SLIDE 1 The New Champ Clark Bridge
US 54 over the Mississippi River at Louisiana, Missouri
2019 Midwest Geotechnical Conference
Don Hammond, PE HNTB Corporation
SLIDE 2 Louisiana (Missouri)
bridges connecting Missouri and Illinois north of St. Louis
(Alton, Hannibal & Quincy)
miles via Hannibal
SLIDE 3
Aerial Looking West
SLIDE 4 Key Topics
- History of Original Bridge & Geologic Profile
- Design/Build
- Foundations – with focus on large OE pipe pile
- East Approach Embankment on Soft Ground
SLIDE 5
Original Champ Clark Bridge
SLIDE 6 Original Champ Clark Bridge: Timeline
- February 1926 – Chamber of Commerce
initiated formal planning. Within 3 days, legislation was moving through Congress.
- March 1926 – Harrington, Howard & Ash
staff were on site.
- October 1926 – Substructure work begun
- May 1928 – Bridge completed and open
SLIDE 7
Original Champ Clark Bridge: Bid
SLIDE 8
Geologic Profile
SLIDE 9
Original Champ Clark Bridge: Foundations
30 ton timber piles driven no less than 35 feet below bottom of pier.
SLIDE 10
Original Champ Clark Bridge: Struggles
SLIDE 11
for 2 lanes
for wide loads
for emergency maintenance
Original Champ Clark Bridge: Recent Issues
SLIDE 12
Original Champ Clark Bridge: Recent Issues
SLIDE 13
flooding of Illinois approach
Another Issue
SLIDE 14
- Design/Build became legal in Missouri in 2005
- Chose Design/Build to expose IDOT to method
- Missouri is the lead state with Illinois as a partner
Design/Build in Missouri
SLIDE 15
- Construct project on budget ($62.5M)
- Safe, reliable, low maintenance structure that provides at
least 100 years of service life
- 405 foot navigation clearance
- Minimize and mitigate construction impacts
- Deliver project using a diverse workforce
Project Goals
SLIDE 16
- Two 12-foot lanes with 10-foot shoulders
- Improve traffic flow at US 54 / Rte 79 intersection
- Engage community
Additional Unspecified Objectives
SLIDE 17
- Permits: 404, 408, Coast Guard, etc.
- Right of Way (Army Corps and Sny Levee)
- Some hydraulic modeling
- PreAward Geotech
Risk Mitigation Ahead of Award
SLIDE 18 Pre-Award Geotechnical Investigation
- 10 River Borings
- 13 Land Borings
- 2 CPTs
SLIDE 19
Geologic Profile
SLIDE 20 4/17/17 Supplemental Pre-Award Geo Report Issued
SLIDE 21 Contract Awarded to Massman/HNTB in June 2017
5 Spans on four 12-foot Deep Steel Plate Girders 3 Spans on Prestressed Concrete Girders (NU)
SLIDE 22 Contract Awarded to Massman/HNTB in June 2017
July
- Completed 8 Water Borings (1 at each shaft)
Aug.
- Completed 20 Land Borings
Sept.
- Issued Memo for River Pier Foundations
Oct.
- Issued Memo for Approach Piers and Abutments
Nov.
- Began Inspection of Drilled Shaft Construction
Jan.
- Issued Memo for Block Wall and Embankment
SLIDE 23 Post-Award Geotechnical Investigation
- 8 River Pier Borings
- 3 Approach Pier Borings
- 2 Abutment Borings
- 6 Wall Borings
- 9 Embankment Borings
Total = 28
SLIDE 24 New Champ Clark Bridge: Spans and Foundations
Spread Footing on Rock 11.5’ Dia. Drilled Shafts with 11.0’ Dia. Rock Sockets H-Piles to Rock 48” Open Ended Pipe Piles to Rock
SLIDE 25
New Champ Clark Bridge: Spans and Foundations
SLIDE 26
West Abutment & Retaining Wall
SLIDE 27
West Abutment & Retaining Wall
SLIDE 28
West Abutment & Retaining Wall Factored Bearing Pressure = 13 ksf Factored Bearing Resistance = 32 ksf Cut was Line Drilled
SLIDE 29 River Piers
11.5 ft Shafts with 11.0 ft Sockets:
- 5/8” Wall Permanent Casing
- 20 to 60 ft Long Shafts
- 22 ft Long Sockets
- 8 CSL Tubes
- 60 #18 bars
- Factored Axial Load = 8100 kips / Shaft
SLIDE 30 River Piers
Confidentially, pre- award samples of Maquoketa Shale were tested for Slake Durability (ASTM D4644) Results confirmed that of Maquoketa Shale was actually shaley, silty dolomite along rock sockets, that would not rapidly degrade during construction.
SLIDE 31 River Piers
Determination that slurry was not needed resulted in significant cost savings and shortened construction schedule by 2 weeks.
