TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL Introduction / Roles - - PowerPoint PPT Presentation

town of westwood paul hanlon elementary school
SMART_READER_LITE
LIVE PREVIEW

TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL Introduction / Roles - - PowerPoint PPT Presentation

TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL Introduction / Roles Similar Experience Timeline MSBA Process WSBC Role MSBA Reimbursement Designer Selection SBC Kick-off | June 6, 2019 One Edgewater Drive, Suite 204 |


slide-1
SLIDE 1

One Edgewater Drive, Suite 204 | Norwood, MA 02062 | 508.589.5061 | www.compasspminc.com

TOWN OF WESTWOOD PAUL HANLON ELEMENTARY SCHOOL

SBC Kick-off | June 6, 2019

  • Introduction / Roles
  • Similar Experience
  • Timeline
  • MSBA Process
  • WSBC Role
  • MSBA Reimbursement
  • Designer Selection
slide-2
SLIDE 2

INTRODUCTION/ROLES

Timothy Bonfatti Project Director Bryan Jarvis Project Executive Emily Sarazin Construction Site Manager FEASIBILITY/DESIGN PHASE CONSTRUCTION PHASE

TOWN OF WESTWOOD | PAUL HANLON ELEMENTARY SCHOOL

Christopher Kenney Senior Project Manager Bryan Jarvis Project Executive Christopher Kenney Senior Project Manager Brian Kelley Vice President

slide-3
SLIDE 3

ELEMENTARY SCHOOL EXPERIENCE

HUNNEWELL ELEMENTARY SCHOOL, Wellesley

  • Swing Space Analysis
  • Extensive Site Constraints
  • Significant Public Engagement
  • Net Zero Energy Ready

HARDY/ UPHAM ELEMENTARY SCHOOL, Wellesley

  • Redistricting / Consolidation Options
  • Historically Sensitive Considerations
  • Focus on Sustainability
  • K-5 Neighborhood Schools
slide-4
SLIDE 4

ELEMENTARY SCHOOL EXPERIENCE

MARATHON ELEMENTARY SCHOOL, Hopkinton

  • Extensive Options Analysis
  • Reviewed Four (4) Separate Sites
  • Expanded School During Construction
  • 2 Months Ahead of Schedule & $4M Under Budget

FIELD ELEMENTARY SCHOOL, Weston

  • Upper Elementary
  • Congested Campus – 3 Other Schools
  • Built on Sloped Site
  • Extensive Daylighting
slide-5
SLIDE 5

APPROACH TIMELINE

OPM Approval 06/19 09/19 Designer Selection 01/20 Submit PDP Submit PSR 04/20 Town Mtg Ballot Vote Submit SD Report 08/20 10/20 02/21 Complete DD Complete CD 08/21 10/21 Start Construction

PDP: Preliminary Design Plan | PSR: Preferred Schematic Report | SD: Schematic Design Report

Community Forum

slide-6
SLIDE 6

MSBA Process – Feasibility / SD Phase

Preliminary Design Program (PDP)

  • Educational Program
  • Initial Space Summary
  • Evaluation of Existing

Conditions

  • Site Development Requirements
  • Preliminary Evaluation of

Alternatives Preferred Schematic Report

  • Evaluation of Existing

Conditions

  • Final Evaluation of

Alternatives

  • Preferred Solution

Schematic Design Report

  • Schematic Design (30%)
  • Final Design Program
  • Traffic Analysis
  • Environmental Assessment
  • Geotechnical
  • Code Analysis
  • Sustainability
  • ADA / MAAB Analysis
  • Room Data Sheets
  • Project Delivery System
  • Construction Estimates
  • Total Project Budget
  • Maximum Reimbursement
  • Project Schedule
slide-7
SLIDE 7

WSBC –Responsibility Matrix - FS

Deliverable Review/ Comment Vote Time Frame* Comment MSBA Submissions X

Q1, Q2, Q4

Design Alternatives X Q1 Education Plan / Space Summary X Q1 SC Vote Sustainability Approach X Q2 Evaluation Criteria X Q1 Shortlist of Options X Q1 Instructional Technology X Q3 SC Vote Project Budget / Schedule X Q3 Community Outreach X Design Elements X Q2 Final Preferred Option X Q2

*assumes Designer Selected 10/19 – all time frames 2020

slide-8
SLIDE 8

MSBA Process – Reimbursement

MSBA Cost t Caps s / Ex Exclu lusion sions

The MSBA has several types of costs which are ineligible for reimbursement. They fall into three general categories.

