the smart grid
play

The Smart Grid: Distributed optimization & control challenges - PowerPoint PPT Presentation

The Smart Grid: Distributed optimization & control challenges Kameshwar Poolla UC Berkeley June 24, 2011 HYCON2 Trento, June 2011 Objectives Cover essential background on power systems Tell you about what is changing -


  1. The Smart Grid: Distributed optimization & control challenges Kameshwar Poolla UC Berkeley June 24, 2011 HYCON2 – Trento, June 2011

  2. Objectives � Cover essential background on power systems � Tell you about what is changing - Renewables - Distribution automation - Markets - Communication and sensing � Discuss some opportunities - Distributed optimization - Distributed control � Describe our vision of Grid2050 HYCON2 – Trento, June 2011

  3. A. The Legacy Grid 1. Components 2. Complications 3. Fact & Figures 4. Basic Power Systems Engineering 5. Basic Power Systems Economics HYCON2 – Trento, June 2011

  4. Power System Components � Generation system: power source ideally with fixed voltage and frequency � Load or demand: consumes power ideally constant and resistive � Transmission system: transmits power ideally as a perfect conductor � Distribution system: local reticulation of power � Control equipment: many functions coordinate supply with load, regulate voltage and frequency, protection, handle component failures HYCON2 – Trento, June 2011

  5. A simple power system generator load transmission HYCON2 – Trento, June 2011

  6. Complications � Loads vary a lot, not purely resistive not known in advance day-ahead forecast accuracy 2-4% � Generators have constraints: ramping, capacity � Transmission lines are reactive, have capacity constraints � Everything is connected in a complex network of heterogeneous elements � Must be robust to component failure � Must deliver power economically through markets HYCON2 – Trento, June 2011

  7. Load variability � Aggregate loads in CA on a hot day in 1999 � Peak is 2-6pm [system can be very stressed] � Variation is 50% of peak load HYCON2 – Trento, June 2011

  8. Generation, T&D HYCON2 – Trento, June 2011

  9. Generators � Limited capacity � Contain control systems to regulate frequency and voltage � Many different types with different costs, cold-start times, ramp rates, inertia Coal, gas, nuclear, hydro, wind, solar, � Other points - Stability issues are important for thermal generators - Start-up times require unit commitment in advance - Require to be taken off-line for maintenance/repair HYCON2 – Trento, June 2011

  10. Transmission � Operate at high voltages to reduce resistive line loss [765, 500, 345, 230 kV] � Mainly 3 phase AC � HV DC for long lines and undersea cables � T & D losses in 2007 ������ � Moving electricity across 1000 Km is cheap 0.005 – 0.02 $/kW hr [not counting capital cost] Key fact: aging transmission infrastructure is causing many problems in the US HYCON2 – Trento, June 2011

  11. HYCON2 – Trento, June 2011

  12. It’s a Complex Network � Distribution network - has tree structure - Serving millions of customers - Changing topology � Transmission network - has loops, node degree < 5 - Enables routing of power from multiple generators - 4000-12000 buses � Network aspect can cause problems - Cascading failures - Islanding - Stability issues HYCON2 – Trento, June 2011

  13. Operations � Too complex, so broken into control areas � Each area handled by a Balancing Authority/System Operator � Inter-area power transfer for control area imbalances � Balancing functions of System Operator - Ex ante: Economic Dispatch Schedule generation to meet forecast demand - Real time: Monitoring For system failures, power quality, line congestion - Ex post: Reserve management Schedule generation to handle unexpected events HYCON2 – Trento, June 2011

  14. North America Interconnections Geographic segmentation for easier management of electricity HYCON2 – Trento, June 2011

  15. Electricity Markets � Intimately connect to power systems engineering � Electricity is different from bananas � Bilateral Contracts 65% of power is sold in long-term bilateral contracts � Bulk-power markets Multiple time-scales: Day-Ahead, Hour-Ahead, Real-Time � Markets are partially regulated Price caps, subsidies, extra-market mechanisms � Ancillary Services Markets for other stuff Reserves, Inertia, HYCON2 – Trento, June 2011

  16. Economic Dispatch � Scheduling generation to meet forecast demand � Done by SO in advance through electricity markets Forecast the demand 1. Get bid stacks from generators 2. Select generation to minimize cost 3. � Constraints Existing bilateral contracts Transmission line limits Power system security � It is a centralized optimization problem � Output: schedule of committed generation and prices HYCON2 – Trento, June 2011

