UFGS 32 13 14 Airfield Concrete Mix Design LESSONS LEARNED
By: Richard L. Allen, PE BOWSER-MORNER, INC.
UFGS 32 13 14 Airfield Concrete Mix Design LESSONS LEARNED By: - - PowerPoint PPT Presentation
UFGS 32 13 14 Airfield Concrete Mix Design LESSONS LEARNED By: Richard L. Allen, PE BOWSER-MORNER, INC. AGGREGATE QUALIFICATION ISSUES It can be difficult to identify aggregates that meet UFGS 32 13 14 in some regions. Aggregate
By: Richard L. Allen, PE BOWSER-MORNER, INC.
UFGS 32 13 14 in some regions.
requirements will meet UFGS 32 13 14 Table 5.
problems in sourcing aggregates. Large coarse aggregates tend to have more issues with ASR-deleterious materials than smaller sizes (i.e. #57s, #67s) due to less beneficiation during production.
materials.
appropriate.
Sampling ± 2 days ASTM C666A Freeze/Thaw Durability ± 90 days ASR Rapid Mortar Bar ± 35 days ASR Mitigation Trials ± 35 days UFGS 32 13 14 Table 5 Deleterious Exam ± 30 days ASTM C33 Full Quality Analysis ± 30 days
TIME REQUIREMENTS: The time requirements for mix review and approval also need to be considered.
± 2 days
± 2 days
± 7 days
± 14 days
± 90 days
± 2 days
Qualify Aggregate First, then run Mix Designs
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
1 2 3 4 5 6 1 2 3 4 1 1 2 3 4 6 7 8 9 10 11 12 13 5 6 7 8 9 10 11 2 3 4 5 6 7 8 7 8 9 10 11 12 13 14 15 16 17 18 19 20 12 13 14 15 16 17 18 9 10 11 12 13 14 15 14 15 16 17 18 19 20 21 22 23 24 25 26 27 19 20 21 22 23 24 25 16 17 18 19 20 21 22 21 27 28 29 30 26 27 28 29 30 31 23 24 25 26 27 28 29 28 30 31
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
3 1 7 5 2 4 10 8 14 6 12 3 9 11 17 15 21 13 19 10 16 18 24 22 28 20 26 17 23 25 29 27 24 30
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
6 6 3 1 7 13 7 13 4 10 2 8 14 20 14 20 11 17 9 15 21 27 21 27 18 24 16 22 28 28 25 31 23 29 30 31
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
5 1 2 3 1 2 3 4 5 6 7 1 2 3 4 6 12 4 5 6 7 8 9 10 8 9 10 11 12 13 14 5 6 7 8 9 10 11 13 19 11 12 13 14 15 16 17 15 16 17 18 19 20 21 12 13 14 15 16 17 18 20 26 18 19 20 21 22 23 24 22 23 24 25 26 27 28 19 20 21 22 23 24 25 27 33 25 26 27 28 29 30 31 29 30 31 26 27 28 29 30
June 2020 July 2020 August 2020 September 2020
AGGREGATE TESTING & MIX DESIGN TESTING AGGREGATE TESTING & MIX DESIGN TESTING AGGREGATE & MIX DESIGNS AGGREGATE TESTING AGGREGATE TESTING AGGREGATE TESTING PRODUCTION PAVING
February 2021 March 2021 April 2021
MIX DESIGN REVIEW & ACCEPTANCE PLANT SET-UP PLANT CERTIFICATION MIX DESIGN TESTING & REPORT
June 2021 July 2021 August 2021 September 2021 May 2021
TRIAL BATCHING & UNIFORMITY TEST STRIP
October 2020 November 2020 December 2020 January 2021
Begin trial batching as soon as Table 5 Deleterious and ASTM C33 Results are done. (RISKIER)
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
1 2 3 4 5 6 1 2 3 4 1 6 7 8 9 10 11 12 13 5 6 7 8 9 10 11 2 3 4 5 6 7 8 7 13 14 15 16 17 18 19 20 12 13 14 15 16 17 18 9 15 14 20 21 22 23 24 25 26 27 19 20 21 22 23 24 25 16 22 21 27 28 29 30 26 27 28 29 30 31 23 29 28 30 31
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
3 1 7 5 2 4 10 8 14 6 12 3 9 11 17 15 21 13 19 10 16 18 24 22 28 20 26 17 23 25 29 27 24 30
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
6 6 3 1 7 13 7 13 4 10 2 8 14 20 14 20 11 17 9 15 21 27 21 27 18 24 16 22 28 28 25 31 23 29 30 31
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa
5 1 2 3 1 2 3 4 5 6 7 1 2 3 4 6 12 4 5 6 7 8 9 10 8 9 10 11 12 13 14 5 6 7 8 9 10 11 13 19 11 12 13 14 15 16 17 15 16 17 18 19 20 21 12 13 14 15 16 17 18 20 26 18 19 20 21 22 23 24 22 23 24 25 26 27 28 19 20 21 22 23 24 25 27 33 25 26 27 28 29 30 31 29 30 31 26 27 28 29 30
June 2020 July 2020 August 2020 September 2020
AGGREGATE TESTING AGGREGATE TESTING
October 2020 November 2020 December 2020 January 2021
AGGREGATE TESTING AGGREGATE TESTING MIX DESIGN TESTING MIX DESIGN TESTING MIX DESIGN TESTING
February 2021 March 2021 April 2021 May 2021
MIX DESIGN TESTING & REPORT MIX DESIGN REVIEW & ACCEPTANCE PLANT SET-UP TRIAL BATCHING & UNIFORMITY PLANT CERTIFICATION TEST STRIP
June 2021 July 2021 August 2021 September 2021
PRODUCTION PAVING
Recommendations: 1) Obtain aggregate gradation data for previous ± 6 months (CA & FA)
2) Use the average gradations for aggregate blending calculations and for calculating the Coarseness Factor (CF) and Workability Factors (WF) for the mix. 3) Use the min/max data from recent gradations to check likely range of aggregate variation during the project. This can give you insight into what type of mix variability you can expect during the project.
Min/Max Aggregate Data can be used to predict likely range of variations during project
This approach allows you to tailor (to some degree) mix properties to fit planned methods of placement. Need 2 or 3 Coarse Aggregates for Maximum Flexibility
“Tarantula” Curve
LOW POINT MID POINT HIGH POINT 3 Mixes x 6 break dates x 6 samples per break result in 108 samples and 18 different batches
re: Supplementary Cementitious Materials for ASR Control Fly Ash
Lithium Nitrate
Natural Pozzolans
CONDUCT PRE-PRODUCTION BATCHING TO VERIFY MIX PROPERTIES. Do not assume that mixes will perform the same in regular production as they did in the laboratory setting!
You will need to adjust mixing times, admixture dosages and air adjustments to adapt the trial mix for field purposes.
Do not wait until the day of the test lane placement to figure this out!
When adjusting for air and slump, always put all of the design mix water in, then adjust admixtures. Failure to include all of the design mix water will result in: 1. Surfaces that are stickier and more difficult to finish. 2. Wide fluctuations in test results. 3. Non-predictable strength performance (you’ve changed the mix from what was designed). Only change the water content with the designer’s knowledge and approval.
The loader operator at the batch plant will have a significant impact, for better or for worse, on the success of the project.
CF and WF ratios are controlled by a very small portion of the aggregate, so getting representative samples is a critical process.
It is possible for individual aggregate gradations to be within specification limits, but for CF & WF to vary
GRADATION CHANGES
If aggregate gradation results cause CF and WF to vary outside project limits, the specification requires you to re-adjust aggregate proportions. RECOMMENDATION
field, don’t make knee-jerk adjustments on the basis of a single outlying gradation result.
samples.
specimens is CRITICAL.
etc.) be performed? Is the technician qualified and experienced at running these tests?
Unusually high strength test results should be investigated. Production test results should typically not vary more than 15% or so from the mix design results.
are encountered.
200 400 600 800 1000 1200 2000 4000 6000 8000 10000 Flexural Strength (psi) Compressive Strength (psi) Outliers Outliers
Richard L. Allen, P.E. rallen@bowser-morner.com