Rigid Inclusion Design & Construction Wentworth Institute of - - PowerPoint PPT Presentation

rigid inclusion design construction
SMART_READER_LITE
LIVE PREVIEW

Rigid Inclusion Design & Construction Wentworth Institute of - - PowerPoint PPT Presentation

haywardbaker.com Rigid Inclusion Design & Construction Wentworth Institute of Technology | Beatty Hall | Boston, MA Kevin Dawson, PE, Vice President, New England Area Manager Presentation Outline Why Rigid Inclusions What are Rigid


slide-1
SLIDE 1

haywardbaker.com

Rigid Inclusion Design & Construction

Wentworth Institute of Technology | Beatty Hall | Boston, MA

Kevin Dawson, PE, Vice President, New England Area Manager

slide-2
SLIDE 2

116

Presentation Outline

Why Rigid Inclusions What are Rigid Inclusions Common Applications Design Overview Quality Control Questions

slide-3
SLIDE 3

117

Why Rigid Inclusions?

  • Geotechnical

−Reduce Settlement −Increase Bearing Capacity

  • Structural

−Shallow Spread Footing −Slab-on-grade replaces structural slab

  • Environmental

−Little to no spoil (contamination) −Quiet compared to pile driving

slide-4
SLIDE 4

118

Benefits

Cost: Shallow spread foundations and slab-on-grade

  • vs. pile caps and structural

slab Schedule: Gain time compared to surcharge or surcharge with wick drains Reduce settlement more than aggregate piers Minimizes spoil created at ground surface Quality verification through data acquisition and testing

slide-5
SLIDE 5

119

What are Rigid Inclusions (RI)?

  • High modulus grout columns
  • Typical diameters 12” to 18”
  • Works in conjunction with a

load transfer platform (LTP)

  • Less compressible than an

aggregate pier or stone column

slide-6
SLIDE 6

120

Installation

Tool is driven/drilled to bearing layer. Displace soil minimal spoil generated Refusal based on design and feedback from installation process Grout is backfilled into cavity while extracting the tool.

slide-7
SLIDE 7

121

RI System Installation Overview

  • 1. Working platform preparation and control (Safety)
  • 2. RIs are installed using drilling or vibratory methods
  • 3. RI heads are lowered (as needed)
  • 4. Load transfer platform (LTP) is installed per design

(1) (2) (3) (4)

slide-8
SLIDE 8

122

Typical RI Installation

slide-9
SLIDE 9

123

Geologic Conditions

1 2 3

slide-10
SLIDE 10

124

Applications: Foundation Support

slide-11
SLIDE 11

125

Applications: MSE Walls

slide-12
SLIDE 12

126

Applications: Warehouses

slide-13
SLIDE 13

127

Quantifying Benefits

20-30 ft 1700 psf

Estimated settlement without ground improvement – 6 inches Estimated settlement with aggregate piers – 1.5 to 3 inches Estimated settlement with rigid inclusions – less than 1 inch

slide-14
SLIDE 14

128

Finite Element – Axisymmetric/Unit Cell

Behavior of a single RI that is part of an infinite grid of RIs Load-displacement

– Designer must account for the relative movement between the RI tip and the adjacent soil and the relative movement between the RI head and the LTP

slide-15
SLIDE 15

129

A load transfer platform (LTP) is used to transfer load from the structure to the Rigid Inclusions Structural Fill – Granular soil (VDOT 21B) LTPs may include 1 to 3 layers of embedded geogrid or steel mesh

Load Transfer Platform

slide-16
SLIDE 16

130

A load transfer platform (LTP) is used to transfer load from the structure to the Rigid Inclusions Structural Fill – Granular soil (VDOT 21B) LTPs may include 1 to 3 layers of embedded geogrid or steel mesh

Load Transfer Platform

slide-17
SLIDE 17

131

HBI Data Acquisition System (DAQ)

slide-18
SLIDE 18

132

HBI Data Acquisition System (DAQ)

slide-19
SLIDE 19

133

RI Load Testing

Static Load Testing

150% to 200% Design load Design load from Finite Element Analysis

slide-20
SLIDE 20

134

Thank You!! Questions?