US 69 RELIEF ROUTE STUDY Jacksonville, Texas PUBLIC MEETING #3 - - PDF document

us 69 relief route study
SMART_READER_LITE
LIVE PREVIEW

US 69 RELIEF ROUTE STUDY Jacksonville, Texas PUBLIC MEETING #3 - - PDF document

US 69 RELIEF ROUTE STUDY Jacksonville, Texas PUBLIC MEETING #3 August 28 th 2018 US 69 Jacksonville Relief Route Study August 28 th , 2018 1


slide-1
SLIDE 1

1

US 69 Jacksonville Relief Route Study August 28th, 2018

US 69 RELIEF ROUTE STUDY

Jacksonville, Texas

PUBLIC MEETING #3 August 28th 2018

Welcome to the final public meeting for the US 69 Relief Route Study in Jacksonville. This presentation will give a recap of the information that was presented at previous public meetings held on February 22nd and May 29th of 2018, as well an overview of the process considered to determine recommended corridors. 1

slide-2
SLIDE 2

2

US 69 Jacksonville Relief Route Study August 28th, 2018

Purpose and Need

PURPOSE: PURPOSE: PURPOSE: PURPOSE:

  • Improve safety
  • Enhance freight mobility
  • Reduce travel time
  • Increase mobility
  • Improve the overall Level of Service
  • Facilitate efficient hurricane evacuation

NEED: NEED: NEED: NEED:

  • US 69 is inadequate to meet current and future traffic volumes
  • Increased travel times
  • Reduced mobility
  • Texas Highway Freight Network
  • High crash rate
  • Increased congestion and decline in efficiency during hurricane evacuations
  • An early task for the project was the development of the purpose and need for a US 69

relief route. We found that US 69 is inadequate to meet the current and future traffic volumes.

  • In the 200 miles between Tyler and Beaumont, there are 27 traffic signals on US 69 and

almost a third of them, 8, are in Jacksonville. The most congested of these 8 intersections, at Loop 456, US 79 and SH 135, are operating with severe congestion

  • The Jacksonville area is projected to have 30% population growth between 2010 to 2040,

and traffic is expected to increase similarly.

  • Additionally, US 69 is on the Texas Highway Freight Network and is expected to see an

increase in truck traffic in the future

  • In downtown Jacksonville, the crash rate along US 69 is up to 65% higher than statewide

average.

  • The purpose of the US 69 relief route will be to increase safety by reducing crashes, give

through truck traffic along US 69 an alternate route around Jacksonville, instead of forcing the trucks through downtown, reduce congestion through Jacksonville, and in turn reduce the travel time and increase mobility and make hurricane evacuation through Jacksonville more efficient. 2

slide-3
SLIDE 3

3

US 69 Jacksonville Relief Route Study August 28th, 2018

Universe of Alternative Corridors

At the second public meeting held on May 29th, 2018, the study team presented a map of the alternative corridors. That map, with all of the alternative corridors, is shown here. At the meeting, the study team answered questions and gathered comments to the study. Additionally, people were encouraged to highlight their preferred route, if they had one, and submit that as a comment to the study team. 3

slide-4
SLIDE 4

4

US 69 Jacksonville Relief Route Study August 28th, 2018

TRAFFIC ANALYSIS – Truck Traffic

Truck Traffic on Relief Route – Western Alternatives

1,050 trucks 700 trucks 900 trucks 575 950 875 125 100 25 No Improvements Relief Route Projection

  • As a part of our traffic analysis, we looked at the number of trucks that would potentially

use the relief route, and in doing so, reduce the number of trucks driving through downtown on US 69

  • Looking at the projected traffic for 2040, the left side shows the total number of trucks,

including both northbound and southbound traffic, that would be traveling through Jacksonville on US 69 if no relief route was built.

  • If nothing is done we project 700 trucks per day using US 69 north of US 175, 1,050

trucks between US 175 and US 79, and 900 trucks south of US 79.

  • If a relief route was constructed on the western side of Jacksonville, our projections show

that 575 trucks per day would use the relief route from US 69 to US 175, with 125 still using US 69

  • From US 175 to US 79, 950 trucks would use the relief route, leaving 100 trucks using US

69

  • And from US 79 to US 69 to the south, 875 trucks would use the relief route, leaving only

25 trucks per day on US 69. 4

slide-5
SLIDE 5

5

US 69 Jacksonville Relief Route Study August 28th, 2018

TRAFFIC ANALYSIS – Truck Traffic

Truck Traffic on Relief Route – Eastern Alternatives

575 550 125 475 350 900 trucks 700 trucks 1,050 trucks No Improvements Relief Route Projection

  • If a relief route was constructed on the eastern side of Jacksonville, our projections show

that 575 trucks per day would use the relief route from US 69 to US 79, with 125 still using US 69

  • From US 175 to US 79, 475 trucks would still use US 69
  • And from US 79 to US 69 to the south, 550 trucks would use the relief route, leaving 350

trucks per day on US 69. 5

slide-6
SLIDE 6

6

US 69 Jacksonville Relief Route Study August 28th, 2018

Factors Considered

  • Meets All Aspects of Purpose and Need
  • Potential Environmental Impacts
  • Parks
  • Cemeteries
  • Affected Structures
  • Cultural Resources
  • Wetlands
  • Floodplain
  • Farm Soils
  • Streams
  • Hazardous Material Sites
  • Historical
  • Environmental Justice
  • Public Opinion
  • Cost
  • To help us determine if a corridor should be brought forward for further study in the next

phase of the project, we scored the corridors using several factors.

