the integrated baseline review
play

The Integrated Baseline Review DAVID C. BACHMAN Defense Acquisition - PowerPoint PPT Presentation

The Integrated Baseline Review DAVID C. BACHMAN Defense Acquisition University 09/12/01 1 IBR Policy Story DoD 5000.2-R - 10 June 2001 2.9.3.5. -- Integrated Baseline Reviews (IBRs) PMs and their technical staffs or IPTs shall evaluate


  1. The Integrated Baseline Review DAVID C. BACHMAN Defense Acquisition University 09/12/01 1

  2. IBR Policy Story DoD 5000.2-R - 10 June 2001 2.9.3.5. -- Integrated Baseline Reviews (IBRs) PMs and their technical staffs or IPTs shall evaluate contract performance risks inherent in the contractor’s planning baseline. This evaluation shall be initiated within 6 months after contract award or intra- government agreement is reached for all contracts requiring EVMS or C/SSR compliance. Who What Where When Why 2

  3. BMDO IBR Policy BMDO 5004-H – May 1998 Ballistic Missile Defense Organization (BMDO) Directive No. 5000 series, “Integrated Baseline Reviews,” directs that an IBR be conducted no later than six months following a contract award, or a significant contract modification, on contracts with Earned Value Management Systems (EVMS) Criteria or Cost/Schedule Status Report (C/SSR) requirements. The IBR is conducted jointly by the government and the contractor. 3

  4. BMDO IBR Goals BMDO 5004–H – IBR Goals Program Manager Ownership of the PMB. • Foster the use of Earned Value (EV) as a means of communicating the cost implications of technical and schedule problems. • Provide confidence in the validity of contractor cost/schedule reporting. • Identify areas of risk (cost, schedule, and technical performance) associated with the PMB. • Involve technical specialists and contract analysts in the IBR process. 4

  5. IBR Phases Initial Phase: Planning and Team Building Intermediate Phase: Prepare & Train for the IBR Review Phase: In-plant Activities Final Phase: Using EVM to Manage 5

  6. Initial Phase - Planning & Team Building IBR Planning Schedule 6 5 4 3 2 1 ID Task Name Duration 191 181 171 161 151 141 131 121 111 101 91 81 71 61 51 41 31 21 11 1 12/31 1 Contract Award 0 days 2 Initial Phase 46 days 2/12 3/9 3 IBR Strategic Planning 20 days 2/22 3/5 8 Build the Review Team 8 days 2/26 4/16 Collect Sample EVMS & CA Docu 36 days 12 3/6 3/19 9 ID CWBS Review Strategy 10 days 3/20 4/2 Draft Orientation Schedule 10 days 10 4 Develop IBR Handbook 10 days 4/3 Start the Draft IBR Handbook 0 days 5 4/3 4/16 6 Prepare the Draft IBR Handbo 10 days 4/17 Finish the Draft IBR Handboo 0 days 7 4/3 4/16 11 Draft the In Plant Agenda 10 days 13 Intermediate Phase 54 days 4/17 4/23 14 Finalize the Review Team 5 days 4/24 4/30 15 Assign CWBS review teams 5 days 5/1 5/7 16 Finalize the IBR agenda 5 days 5/8 5/11 17 Finalize the IBR Handbook 4 days 5/14 5/18 Finalize team logistics 5 days 18 5/30 6/1 19 IBR Team Orientation 3 days 6/4 6/8 IBR Team Training 5 days 20 6/11 6/2 21 Prepare for In-plant actvities 15 days 6/3 IBR 0 days 6 22

  7. IBR Phases Initial Phase: Planning and Team Building - Build the review team - Identify CWBS review strategy - Draft orientation schedule - Draft the In-plant agenda - Collect Contractor EVMS material 7

  8. Initial Phase - Planning & Team Building Building The IBR Team Team Leader: Program Manager Senior EVM Specialist: IBR Subject Area Expert IBR POCs: Manages IBR Logistics Conducts IBR Review Group Leaders: SOW Experts Technical Staff: EVM Staff Support: Supports Review Group Other Government: DCMA Support Contractors: Integral IBR Team Member 8

  9. Initial Phase - Planning & Team Building Collect Sample Contractor Data • CWBS • Current CPR & CFSR • CWBS Dictionary • Detailed Control Account Schedules • Program Organizational Structure • EVM System Description • Responsibility Assignment • Subcontractor Data Matrix • Basic Contract • Work Authorization • POOO Mods Documents • EVMS Surveillance • Master Schedule Reports • Control Account Plans 9

  10. IBR Phases Initial Phase: Planning and Team Building Intermediate Phase: Prepare & Train for the IBR - IBR Team Orientation & Training - Assign CWBS review teams - Prepare for In-plant activities - Finalize team logistics - Finalize the IBR agenda 10