  17. Power System Security � Must deliver power even when a component fails - Worry about 1 failure - Called [N-1 contingency] � SO buys reserve capacity - to handle single largest failure - Margins are 7% in CA, 11% in Texas � Feasibility of power flow places constraints on economic dispatch HYCON2 – Trento, June 2011

  18. Robustness & Reserves � Power system security - Contingency Reserves � Demand forecast errors - Operating Reserves - When load rises too sharply to schedule other resources � Keep power quality [frequency 60 ± 0.25 Hz] - Regulation reserves � Management of reserves is complex, centralized HYCON2 – Trento, June 2011

  19. Facts & Figures HYCON2 – Trento, June 2011

  20. US Generation Sources HYCON2 – Trento, June 2011

  21. Generation Sources in California B#;.% A6"&'"29'68& /, >, ?@9%6 //, 1.2.3"4&.' 5)6&"%7'38297' :.6#;.%<"&= />, !"#$%"&'(") !$-&."% *+, /0, C6$%-.D'EC'FGH7'F&.-#%8-' Oregon is 57% Hydro, I63.%'H22$"&'>JJ+'K C#"#.' Washington State is 70% Hydro L"#"'M"4&.) HYCON2 – Trento, June 2011

  22. Generation Sources in Illinois Renewable 0.0% Nuclear 43.6% Coal Hydroeletric 55.1% 0.0% Petroleum Gas 0.6% 0.6% HYCON2 – Trento, June 2011

  23. HYCON2 – Trento, June 2011

  24. Demand side facts � Power will be defined carefully later Installed U.S. generation capacity ������ GW [about 3 kW per person] Average load of UCB about 25 MW Average load of California about 34 GW � Annual U.S. electric energy consumption ������������������������ MWh per person [on average each American uses 1.5 kW of power] HYCON2 – Trento, June 2011

  25. Retail Electricity Prices HYCON2 – Trento, June 2011

  26. AC Power � 60 Hz in US, 50 Hz in US � Phasors � Complex power absorbed by a load ! " � Complex power delivered by a source ! � Conservation of complex power " HYCON2 – Trento, June 2011

  27. Power Flow on a Line � Real power flow controlled by phase difference � Reactive power flow controlled by voltage difference HYCON2 – Trento, June 2011

  28. Reactive power � What is it? - Power that is borrowed and returned each cycle - Not consumed in net � If reactive power is supplied remotely, we have HYCON2 – Trento, June 2011

  29. Reactive power compensation � Best to supply reactive power locally � Need to adjust compensation as load varies � Can be done at load bus by - Adjustable shunt capacitance - Load-tap-changing transformer - Power electronics devices HYCON2 – Trento, June 2011

  30. Three Phase � 3 conductors instead of 6 for same power transfer � Sum of powers across phases is constant HYCON2 – Trento, June 2011

  31. Balanced 3-phase Operation � Symmetrical loads � Symmetrical generation � 120 o phase shift from one phase to next � Allows analysis one-phase-at-a-time � Steady-state frequency = 60 Hz � Quasi-steady-state frequency �� 60 Hz Changes slowly, so can still use phasors for analysis Time-varying magnitudes and angles HYCON2 – Trento, June 2011

  32. Generator Models � Per-phase � Includes voltage regulation loop � More complex models for transient analysis [Swing equation] � Still more complex models to analyze field/armature effects, frequency swings, rotor vibrations, etc ! " HYCON2 – Trento, June 2011

  33. Transmission line Models � Per-phase � Medium to long lines: � -model � Short lines (< 150 miles) � Line loadability Short lines: thermal limits Long lines: stability limits � Decent power system model sparse circuit driven by variable sources serving uncertain loads HYCON2 – Trento, June 2011

  34. Power Quality � Voltage 1 ± 0.02 per unit � Frequency 60 ± 0.25 Hz Frequency oscillations are an early indicator of system stability Voltage collapse is the result Modest voltage excursions result from poor reactive power support Result is inefficiency HYCON2 – Trento, June 2011

  35. Dispatch � Selecting generation to meet forecasted demand � Centralized - System operator communicates with generators - Schedules setpoints � Day Ahead - Forecast load ± 3% - Schedule generation in DA markets � Hour Ahead - Better load forecast ± 0.5 % - HA is an adjustment market � Real-time Balancing - Real time is actually 5-10 minute ahead - Reissue set-points for select generators HYCON2 – Trento, June 2011

  36. Primary Generation Control � Also called Load-frequency control � To account for minute imbalances between supply and demand � Completely decentralized � How it works - Frequency drop: add generation - Frequency rise: decrease generation � Details - Done by adjusting governor in thermal generation - Time scale 0.1 seconds HYCON2 – Trento, June 2011

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend