SLIDE 1
New Build Briefing
Chris Munby – Assets and Development Manager Steve Leonard – Head of Assets and Development
SLIDE 2 The Team
- Steve – Head of Assets & Development
- Chris – Assets & Development Manager
- Mike, Nicola & Emma – Development Officers
- Amanda – Home Sales Advisor
SLIDE 3 The Development Process
- Land – privately owned and owned by the Council.
- Deciding mix and tenure.
- Procurement of contractors and consultants.
- Planning and public consultation.
- Delivery.
- Sales and Letting.
- Ownership - both SHL & the Council (HRA).
SLIDE 4 Funding New Build
- Grant funding provided by Homes and Communities
Agency.
- Remaining borrowing comes from Council.
- Rents & sales receipts repay the loan.
- Management and maintenance and major repairs
allowances are built into the financial model.
SLIDE 5 Achievements to date
- Built or acquired 315 new homes:
- Built; 163 new homes for rent.
67 new homes for shared ownership.
- Acquired; 52 homes via Mortgage Rescue.
27 empty properties. 6 buy backs.
- Enabled by securing £13m of capital grant from
HCA.
SLIDE 6
Fir Tree, Reddish
SLIDE 7
Turves Rd. Cheadle Hulme
SLIDE 8
Essex Rd. Brinnington
SLIDE 9
Prospect House, Cheadle Hulme
SLIDE 10
Berlin Rd. Edgeley
SLIDE 11 Currently on site
- 264 units currently on site;
136 new homes for rent. 128 new homes for shared ownership.
- Includes new homes via S106 agreements.
- Enabled by securing £4.8m capital grant from
HCA.
SLIDE 12
Charles St. Heaviley
SLIDE 13
Cherry Tree Hospital, Offerton
SLIDE 14
Off site manufacture – Cross Keys, Adswood
SLIDE 15 New sites for 2016-18
- Have secured £5.4m in capital grant to
deliver;
- 116 new homes for rent.
- 91 new homes for shared ownership.
- 10 new homes – L&D
- S106 sites - various
SLIDE 16
Lapwing Lane, Brinnington
SLIDE 17
- St. Thomas’ Hospital, Shaw Heath
SLIDE 18
Edwin St. Little Moor
SLIDE 19 Beyond 2018
- Funding bid submitted for 420 units for Shared
Ownership (2018-21).
- No funding available from HCA for rent.
- Therefore looking at market rent and outright
sale to subsidise new affordable rent units.
- Stockport Council Housing Company.
SLIDE 20 Summary
- The Development Process
- New Build Funding
- The Development Programme;
- Complete
- On site
- 2016-2018
- The Future;
- Drive towards Shared Ownership
- Market Rent & Outright Sale to cross subsidise Affordable
rent.
SLIDE 21
Any questions?