SLIDE 32
River Piers: Drilled Shaft Design
SLIDE 33
River Piers: Drilled Shaft Design
Factored Side Resistance = 0.40 (qs) = 8.7 ksf Similarly… Factored Tip Resistance = 0.36 (qt) = 269 ksf
SLIDE 34
River Piers: Drilled Shaft Construction
SLIDE 35
River Piers: Drilled Shaft Construction
SLIDE 36
River Piers: Drilled Shaft Construction
SLIDE 37 Approach Piers
Originally designed as traditional H-pile supported footings. At MoDOT’s suggestion, Massman switched to 48” diam.
- pen ended pipe pile bents.
Eliminated footing excavations in saturated, flood-prone overbank 16 ft of scour Unbraced Length 38 ft
SLIDE 38 Approach Piers: 48” Dia. Open Ended Pipe Piles
ASTM A-252 Grade 3 (Fy = 45 ksi) Galvanized to 20 ft below scour Top Half 1-inch Wall / Bottom Half ¾-inch Wall Filled with concrete above scour
SLIDE 39 Approach Piers: 48” Dia. Open Ended Pipe Piles
Want to drive through 10-ft layer of cobbles & boulders to seat on rock. Hard Rock or Soft Rock? Shaley DOLOMITE or Calcareous SHALE? Since Qu > 4000psi, decided it is hard rock. Cutting Shoe Point Reinforcement Required
SLIDE 40 Approach Piers: 48” Dia. OEP (3/4” Wall)
Nominal bearing resistance shall not exceed maximum factored axial structural resistance for severe driving. [AASHTO 10.7.3.2.3]
- Max. Factored Axial Str. Resistance = 0.6 (45) 111.4 = 3006 kips
Let Nominal Bearing Resistance = 3006 kips
SLIDE 41 Approach Piers: 48” Dia. OEP (3/4” Wall)
Decided to PDA each pile & use a geotechnical resistance factor of 0.65
- Max. Factored Axial Geo. Resistance = (0.65) 3006 = 1954 kips
- Max. Factored Axial Load (from Br. Engr.) = 1860 kips < 1954 kips OK
Req’d Nom. Driving Resistance, Rndr = 1860/0.65 = 2865 kips (57% Fy)
SLIDE 42 Source: NCHRP Synthesis 478
Approach Piers: 48” Dia. OEP
...but Massman’s PDA Consultant, FTC, still worried about damaging pile based on recent events. Since:
- Driving to end bearing
- With known, consistent top of rock
- PDA/CAPWAP on every pile
HNTB (with MoDOT acceptance) raised resistance factor to 0.9 with 0.8 preferred.
Rndr = 1860/0.9 = 2070 kips (41% Fy)
SLIDE 43 Approach Piers: 48” Dia. OEP
Massman Submitted: Delmag D62-22 164.6 kip-ft rated energy 13.7 kip ram weight HNTB Review Comments
SLIDE 44
Approach Piers: 48” Dia. OEP -- WEAP
SLIDE 45
Approach Piers: 48” Dia. OEP -- PDA
SLIDE 46 Approach Piers: 48” Dia. OEP - CAPWAP
- 10 to 15 bpi at EOD
- Stopped 1 to 4 feet above est. top of rock
CAPWAP Results Capacities: 2100 to 2800 k > 2070 k (ok)
30% to 60% side friction
Max Stress: 20 to 25 ksi < 40.5 ksi (ok)
SLIDE 47 East Abutment: HP-12x53
Delmag D30-32 75.4 kip-ft rated energy 6.6 kip ram weight Rndr = 485 kips RPDA = 492 kips Pile Tip 135.5 ft below grade
SLIDE 48
East Approach Embankment
SLIDE 49
East Approach Embankment
SLIDE 50
East Approach Embankment – Stage Raise
SLIDE 51
East Approach Embankment – Settlement Plates
SLIDE 52 East Approach Embankment - OK to Pave?
From Trend Line: Bo = 2.0929 B1 = 0.8789 Smax = Bo/(1-B1) Smax =17.282 inches Remaining Settlement = 17.3-15.3 = 2 inches
SLIDE 53
Approach Piers
SLIDE 54
Steel Erection
SLIDE 55
Steel Erection
SLIDE 56
Flood Stage
SLIDE 57
Deck Construction
SLIDE 58
Deck and West Approach
SLIDE 59
Opened August 3, 2019
3 mo. ahead of schedule
SLIDE 60 Your Questions…
Original Champ Clark Bridge $1.0 M in 1926 = $14.3 M in 2018 New Champ Clark Bridge Winning Bid of $60 M in 2017
More Traffic / Heavier Traffic Unrestricted Vehicle Height Above 500 yr Flood Wider Deck
SLIDE 61
Construction Timelapse