  • Categorically Ineligible

– Costs that are not core to the educational program – Costs for items that are not part of the permanent building and grounds – costs beyond the project scope

  • Costs that Exceed MSBA Caps
  • Costs for Spaces that Exceed Guidelines (sometimes)

– Costs for spaces that are eligible but exceed the MSBA guidelines and not approved by MSBA staff

slide-9
SLIDE 9

MSBA Process – Reimbursement

MSBA Cost t Caps s / Ex Exclu lusion sions

The following costs are categorically ineligible for reimbursement

  • Land Acquisition
  • Legal Fees
  • Off site Improvements
  • Synthetic Turf; Spectator Amenities; Stadiums
  • Utility Company Charges
  • Swing Space
  • Building Permits / Local Board Costs
  • Financing Costs
  • Site Remediation
  • Asbestos Containing Floor Tiles
  • Auditorium (although a cafetorium would be eligible)
slide-10
SLIDE 10

MSBA Process – Reimbursement

MSBA Cost t Caps s / Ex Exclu lusion sions

Costs that exceed the following caps are ineligible

  • Soft

t Costs exceedi ding ng 20% of constructi ruction

  • n costs
  • OPM costs

ts exceedi ding ng 3.5% % of constr truc uction

  • n costs;

; Architect costs ts exceedi ding ng 10% of constr tructi uction n costs ts

  • Buildi

ding ng costs exceedi ding g $326/SF /SF (periodi

  • dical

ally y update ted) d)

  • Site costs

ts that exceed 8% of the buildi ding g costs ts

  • Furnishi

hings ngs and Techno nolog

  • gy Equipme

pment nt that exceed d $2,400/ / student nt based d on approv

  • ved

d enrollme ment

  • Change

nge Orders exceedi ding ng 1% of constr truc ucti tion

  • n cost
slide-11
SLIDE 11

Designer Selection Process

Designer Selection is determined by the MSBA Designer Selection Panel

  • Total of 15 members. Twelve permanent members are appointed by MSBA; three members

are assigned by the district

  • Representative from School Committee
  • Superintendent or Representative
  • CEO or Representative
  • Firms must have been pre-qualified by MSBA
  • MCPPO certified
  • 17.6% M/WBE Participation
  • Compass will manage the selection process on behalf of DSP (working with WW

procurement)

  • Finalize RFS
  • Advertisement Walk-through
  • Reference Checks
  • District reps cannot “pre-rank” but can discuss submissions
  • DSP hearing in Boston – shortlist to 3 or 4 finalists
  • 2nd DSP hearing will be interviews
  • Shortlist and finalist are ranked by vote of DSP. 1st ranked – 3 points; 2nd ranked – 2 points;

3rd ranked – 1 point

  • Town (with OPM) negotiates fee and awards contract
slide-12
SLIDE 12

Designer Selection Process

Proposed Timeline for Designer Selection

WPS / SBC Receive Draft RFS 6/10/19 MSBA Receive Draft RFS 6/17/19 MSBA Returns RFS Comments 7/1/19 Submit to Central Register and Local paper 7/18/19 RFS Available 7/24/19 Pre-Proposal Informational Session 7/31/19 (Location and Time: TBD) Last Day for Questions from Respondents 8/14/19 Responses Due by 11:00am 8/21/19 CPM Complete Reference Checks and Subconsultant Matrix 8/28/19 Submit Information to MSBA DSP 8/29/19 MSBA DSP Meeting 9/17/19 MSBA DSP Interview (if decided) 10/1/19