  11. Intermediate Phase - Prepare & Train Preparing the Contractor • Contractor’s experience with the IBR process? • Have they been prepared for CAM discussions? • Do CAMs understand the basis of estimate/agreed-to work scope, schedule, and budget? • Is this the first meeting between the contractor and the government team? • Has the contractor and the program office prepared for a successful IBR? 11

  12. Intermediate Phase - Prepare & Train Preparing Yourself • Know your CWBS assignments – Be familiar with scope, schedule, budget • Know your strengths and weaknesses? – How well do you know • the contract? • the contractor? • the CAM(s)? • How are your EVM skills? • The multi-functional Team (Cost, Schedule, Technical) is an opportunity to transfer knowledge and experience 12

  13. Intermediate Phase - Prepare & Train Training • IBR Policy and Process • Fundamentals of earned value management • Fundamentals of scheduling • Performance Measurement Baseline & EV Techniques • Contractor’s earned value management system • Control Account’s work authorization documents, network schedule, and resource allocation • CAM discussion dynamics • Moot IBR CAM Discussions 13

  14. IBR Phases Initial Phase: Planning and Team Building Intermediate Phase: Prepare & Train for the IBR Review Phase: In-plant Activities - Kick-off meeting - Review IBR Objectives - Document Review - CAM Discussions - Daily Out Briefs - Document Results - Follow-up as necessary 14

  15. Document Review Technical Analysis Tech APB Analysis - Develop KPPs Program Office Documents Performance Cost Schedule Develop Drivers KPPs KPPs KPPs APB TPMs SOW Schedule Analysis Critical Schedule Work Auth Document Path, Float, Technical Drivers Risk DOCs Contract Work Packages Master Schedule Scope Budget CWBS Schedule RAM Task Detailed Resources Description Schedule P000 Resource Analysis Mods Labor Material Resource EVMS Facilities Drivers Time Phased Budget CPR Budget 15

  16. Review Phase – In-plant Activities • TECHNICAL ASSESSMENT • What are the High Risk Areas? Areas for Discussion • Conditions of Measurement ? • What are the Technical Requirements? • SCHEDULE ASSESSMENT • Underdeveloped Logic • Illogical/Forced Sequencing • Lack of Experience • Consideration of Technical Risks • WORK AUTHORIZATION • BUDGET ASSESSMENT • Schedules • Budget Validity/Risk • Budget Authorization • Distribution Logic • Control Account Plans(CAP) • Management Reserve • Undistributed Budget • WORK ASSESSMENT • Which tasks may be overstated? • Which tasks may be understated? • What has been left out? 16

  17. Review Phase – In-plant Activities CAM Discussions – CAM Interview • Interview Activities – In the CAMs work area – Confirm control account work packages accurately summarize assigned CWBS requirements – Data Traces – Scope, Schedule, and Budget – Identify and Document Risk • Don’t – Provide Guidance, Debate or Disagree with CAM – Enter side discussions – Exceed allotted interview time – schedule follow-up sessions if needed 17

  18. IBR Outcomes • Improved technical understanding of PMB sufficiency (at all levels) • A “documented” account of PMB review findings • An “action list” to tackle near-term cost, schedule and technical concerns • Improved communications between the Program Office, DCMA and the Contractor 18

  19. IBR Phases Initial Phase: Planning and Team Building Intermediate Phase: Prepare & Train for the IBR Review Phase: In-plant Activities Final Phase: Using EVM to Manage - Periodic PMB Analysis - Identify Risk Areas - Contract Baseline Changes - Validity and Limitation Issues - Subsequent IBRs 19

  20. Final Phase - Using EVM to Manage Rolling Wave Planning Concept • Detailed planning of all of the contract tasks is usually not possible at the start of the contract. • Detailed planning is done in increments or “waves”. • Once the nearest term work is completed, the next “wave” of work is detail planned, and then the next, etc. • Subsequent IBRs may be required as the contract matures and major efforts transition from summary level planning to detailed planning 20

  21. Final Phase - Using EVM to Manage Ongoing Baseline Validity and Realism • Validity – PMB still represents goals and objectives – PMB points to valid variances – Variances result in management action – Timely Incorporation of Contract Changes – Use of MR and UB • Realism – PMB changes made for management reasons not for reporting reasons – Use of Over-target Baselines – Use of Single Point Adjustments 21

  22. IBR Benefits • Early insight to technical sufficiency of the PMB – Tests the relationship between SOW/SOO and WBS – Assures planning and budgeting are accurate at the cost account level – Reviews available performance information to assure objective and meaningful reporting of technical status • Preparatory activities provide value – government and contractor personnel meet for training – contractor briefs their system – government program managers improve their familiarity with contractor processes and earned value data 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend