UCSF Academic and Research Building at Zuckerberg San Francisco General Hospital and Trauma Center Paul Jenny Senior Vice Chancellor Finance and Administration University of California, San Francisco September 19, 2017 By continually


slide-1
SLIDE 1 September 19, 2017

Paul Jenny Senior Vice Chancellor Finance and Administration University of California, San Francisco

UCSF Academic and Research Building at Zuckerberg San Francisco General Hospital and Trauma Center

slide-2
SLIDE 2

By continually advancing healthcare for the most serious conditions, UCSF research conducted at Zuckerberg San Francisco General Hospital and Trauma Center has improved the lives of countless patients and families in our city. The new research and academic building will nurture powerful new collaborations by bringing all of our physician-researchers under one roof, in up-to-date facilities, while keeping them close to the patients who are their top priority.”

Sam Hawgood, MBBS Chancellor, UCSF

UCSF Academic and Research Building at the Zuckerberg San Francisco General Campus September 19, 2017 Health Commission Meeting
slide-3
SLIDE 3 UCSF Academic and Research Building at the Zuckerberg San Francisco General Campus September 19, 2017 Health Commission Meeting

UCSF’s Academic and Research Building and Site Improvements: Conceptual Site Plans

slide-4
SLIDE 4 UCSF Academic and Research Building at the Zuckerberg San Francisco General Campus September 19, 2017 Health Commission Meeting
slide-5
SLIDE 5 UCSF Academic and Research Building at the Zuckerberg San Francisco General Campus September 19, 2017 Health Commission Meeting
slide-6
SLIDE 6

Start Procurement of Design and Construction Team October 2017 Regents Approval of Project Budget and Design Fall 2018/Winter 2019 Road Improvements Construction Start Winter 2019 Complete Fall 2019 New Building Construction Start Fall 2019 Complete Summer 2021 Move-in Fall 2021

Draft Timeline for UCSF’s Academic and Research Building and Site Improvements

UCSF Academic and Research Building at the Zuckerberg San Francisco General Campus September 19, 2017 Health Commission Meeting