The Economic Impact of Nuclear Power Generation in Connecticut - - PowerPoint PPT Presentation

the economic impact of nuclear power generation in
SMART_READER_LITE
LIVE PREVIEW

The Economic Impact of Nuclear Power Generation in Connecticut - - PowerPoint PPT Presentation

The Economic Impact of Nuclear Power Generation in Connecticut Stan McMillen, Ph.D. Managing Economist, DECD Nandika Prakash, Economist, DECD Alissa DeJonge, Director of Research, CERC Dale Shannon, Senior Economist, CERC 1 Scope of Study


slide-1
SLIDE 1

The Economic Impact of Nuclear Power Generation in Connecticut

Stan McMillen, Ph.D. Managing Economist, DECD Nandika Prakash, Economist, DECD Alissa DeJonge, Director of Research, CERC Dale Shannon, Senior Economist, CERC

1

slide-2
SLIDE 2

Scope of Study

  • Assess the economic and fiscal impacts of

replacing or adding baseload generation in CT.

– Replace existing nuclear unit(s) at Millstone with a 1,000 MWe nuclear or CCGT plant – Add 1,000 MWe nuclear or CCGT plant to Millstone or CT Yankee

2

slide-3
SLIDE 3

Estimating Economic Impact

Control Forecast Alternative Forecast

09 10 11 12 09 10 11 12 09 10 11 12

Economic Impact

3

slide-4
SLIDE 4

Common Economic Modeling Assumptions

  • Each unit receives its LCOE
  • No net new job creation
  • No net new procurement (B2B activity)
  • No net new electricity sales
  • Merchant operators
  • Decommissioning phase greatly

compressed into one year (cost incl. In nuclear LCOE)

4

slide-5
SLIDE 5

Common Modeling Assumptions

  • No additional cost for spent fuel storage
  • Natural gas pipeline extension included for

CCGTs

  • Workers receive utility industry average

wage

  • Workers live in CT
  • Modeling time begins in 2009 and ends in

2050

5

slide-6
SLIDE 6

Assumptions: Replacement

  • Replacements are large construction

projects at the Millstone campus

– No net new jobs, capacity, procurement (B2B) – Use MIT 2009 cost & operational parameters with capacity factor for nuclear increased to 90%. – Electricity sales do not change (demand is constant)

6

slide-7
SLIDE 7

Economic Impact Drivers: Replacement

2009 2010 2011 2012 2013 2014 Total Nuclear plant construction & nuclear decommission $405 $1,093 $1,391 $1,159 $456 $887 $5,391 CCGT plant construction & nuclear decommission $493 $507 $887 $1,887 Pipeline construction $25 $25 $50 Total CCGT $543 $557 $887 $1,937

CCGT: Vendor EPC overnight cost = $850 million in 2007$; pipeline extension cost $5 million/mile for 10 miles AP 1000: Vendor EPC overnight cost = $3.333 billion in 2007$; construction outlays: 10%, 25%, 31%, 25%, 10%

7

slide-8
SLIDE 8

Economic Impacts

Source: The REMI model and author’s calculations. 8

Economic Variable 2009 2010 2011 2012 2013 2014 New Total employment Nuclear 7,993 20,320 24,756 19,249 6,021

12,087

CCGT NA NA NA

8,685 8,368 13,679

New Construction Jobs Nuclear 5,708 14,660 18,194 14,636 5,365

9,922

CCGT NA NA NA

6,263 6,187 10,245

New State GDP (mil nominal $) Nuclear

$460.5 $1,214.9 $1,495.1 $1,161.2 $313.4 $725.5

CCGT

NA NA NA $543.5 $531.1 $889.9

New Output (Sales) (mil nominal $) Nuclear

$780.5 $2,051.6 $2,516.2 $1,948.9 $530.0 $1,207.3

CCGT

NA NA NA $917.4 $894.6 $1,474.7

New Personal Income (mil nominal $) Nuclear

$393.6 $1,055.8 $1,400.3 $1,225.8 $556.5 $902.2

CCGT

NA NA NA $472 $507.80 $867.20

Net New State Revenue (mil nominal $) Nuclear

$77.78 $190.7 $218.66 $147.7 $0.53 $72.67

CCGT

NA NA NA $87.65 $77.71 $131.5

slide-9
SLIDE 9

Assumptions: Baseload Addition

  • Marginal units are displaced in CT

– These plants cease operation – Released labor & procurement absorbed by new units at Millstone or CT Yankee site. – No net new jobs or procurement – Electricity sales do not increase b/c demand is constant – Wholesale price declines as higher cost marginal units leave the market.

9

slide-10
SLIDE 10

Assumptions: Baseload Addition

  • Retail price declines 50% of wholesale decline

(2.85%) [ISO-NE, June 2006, White Paper]

  • Omit siting & permitting costs & time
  • No net new jobs, capacity, procurement
  • Use MIT 2009 cost & operational parameters

with capacity factor for nuclear increased to 90%.

