,
evolutionary significant units, and any designated critical habitat for these species
- Applies to certain projects that meet specific project design
criteria set forth in the NLAA Program; eligible project categories include:
- Bank Stabilization
- Boat Docks, Piers, and Wharfs
- Bridge Repair/Widening/Replacement
- Culvert Replacement/Upgrade
- Levee Maintenance
- Buoys, Floats, and Other Devices to Facilitate Mooring of
Vessels
- Pipeline Repair or Replacement
- Projects that don’t meet design criteria do not qualify for
coverage and will require separate independent consultation (either formal or informal) with NMFS
Example – 2013 USACE/NMFS NLAA Program
- NLAA Program addresses the following species:
– Fish: Chinook salmon, Coho salmon, Steelhead and Green sturgeon – Marine Mammals: Blue whale, Fin whale, Humpback whale, Sei whale, Sperm whale, Western North Pacific grey whale
- Some species (Pacific eulachon, White abalone
and Black abalone) are specifically excluded from coverage due to difficulty identifying the extent and magnitude of impacts from certain project types
- NLAA applies to three geographic regions to
account for: 1. species vulnerability to project effects 2. species-specific biological requirements 3. differences in ecological landscapes
Example – 2013 USACE/NMFS NLAA Program
Geographic Areas: Northern California Coast Central California Coast Central Valley
- Project design criteria intended to ensure projects, either individually or combined, are not likely
to adversely affect covered species and critical habitat
- Project design criteria include two types:
– Criteria that apply to all project types = standard avoidance and minimization measures – Project-specific criteria = requirements specific to each project under the approved categories
- Work windows/project timing requirements (e.g., avoidance of spawning seasons)
- Geographic restrictions (e.g., on North Coast, in SF Bay, in Central Valley)
- Methods and materials approved for use (e.g., pile driving for boat docks)
- Special notification or assistance requirements (e.g., monitoring or reporting)
Example – 2013 USACE/NMFS NLAA Program
Questions?
Presenters
Laurie Monarres Regulatory Specialist
415.321.5315
lmonarres@dudek.com David Wickens Regulatory Specialist
415.321.5314
dwickens@dudek.com Sean O’Brien Senior Biologist
415.321.5317