Update on Wastewater Efforts In Barnstable Department of Public - - PowerPoint PPT Presentation

update on wastewater efforts in barnstable
SMART_READER_LITE
LIVE PREVIEW

Update on Wastewater Efforts In Barnstable Department of Public - - PowerPoint PPT Presentation

Barnstable Town Council Update on Wastewater Efforts In Barnstable Department of Public Works January 23, 2020 1 Town of Barnstable, Department of Public Works Update Since December Update Since December Finalized the Draft CWMP


slide-1
SLIDE 1

Town of Barnstable, Department of Public Works

1

Barnstable Town Council

Update on Wastewater Efforts In Barnstable

Department of Public Works January 23, 2020

slide-2
SLIDE 2

Town of Barnstable, Department of Public Works

Update Since December Update Since December

  • Finalized the Draft CWMP
  • Submit Draft CWMP to MEPA

– Expanded Environmental Notification Form (EENF) was submitted on January 15, 2020 – Mill Pond Dredging and other non-traditional projects may be handled as a notice of project change (NPC) to the CWMP. – Keys upcoming dates are:

  • Publication in the Environmental Monitor: 2/10/20
  • ENF Comments Due: 3/2/20
  • ENF Decision, EIR Comments: 3/12/20
  • EIR process begins thereafter, timeline will be dependent

upon comments received.

2

slide-3
SLIDE 3

Town of Barnstable, Department of Public Works

3

slide-4
SLIDE 4

Town of Barnstable, Department of Public Works

4

Non-traditional Focus Area – Three Bays Non-traditional Focus Area – Three Bays

Non-traditional methods.

  • Cotuit Bay Inlet Dredging
  • Mill Pond dredging
  • Abandoned cranberry

bogs conversion

  • Warren’s Cove -

aquaculture

  • Alternative septic systems
  • Permeable Reactive

Barriers (PRBs)

  • Stormwater treatment
slide-5
SLIDE 5

Town of Barnstable, Department of Public Works

5

Sampson’s Island Dredging Sampson’s Island Dredging

slide-6
SLIDE 6

Town of Barnstable, Department of Public Works

6

Sampson’s Island Dredging Sampson’s Island Dredging

slide-7
SLIDE 7

Town of Barnstable, Department of Public Works

Mill Pond Dredging Mill Pond Dredging

  • The Issue:

– Mill Pond is full of silt and debris – 9 feet thick in places – In 20 years nitrogen removal capacity has declined from 20% to 10% – Healthy ponds = 30% to 50% – If 50% restored, estimated remove over 2,200 kg/year of additional nitrogen

  • The Solution:

– Dredge to its original depths (sand layer) and perimeter – Estimated 30,000 CYs of material (to be confirmed) – Pond depths restored to approximately 8 feet in the deepest areas

  • Nest Steps

– Once CWMP approved by MEPA, NPC will be submitted for Mill Pond

7

slide-8
SLIDE 8

Town of Barnstable, Department of Public Works

Cranberry Bogs Cranberry Bogs

  • The Issue:

– Existing and abandoned bogs - Ideal locations for nontraditional solutions

  • The Solutions:

– Effort led by BCWC – Conversion to ponds (~50%) – Conversion to wetlands (TBD) – Installation of floating wetlands (8- 15%)

  • Next Steps:

– BCWC working with the Town, EPA, UMASS, and Land Owners to pilot potential solutions

8

slide-9
SLIDE 9

Town of Barnstable, Department of Public Works

  • The Issue:

– Currently not appropriate for aquaculture due to silt. – Potential to be nursery for aquaculture farms – The product relocated to established aquaculture farms

  • The Solution:

– Dredging Warrens Cove back to a sandy bottom – Establish aquaculture nurseries

  • Variety of species

– The Cape Cod Commission estimated that aquaculture beds/floating racks can remove 8-15% of the nitrogen they encounter

  • Next Steps:

– Sampling efforts – Meet with regulatory agencies – Permitting

9

Warrens Cove Warrens Cove

slide-10
SLIDE 10

Town of Barnstable, Department of Public Works

10

slide-11
SLIDE 11

Town of Barnstable, Department of Public Works

Other Non-traditional Opportunities Other Non-traditional Opportunities

  • PRBs

– EPA Demonstration Project

  • Prince Cove Area

– Horse Farms?

  • Alternative Septic

Systems

– Prince Cove – BCWC efforts at Shubael Pond

  • Alternative Toilets

11

slide-12
SLIDE 12

Town of Barnstable, Department of Public Works

Stormwater Stormwater

  • The Issue:

– Stormwater systems are in various states of repair

  • The Solution:

– A comprehensive survey identifying those that need repair, or replacement. – Identify new systems/BMP needed to protect water quality – Credit for work already done

  • Cotuit Town Dock, etc.

12

slide-13
SLIDE 13

Town of Barnstable, Department of Public Works

Next Steps Next Steps

  • Ongoing public outreach as requested
  • Staffing Discussions to implement the plan

– Preliminary Design in house – Final Design by consultants – Construction Administration (CA) and Inspection in-house with some consultant support – WPCF design, CA, and inspection by consultants

  • Continuing preliminary design of traditional

projects that are underway

  • Permitting efforts
  • Continuing to meet with Vineyard Wind

regarding the Strawberry Hill Road Project and Phase II

13

slide-14
SLIDE 14

Town of Barnstable, Department of Public Works

Discussion? Discussion?

14