TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL Introduction / Roles - PowerPoint PPT Presentation

TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL Introduction / Roles Similar Experience Timeline MSBA Process WSBC Role MSBA Reimbursement Designer Selection SBC Kick-off | June 6, 2019 One Edgewater Drive, Suite 204 |


  1. TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL • Introduction / Roles • Similar Experience • Timeline • MSBA Process • WSBC Role • MSBA Reimbursement • Designer Selection SBC Kick-off | June 6, 2019 One Edgewater Drive, Suite 204 | Norwood, MA 02062 | 508.589.5061 | www.compasspminc.com

  2. INTRODUCTION/ROLES TOWN OF WESTWOOD | PAUL HANLON ELEMENTARY SCHOOL FEASIBILITY/DESIGN PHASE Timothy Bonfatti Project Director Bryan Christopher Jarvis Kenney Project Senior Project Executive Manager CONSTRUCTION PHASE Brian Kelley Vice President Emily Bryan Christopher Sarazin Jarvis Kenney Construction Project Senior Project Site Manager Executive Manager

  3. ELEMENTARY SCHOOL EXPERIENCE HUNNEWELL ELEMENTARY SCHOOL, HARDY/ UPHAM ELEMENTARY SCHOOL, Wellesley Wellesley • Redistricting / Consolidation Options • Swing Space Analysis • Historically Sensitive Considerations • Extensive Site Constraints • Focus on Sustainability • Significant Public Engagement • K-5 Neighborhood Schools • Net Zero Energy Ready

  4. ELEMENTARY SCHOOL EXPERIENCE FIELD ELEMENTARY SCHOOL, Weston MARATHON ELEMENTARY SCHOOL, Hopkinton • Upper Elementary • Extensive Options Analysis • Congested Campus – 3 Other Schools • Reviewed Four (4) Separate Sites • Built on Sloped Site • Expanded School During Construction • Extensive Daylighting • 2 Months Ahead of Schedule & $4M Under Budget

  5. APPROACH TIMELINE Community Forum Start Complete Submit OPM Submit Construction DD SD Report Approval PDP 09/19 04/20 08/21 10/20 01/20 08/20 02/21 Town Mtg Complete Designer Submit 06/19 10/21 Ballot Vote CD Selection PSR PDP: Preliminary Design Plan | PSR: Preferred Schematic Report | SD: Schematic Design Report

  6. MSBA Process – Feasibility / SD Phase Preliminary Design Program (PDP) Preferred Schematic Report Schematic Design Report • Schematic Design (30%) • • Educational Program Evaluation of Existing • Final Design Program Conditions • Traffic Analysis • Initial Space Summary • Environmental Assessment • Final Evaluation of • Geotechnical • Evaluation of Existing Alternatives • Code Analysis Conditions • Sustainability • Preferred Solution • ADA / MAAB Analysis • Site Development Requirements • Room Data Sheets • Project Delivery System • Preliminary Evaluation of • Construction Estimates Alternatives • Total Project Budget • Maximum Reimbursement • Project Schedule

  7. WSBC – Responsibility Matrix - FS Deliverable Review/ Vote Time Comment Comment Frame* Q1, Q2, Q4 MSBA Submissions X Design Alternatives X Q1 Education Plan / Space X Q1 SC Vote Summary Sustainability Approach X Q2 Evaluation Criteria X Q1 Shortlist of Options X Q1 Instructional Technology X Q3 SC Vote Project Budget / Schedule X Q3 Community Outreach X Design Elements X Q2 Final Preferred Option X Q2 *assumes Designer Selected 10/19 – all time frames 2020

  8. MSBA Process – Reimbursement MSBA Cost t Caps s / Ex Exclu lusion sions The MSBA has several types of costs which are ineligible for reimbursement. They fall into three general categories. • Categorically Ineligible – Costs that are not core to the educational program – Costs for items that are not part of the permanent building and grounds – costs beyond the project scope • Costs that Exceed MSBA Caps • Costs for Spaces that Exceed Guidelines (sometimes) – Costs for spaces that are eligible but exceed the MSBA guidelines and not approved by MSBA staff

  9. MSBA Process – Reimbursement MSBA Cost t Caps s / Ex Exclu lusion sions The following costs are categorically ineligible for reimbursement • Land Acquisition • Legal Fees • Off site Improvements • Synthetic Turf; Spectator Amenities; Stadiums • Utility Company Charges • Swing Space • Building Permits / Local Board Costs • Financing Costs • Site Remediation • Asbestos Containing Floor Tiles • Auditorium (although a cafetorium would be eligible)

  10. MSBA Process – Reimbursement MSBA Cost t Caps s / Ex Exclu lusion sions Costs that exceed the following caps are ineligible ‣ Soft t Costs exceedi ding ng 20% of constructi ruction on costs ‣ OPM costs ts exceedi ding ng 3.5% % of constr truc uction on costs; ; Architect costs ts exceedi ding ng 10% of constr tructi uction n costs ts ‣ Buildi ding ng costs exceedi ding g $326/SF /SF (periodi odical ally y update ted) d) ‣ Site costs ts that exceed 8% of the buildi ding g costs ts ‣ Furnishi hings ngs and Techno nolog ogy Equipme pment nt that exceed d $2,400/ / student nt based d on approv oved d enrollme ment ‣ Change nge Orders exceedi ding ng 1% of constr truc ucti tion on cost

  11. Designer Selection Process Designer Selection is determined by the MSBA Designer Selection Panel • Total of 15 members. Twelve permanent members are appointed by MSBA; three members are assigned by the district • Representative from School Committee • Superintendent or Representative • CEO or Representative • Firms must have been pre-qualified by MSBA • MCPPO certified • 17.6% M/WBE Participation • Compass will manage the selection process on behalf of DSP (working with WW procurement) • Finalize RFS • Advertisement Walk-through • Reference Checks • District reps cannot “pre - rank” but can discuss submissions • DSP hearing in Boston – shortlist to 3 or 4 finalists 2 nd DSP hearing will be interviews • Shortlist and finalist are ranked by vote of DSP. 1 st ranked – 3 points; 2 nd ranked – 2 points; • 3 rd ranked – 1 point • Town (with OPM) negotiates fee and awards contract

  12. Designer Selection Process Proposed Timeline for Designer Selection WPS / SBC Receive Draft RFS 6/10/19 MSBA Receive Draft RFS 6/17/19 MSBA Returns RFS Comments 7/1/19 Submit to Central Register and Local paper 7/18/19 RFS Available 7/24/19 Pre-Proposal Informational Session 7/31/19 (Location and Time: TBD) Last Day for Questions from Respondents 8/14/19 Responses Due by 11:00am 8/21/19 CPM Complete Reference Checks and Subconsultant Matrix 8/28/19 Submit Information to MSBA DSP 8/29/19 MSBA DSP Meeting 9/17/19 MSBA DSP Interview (if decided) 10/1/19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.