The Presentation Building Overview Thesis Proposal Structural - - PDF document

the presentation
SMART_READER_LITE
LIVE PREVIEW

The Presentation Building Overview Thesis Proposal Structural - - PDF document

4/16/2008 The Presentation Building Overview Thesis Proposal Structural Analysis Structural Analysis The Floor System The Lateral System Architectural Breadth CM Breadth NA NATHAN NA NATHAN AN E. AN E. E. REY


slide-1
SLIDE 1

4/16/2008 1

NA NATHAN AN E.

  • E. REY

REYNOLDS OLDS NA NATHAN AN E.

  • E. REY

REYNOLDS OLDS ADVISOR: M.

  • M. KEV

KEVIN P N PARF RFITT AD ADVI VISOR: M

  • M. KEVI

VIN P PARFITT STRUCTUR URAL AL OPT OPTION ON ST STRU RUCTURAL O OPTION THE PENNSYLVANIA NIA ST STATE U UNIVERSIT SITY THE PENNSYLVANI NIA S STATE U E UNIVER ERSITY APRI RIL 1 L 15, , 2008 2008 APRI RIL 1 L 15, , 2008 2008 ARCHITECTURAL ENG ENGINE NEER ERING G ARCHITECTURAL ENG ENGINE NEER ERING G

The Presentation

Building Overview Thesis Proposal Structural Analysis Structural Analysis The Floor System The Lateral System Architectural Breadth CM Breadth Conclusions

The Building

Architecture

1970’s Era Law School 90,000 SF Addition Classroom Space Office Space

Construction

4 Phases Minimal Interruption 2 Year Construction

The Building

Structure

Steel Moment Frame Construction 1 Bay Clearspan Geopier Foundation Stabilization

5 Stories 2 Stories

The Proposal

Structural Study Floor System Analysis

○ Composite Steel Joists (CJ-Series)

Lateral System Analysis

y y

○ Braced Frame or Shear Wall Design

The Proposal

Breadth Studies Architecture

○ Floor Plans ○ Elevations

Construction Management

○ Cost Estimate ○ Project Schedule

slide-2
SLIDE 2

4/16/2008 2

The Structure

Floor System Considerations Large Open Spans Maintain Existing Depth (31”) Strength Design Vibration Characteristics Vibration Characteristics

The Structure

Strength Analysis Designed using SJI Standard Specs Spacing: 5’ O.C. Non-Composite Dead Load: 270 PLF

Non Composite Dead Load: 270 PLF

Live Load: 600 PLF Total Load: 1150 PLF Preliminary Design: 26CJ 1150/600/270

The Structure

Vibration Analysis Spacing: 5’ O.C. Damping Coefficient: 0.03

○ First Floor Classrooms

s

  • o C ass oo

s Natural Frequency: 3.96 Hz Peak Acceleration: 0.0041g < 0.005g Final Design: 26CJ 1600/775/270

○ (46) ¾” Shear Studs ○ Larger than Required by Strength

The Structure

Existing Floor System Proposed Floor System

The Structure

Existing Floor System Proposed Floor System

The Structure

Lateral System Considerations Classroom Layout Drift Requirements Member Properties

Member Properties

slide-3
SLIDE 3

4/16/2008 3

The Structure

North-South Lateral System Shear Wall

○ Impractical Coordination of Trades

Diagonal Bracing

○ Span Length Issues (55 ft)

Knee Bracing

○ Excessive First Floor Drift

Chevron Bracing

○ Architectural Interruption Classroom Corridor

Eccentric Chevron Bracing

○ Minimal Complications

The Structure

North-South Braced Frame Eccentric Chevron Brace

○ First Floor

HSS9x7x1/2”

○ Upper Floors

HSS8x6x1/2”

3 Braces Required Increased Column Size

○ W14x109

Drift: 0.88 inches

The Structure

East-West Braced Frame Diagonal Bracing

○ HSS8x6x1/2”

Typical Column Size

yp

○ W14x82

Drift: 0.43 inches

The Structure

Typical Bracing Connections

Typical Chevron Brace Typical Diagonal Brace

The Structure

Additional Structural Considerations Foundations

○ Geopier Stabilization Remains Necessary ○ Not Significantly Modified

Beams Beams

○ W21x50 (44) ¾” Shear Studs

Columns

○ Sized for Gravity Load Only W14x82 ○ Existing Design Sized for Drift W14x159

The Architecture

Revised First Floor Plan

Revised Classroom Layout Service Area Service Area Maintain Existing Corridor

slide-4
SLIDE 4

4/16/2008 4

The Architecture

Revised Classroom Space

The Architecture

South Elevation

The Architecture

North Elevation

The Construction

4 Phase Construction

○ Phase I (Structure/Sitework)

1 Year Duration

○ Minimize Impact on Classes ○ Existing Overall Project Schedule

The Construction The Construction

Existing System Proposed System

Total Cost: $1.44m Time: 21 Weeks Benefits: Total Cost: $1.31m Time: 20 Weeks Benefits: Less Members No Deck Fireproofing Time Cost

slide-5
SLIDE 5

4/16/2008 5

The Conclusions

Proposed Floor System Negligible Effect on Construction Process Proposed Lateral System Beneficial to Overall Construction Process Beneficial to Overall Construction Process Proposed Architectural Plan More Aesthetically Pleasing Façade

The Conclusions

Recommendations Implement Revised Lateral System

○ Structural Engineer Involved in Schematic

Design Process Maintain Existing Floor System

○ Less Members, Equal Cost

Utilize Revised Architectural Elevations