unithai shipyard presentation introduction
play

UNITHAI SHIPYARD PRESENTATION Introduction: The Unithai Group - PowerPoint PPT Presentation

UNITHAI SHIPYARD PRESENTATION Introduction: The Unithai Group represents the Thai arm of the IMC Pan Asia Alliance Group, a regional organization with primary business interests in shipping, distribution, logistics, engineering and


  1. UNITHAI SHIPYARD PRESENTATION

  2. Introduction: • The Unithai Group represents the Thai arm of the IMC Pan Asia Alliance Group, a regional organization with primary business interests in shipping, distribution, logistics, engineering and infrastructure development. • Unithai’s operations in Thailand include shipping services, a container terminal, a logistics based distribution centre and the largest shipyard in Thailand (UTSE). • UTSE Incorporated in 1990 as a PLC and started operations in 1993 • 3 main activities, supported by a centralized supporting function: Shipyard Business Division (SBD) Marine Onshore & Offshore Service Division (MOS) Offshore Fabrication Division (OFD) • Our corporate mission is to create sustainability as the shipyard partner of choice • UTSE exists to provide quality shiprepair, conversion, newbuilding, services and onshore/offshore fabrications to customers worldwide. We work closely and in partnership with customers to determine their needs and to satisfy their requirements on time and at competitive costs 2

  3. UTSE Qualification: 3

  4. UTSE LOCATIONS: Operate in 2 Strategic Locations o Laem Chabang Yard • Workshop • Bonded Warehouse • Fabrication area • Load out jetty Leam Chabang Songkhla Yard • Warehouse • Workshop • Offshore tool / equipment Songkhla • Supply base • Jetty 4

  5. UTSE Key Facilities: 2 Special Project Marine Business 3 1 Unithai JV Business (CUEL) Unithai Fabrication Business Fabrication Area / Assemble Area Ship repair and conversion Total yard area 693,000 m2 5

  6. SBD Key Facilities: Repair Jetty 190 m. Workshop Repair Quay 390 m. Floating Dock 2 13,500T Lifting Floating Dock 3 48,000T Lifting Developing Quay 315 m. Depth 14 mtr Shore crane 30T 6

  7. SBD Key Facilities: • 2 Floating docks • 390 meters quay with 45 tonnes shore crane • Extension quaywall 315 mtr (under process) • 190 meters jetty/quay • 6-7 meters (MSL) water depth. • 100 tonnes floating crane • Painting booth for steel work Repair Facilities • 7,500 sqm of covered workshops • 3,750 sqm mechanical, electrical • 3,750 sqm steelwork pre- fabrication Unithai 3 Unithai 2 shop, equipped with optical plate Suphannica Chompoophukha profilers, overhead cranes (up to 32 Lifting cap. (tons) 48,000 13,500 tonnes), break press, bending rolls, LOA (m) 300 190 automatic pipe benders & thin plating Breadth (m) 52 34.4 equipment Docking Draft (m) 7.0 5.5 7

  8. SBD Activities: Services Vessels Value • • • Steel repair / Modification Container / Bulker / Tanker Reliable / Experience • • • Accommodation work Car carrier / Reefer Commitment / On time • • • Tank coating / Hull coating Cruise ship Price competitive • • • Machinery / piping / valves Royal Thai Navy / US Navy Customer oriented • • • Tail shaft work / CPP work LPG Available spare part • • Engine overhaul Dredger • • Cargo gear repairs and testing Derrick Lay Barge • • Automation / Motor/ generator repair Air Craft carrier • • Pneumatics / hydraulic / electronic. Offshore Tender barge • • Afloat Repair Offshore tug 8

  9. SBD Activities: • Steel Repair/Renew • Full blasting and Silicon coating • Propulsion System Services • Main Engine Repair & Overhaul • Reconditioning Services • E & I, Navigation and Communication Services • Boiler Services • Dynamic Balancing all parts 9

  10. SBD Activities: Ballast Water Management System (BWMS) Ballast Water Management system Makers in cooperation with Unithai Approval of BWMS G8 Substance Substance Cappacity of (MEPC174(58)) Approval Maker BWMS Name Country Process IMO Basic IMO Final approval given by the Approval Approval Administration Alfa-Laval AB PureBallast Sweden Filtration + UV/T 250 - 3,000 ㎥ /h Approved Approved Approved Optimarin Ballast Optimarin AS System Norway Filtration + UV 21 - 5,400 ㎥ /h N/A N/A Approved JFE Engineering Filtration + Chlorination + 17.5 - 4,500 ㎥ /h Approved Corporation JFE BallastAce Japan Cavitation Approved Approved TECHCROSS INC Electro-Cleen System Korea Electrolysis/Electroc hlorination 300 ㎥ /h Approved Approved Approved 125 - 4,000 ㎥ /h Approved Kuraray Co., Ltd. MICROFADE Japan Filter + Calcium hypochlorite Approved Approved MIURA Co., Ltd. Miura BWMS Japan Filter + UV 200 - 6000 ㎥ /h N/A N/A Approved SUNRUI BalClor China Filtration/Electrolysis 170 , 8,500 ㎥ /h Approved 10

  11. Ship Repair Customer: 11

  12. MOS: Facilities and Service Activities Range of Services • Engineering Services / 3D Scan camera • Brownfield Maintenance Project • Brownfield Modification / Upgrading Project • Manpower Supply • Equipment Supply • NDT • Scaffolding • ASME Tank repair (U, U2, R stamp) • Supply Base / Warehouse • Services Songkhla’s Yard Facilities • Total area 6,666 M2 • Jetty 1 length 60 m • Jetty 2 length 30 m • Water dept4.5 m • Docking area2,900 m2 • Accommodate 12 vessel/ time • Warehouse800 m2 • Storage area 900 m2 • Work shop 350 m2 12

  13. MOS: Facilities and Service Activities 13

  14. MOS: Selected Service Record Refurbishment Oct 2014 - Mar 2015 Works Scope • Major Refurbishment works – hull structures, – machinery, – Electrical – navigational eqpt., – surface treatment, – etc. • Bow & Forecastle Deck modifications • Metering Skid Installation & Integration works Name : FPSO Rubicon Vantage Project : Produced Water Built : 1987 Debottlenecking LOA - 230.18m Location : Bualuang Field LBP - 223.00m Platform : “A” & “B” PW DBN Breadth - 32.40m GRT - 45,150 Tons Owner: OPHIR Refurbishment Work Scope: epC Oct 2014 - Mar 2015 - New equipment installation - Pipe - Electrical & Instrument 14 - Scaffolding

  15. MOS: Selected Service Record US Navy Esso Refinery Project : Voyarge Service (VR) Tank Repair & Maintenance period for Maintenance and Service Pipe Valve and Structure Repair & Maintenance 15

  16. OFD Business: OFD , specializes in the fabrication of steelwork for a wide range of markets and applications. Serving customers on the worldwide basis, activities undertaken include engineering, shop drawing, material supply, fabrication, painting and erection (where required) of steel structures for infrastructure development, power generation, industrial buildings, and offshore structures OFD Capabilities OFD Business includes • Engineering / Procurement • PAR / PAU • • Construction /Quality control Skids Modules • Pre-Commissioning • Offshore Structure • Manpower up to 8 million manhr per annum • Wind Farm Structure • 20,000 Tons per annum • Prefabrication Work • Cryogenic/LNG Tank 16

  17. OFD: Facilities 17

  18. OFD: Facilities Workshop 1 Workshop 2 Workshop 3 Workshop 4 18

  19. OFD: Products: PAR / PAU Offshore Construction Windfarm Structure Prefabrication Work Cryogenic/LNG Tank 19

  20. OFD: Load out Capacity • Load – out Jetty no.1: 30 m wide for 4,500 T integrated components. • Load – out Jetty no.2: 30 m wide for 7,500 T integrated components. • Load – out Jetty no.3: Vessel LOA 100 m – 300 m. • Ground Load: 10 Ton / Sq.m. (Tested up to 30 T / Sq.m.) • Minimum water at low tide is 5.5 – 6.0 m. and normal tide variation is 2.32 m. Water Depth: • SPMT: Maximum Wheel load of SPMT is 36 T / 2.4 m. = 14 T / m Bulk head jetty design capacity is 18.2 T / m 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.