Use of FEA to improve the life of plant assets
Principal Sponsor
13-15 November 2018 Rotorua, NZ
the life of plant assets
How a plant saved $5M illion repair cost
13-15 November 2018 Rotorua, NZ
Use of FEA to improve the life of plant assets the life of plant - - PowerPoint PPT Presentation
Use of FEA to improve the life of plant assets the life of plant assets How a plant saved $5M illion repair cost Principal Sponsor 13-15 November 2018 13-15 November 2018 Rotorua, NZ Rotorua, NZ What is Finite Element Analysis? How do we
Principal Sponsor
13-15 November 2018 Rotorua, NZ
How a plant saved $5M illion repair cost
13-15 November 2018 Rotorua, NZ
is Finite Element Analysis?
do we use it?
use Finite Element Analysis?
Principal Sponsor
13-15 November 2018 Rotorua, NZ
do we use it?
13-15 November 2018 Rotorua, NZ
is Finite Element Analysis?
do we use it?
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
What is FEA?
Principal Sponsor
13-15 November 2018 Rotorua, NZ
Photo by Wes Hicks on Unsplash
13-15 November 2018 Rotorua, NZ
How do we use FEA?
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
How do we use FEA?
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
How do we use FEA?
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
What is FEA?
Principal Sponsor
13-15 November 2018 Rotorua, NZ
Photo by Wes Hicks on Unsplash
13-15 November 2018 Rotorua, NZ
use Finite Element Analysis?
do we use it?
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
Why use FEA?
~30% more efficient
M ore accurate Lighter, stronger, longer lasting… .
Photo by Samuel Penn on Unsplash
S pare capaci ty
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
~30% more efficient Lighter, stronger, longer lasting… . Reduce development time and cost with virtual prototypes and testing
S pare capaci ty
Issue Pitting corrosion Scope Check maximum allowable working pressure Summary Inspecvtion of an offshore pipe found an area of heavy pitting corrosion. A Level 3 Fitness For Service assessment using FEA was carried out to check allowable pressure Benefit $50,000 repair costs saved
Pitting corrosion FFS
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
Issue Weld defect Scope Check acceptability Summary Surface NDT found crack like flaws near a weld
removed by grinding. An FE analysis was carried out to determine how much material could safely be removed while maintaining current design conditions. An acceptable profile was developed and issued as a drawing to the technicians carrying out the grinding. Benefit Saving $75,000 repair costs
Local Metal Loss FFS assessment
Principal Sponsor
13-15 November 2018 Rotorua, NZ
Benefit Saving $75,000 repair costs
13-15 November 2018 Rotorua, NZ
Local Metal Loss FFS assessment
Issue Large area of localised corrosion Scope Check acceptability Summary An event caused a large area of a very high pressure flange to suffer heavy localised
prove the flange was safe due to the complex shape and loading. A Level 3 FFS assessment using FEA demonstrated the flange was still safe.
Principal Sponsor
13-15 November 2018 Rotorua, NZ
Benefit Saving $5M repair and downtime cost
13-15 November 2018 Rotorua, NZ
Dent due to rock fall FFS assessment
Issue Rockfall onto exposed pipeline Scope Determine new maximum allowable working pressure Summary This is an example case of dynamic FE analysis simulation of a large rock hitting a pipe. By approximately modelling the rock and defining its speed when it hit the pipe the simulation can predict the deformed shape of the pipe Benefit Saving $20K repair costs
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
Issue Thermocouple readings higher than expected Scope Simulate exhaust gas flow to predict thermocouple readings Summary Thermocouples in a new heat exchanger produced higher than expected readings resulting in reduced flow. CFD showed that the location and mounting of the thermocouples would give readings higher than the actual tube temperatures. The control system was recalibrated based on the CFD results enabling the flow rate restored to the design value and also
Computerised Fluid Dynamics
Principal Sponsor
13-15 November 2018 Rotorua, NZ
restored to the design value and also increasing the predicted lifespan of the heater tubes. Benefit Saving $250,000 replacement costs
13-15 November 2018 Rotorua, NZ
Issue Compressor skid package design Scope Optimise piping and supports to minimise vibration issues for a wide range of operating conditions Summary A packaged skid based around a reciprocating compressor required the piping and supports to be designed to minimise vibration and pulsations, as well as meeting standard pressure and temperature static stress requirements.
Rotating equipment
Principal Sponsor
13-15 November 2018 Rotorua, NZ
static stress requirements. Benefit Earlier entry into service reduced teething issues Saving $50,000
13-15 November 2018 Rotorua, NZ
x
The Future of Digital twins
PI TI
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ
Issue Critical flange joint Scope Create and monitor a “digital twin” of the joint Summary A digital twin of the joint was created and subjected to the actual loads applied to the real joint based on plant readings, maintenance records, manual readings weather records etc. Maintenance schedules adjusted based on predictions. Benefit $500,000 in downtime replacing gaskets
Digital twins
Principal Sponsor
13-15 November 2018 Rotorua, NZ 13-15 November 2018 Rotorua, NZ