  • First, was whether or not the corridor met all aspects of the purpose and need
  • Next, we looked at the potential environmental impact of each 1,000-foot corridor.

These include potential impacts to: parks, cemeteries, residential and other structures, cultural resources, wetlands, floodplains, farmland, streams, hazardous material sites, potential historical sites and markers, and low income and minority population areas.

  • Following that, we gauged public opinion based on comments that were submitted to the

team, as well as tallying the preferred routes that were highlighted and submitted to the team.

  • Finally, we looked at the potential construction costs for each corridor.
  • We then ranked the corridors based on their scores in each of the four categories;

purpose and need, potentially adverse environmental impacts, public opinion and construction cost. 6

slide-7
SLIDE 7

7

US 69 Jacksonville Relief Route Study August 28th, 2018

Recommended Corridors

We averaged the rankings and made the determination that it is appropriate to bring the top two ranked corridors forward for further study. These two corridors are both on the west side of Jacksonville. They both tie-in to US 69 south of Craft, the turn north near Gum Creek. The two corridors diverge northwest of Jacksonville., with the southern corridor tying into US 69 near Love’s Lookout, and the other recommended corridor tying into US 69 about 1.5 miles further north. We have also included the connection to US 69 along Loop

  • 456. This connection would use the existing corridor and promote connectivity to the Loop east of

US 69. In general, public opinion that was expressed during the May 29th Open House comment period was evenly divided between western and eastern corridors. However, each of the western corridors better addressed the purpose and need for the project by enhancing freight mobility through the greater number of trucks forecasted to use the facility. The western corridors also better addressed the purpose and need through the greater facilitation of hurricane evacuation due to the connection to US 175. The recommended corridors both ranked at the top for the least amount of potentially adverse environmental impacts The combination of these factors is what brought these two corridors forward to be considered for further study. The corridors shown here, and in the exhibits in the main room, show 1,000-foot corridors. The 1,000-foot width is for this analysis only. As the project moves forward, analysis will be done on narrower alignments within the corridors, with a typical width of 400-feet. These alignments will be developed to avoid and minimize potential impacts.

7

slide-8
SLIDE 8

8

US 69 Jacksonville Relief Route Study August 28th, 2018

Project Development Process

Route Route Route Route Study Study Study Study

  • Purpose and Need
  • Environmental

Resources

  • Corridor Option

Locations

  • Corridor Evaluation
  • Public Input
  • Possible

Identification of Recommended Corridor(s)

Schematic Design & Schematic Design & Schematic Design & Schematic Design & Environmental Study Environmental Study Environmental Study Environmental Study (2 (2 (2 (2-

  • 3 Years)

3 Years) 3 Years) 3 Years)

  • Build and No-Build/

Alternatives Analysis

  • Schematic

Development

  • Environmental

Effects

  • Public Input
  • Environmental

Decision

  • Offers and

Negotiations with Property Owners

  • Right-of-Way

Acquisition

  • Utility Relocations
  • Detailed Design
  • Plans, Specifications

and Estimates

  • Bid Ready

Construction Construction Construction Construction (3 (3 (3 (3-

  • 5 Years)

5 Years) 5 Years) 5 Years)

  • Contract Award
  • Construct Facility
  • Open to

Operations

We Are Here The Project Development Process timeline shown is The Project Development Process timeline shown is The Project Development Process timeline shown is The Project Development Process timeline shown is approximate and based on available funding. approximate and based on available funding. approximate and based on available funding. approximate and based on available funding.

Right Right Right Right-

  • of
  • f
  • f
  • f-
  • Way Acquisition,

Way Acquisition, Way Acquisition, Way Acquisition, Utility Relocations, and Utility Relocations, and Utility Relocations, and Utility Relocations, and Final Design Final Design Final Design Final Design (2 (2 (2 (2-

  • 3 Years)

3 Years) 3 Years) 3 Years)

  • Following this meeting, the study team will prepare the final report. This report will

serve as the conclusion for the route study phase of the project.

  • The next stage would be the schematic design and environmental study. This phase can

last from 2 to 3 years, and includes the preliminary design of the facility.

  • Following environmental clearance of the project, assuming that funding is identified, the

final design would begin. This phase, which also includes right-of-way acquisition and utility relocations, can take from 2 to 3 years.

  • Once the facility has been designed, right-of-way is acquired and utilities are cleared,

construction can begin. We estimate that construction of this facility would last from 3 to 5 years. 8

slide-9
SLIDE 9

9

US 69 Jacksonville Relief Route Study August 28th, 2018

US 69 RELIEF ROUTE STUDY

Jacksonville, Texas

PUBLIC MEETING #3 August 28th , 2018

This concludes the presentation. Thank you for attending the US 69 Relief Route Study public meeting. In the main room, you will find maps with the recommended corridors and project team members that can answer your questions. Each of the tables in the main room has the same information on it, so please go to whichever table you prefer. Please remember that comments to the project can be made via comment card or email. Have a safe and enjoyable evening. 9