FORMER GROVE AIRFIELD Introductions Chris Minors Rebecca Sanders - - PowerPoint PPT Presentation

FORMER GROVE AIRFIELD Introductions Chris Minors Rebecca Sanders Damon Buckle Senior Planning Manager Design Manager Associate Director Persimmon Homes Persimmon Homes Jubb Consultancy Contents Development proposals Phasing and


slide-1
SLIDE 1
slide-2
SLIDE 2

FORMER GROVE AIRFIELD

Introductions Chris Minors Rebecca Sanders Damon Buckle Senior Planning Manager Design Manager Associate Director Persimmon Homes Persimmon Homes Jubb Consultancy Contents

  • Development proposals
  • Phasing and key infrastructure provision
  • Indicative development programme
  • First detailed infrastructure application
  • First detailed residential application
slide-3
SLIDE 3

FORMER GROVE AIRFIELD

Proposals

  • 2,500 dwellings
  • Secondary school
  • Primary schools
  • Local centre
  • Open space including community park
  • Realignment of Denchworth Road to the south
  • Sports pitches and pavilion
  • Equipped play areas
  • Strategic landscaping and ecological park
  • Allotments
slide-4
SLIDE 4

FORMER GROVE AIRFIELD

slide-5
SLIDE 5

FORMER GROVE AIRFIELD

Triggers and Obligations (relating to first residential parcel)

  • Prior to commencement provide a live information website

about the progress of the development

  • Prior to commencement notify the county council if the primary

school will be directly delivered or land / funding provided

  • Early delivery of 1 football pitch, temporary changing facilities /

car park @ 50 occupations

  • Local Equipped Area of Play to be provided @ 150 occupations
  • Secondary School site to be offered prior to 150 occupations
slide-6
SLIDE 6

FORMER GROVE AIRFIELD

Indicative Programme 2017/18 Permission Granted

Pre-commencement & Occupation Conditions and Obligations Discharged

Infrastructure Application Submission First Residential Parcel Application Submission Commencement First Occupation 17th July 2017 31st August 2017 30th September 2017 Spring 2018 Winter 2018 Approval December 2017 Approval January 2018

slide-7
SLIDE 7

FORMER GROVE AIRFIELD

First Infrastructure Application

  • Access arrangement to serve initial residential parcels
  • Surface water drainage strategy
  • Foul water drainage strategy
  • Street lighting
  • Tracking and visibility
  • Landscaping proposals
  • End of August submission
  • Anticipated that work will commence early 2018
slide-8
SLIDE 8

FORMER GROVE AIRFIELD

slide-9
SLIDE 9

FORMER GROVE AIRFIELD

slide-10
SLIDE 10

FORMER GROVE AIRFIELD

slide-11
SLIDE 11

Questions?

FORMER GROVE AIRFIELD

slide-12
SLIDE 12

FORMER GROVE AIRFIELD

Website

  • News
  • Construction
  • Planning submissions
  • Consultation
  • Masterplan
  • Infrastructure proposals
  • Residential proposals
  • Community
  • Education
  • Leisure
  • Transport…