  • Same economic & fiscal impact for Millstone or

CT Yankee sites

10

slide-11
SLIDE 11

Economic Impact Drivers: Addition

  • Construction expenditure and schedule

same as replacement

  • CT ratepayers see 2.85% reduction in

their electric bills absent other changes

  • Decommission occurs in 2074 & lasts for

20+ years (assuming 60-year life)

  • No SR/MR change in electricity demand

due to price reduction (=> sales flat)

11

slide-12
SLIDE 12

Economic Impact Drivers: Addition

CCGT: Vendor EPC overnight cost = $850 million in 2007$; pipeline extension cost $5 million/mile for 10 miles AP 1000: Vendor EPC overnight cost = $3.333 billion in 2007$; construction outlays: 10%, 25%, 31%, 25%, 10%

12

2009 2010 2011 2012 2013 2014 - 2050 Retail Electricity Price Reduction NA NA NA NA NA

  • 2.85%

Nuclear plant construction & nuclear decommission $405 $1,093 $1,391 $1,159 $456 NA CCGT plant construction & nuclear decommission $493 $507 NA Pipeline construction $25 $25 NA Total CCGT $543 $557 NA

slide-13
SLIDE 13

Economic Impacts

Annual Average Change from Baseline (2009- 2050) Economic Variable Add Nuclear Plant at Millstone or CT Yankee Add CCGT Plant at Millstone or CT Yankee Total New Employment (Persons) 2,420 1,333 New Construction (Jobs) 957 254

  • Ann. Avg.

Change NPV

  • Ann. Avg.

Change NPV New Gross Domestic Product (mil nominal $) $516.6 $7,594.8 $471.1 $5,768.4 New Output (mil nominal $) $845 $12,576.3 $773.6 $9,581.7 New Personal Income (mil nominal $) $363.6 $6,154.1 $247.6 $3,291.8 Net New State Revenue (mil nominal $) $27.4 $586 $18.6 $306.2 13

slide-14
SLIDE 14

Economic Impacts

Changes in Total, Non-farm & Construction Jobs: New Nuclear Plant at Millstone

  • r CT Yankee
  • 5000

5000 10000 15000 20000 25000 30000 2009 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047 2049

Change in Jobs

Total Employment Private Non-Farm Employment Construction

14

slide-15
SLIDE 15

Economic Impacts

Employment Changes in Total Nonfarm and Construction: New CCGT Plant at the CT Yankee Site

  • 2000

2000 4000 6000 8000 10000 12000 2 9 2 1 1 2 1 3 2 1 5 2 1 7 2 1 9 2 2 1 2 2 3 2 2 5 2 2 7 2 2 9 2 3 1 2 3 3 2 3 5 2 3 7 2 3 9 2 4 1 2 4 3 2 4 5 2 4 7 2 4 9 Change in Jobs Total Employment Private Non-Farm Employment Construction

15

slide-16
SLIDE 16

Discussion: Natural Gas

  • Natural Gas Pricing

– Assume ‘national’ price. – Changes in price for any reason change the price for everyone. – No competitive disadvantage for CT (excl. delivery costs). – Adding CCGT increases CT’s CO2 emission

  • RGGI and RPS targets more difficult to achieve
  • Increased vulnerability to price volatility & supply

disruption

16

slide-17
SLIDE 17

Discussion: Natural Gas

  • For CCGT plant at Millstone or CT Yankee, need

pipeline extension

17

slide-18
SLIDE 18

Regional Electricity Market

  • Regional wholesale markets administered by

ISO-NE:

– Day-Ahead – Real-Time – Forward Capacity – Ancillary Services

  • Regulation
  • Forward Reserve
  • Real-Time Reserve Pricing
  • Voltage Support
  • Other Services & Products

18

slide-19
SLIDE 19

Regional Electricity Market

  • Energy market pays all generators

participating in the day-ahead and real- time markets the price bid by the marginal unit just satisfying the last unit of forecast demand.

  • These payments may not cover all costs

that generators face and generators may participate in other markets to recoup their average total (fixed plus variable) costs.

19

slide-20
SLIDE 20

Regional Electricity Market

  • Because baseload units, especially

nuclear units, have low fuel costs relative to inframarginal (natural gas) units, they typically bid zero in the energy markets.

  • As baseload capacity is added, it

displaces marginal (higher priced generation) units & reduces the wholesale electricity price in the region.

20

slide-21
SLIDE 21

Regional Electricity Market

  • Because nuclear power is relatively

inexpensive to generate, adding nuclear baseload capacity drives down the prices for capacity and reserve otherwise provided by units that have higher fuel costs.

21

slide-22
SLIDE 22

Levelized Cost of Electricity

  • LCOE represents the constant (level) wholesale

price generators receive over the life of a power plant that is necessary to cover all operating expenses including taxes and provide an acceptable return to investors.

  • LCOE provides a uniform way to compare the

wholesale cost of energy across technologies because it takes into account the installed system price and associated costs such as financing, land, insurance, operation and maintenance and depreciation, among others.

22

slide-23
SLIDE 23

Levelized Cost of Electricity

  • LCOE is the net present value of total life

cycle costs of the power plant divided by the quantity of energy produced over the plant’s life.

  • Accounts for carbon costs, inflation,

returns to debt & equity (risk) & fuel escalation rates.

  • LCOE studies document wide variation

23

slide-24
SLIDE 24

LCOE Sensitivity Analysis

Sensitivity Of LCOE to +10% Parameter Changes

  • 10%
  • 8%
  • 6%
  • 4%
  • 2%

0% 2% 4% 6% 8% 10% c a p a c i t y c a p a c i t y f a c t

  • r

h e a t r a t e

  • v

e r n i g h t c

  • s

t i n c r e m e n t a l c a p i t a l c

  • s

t s f i x e d O & M c

  • s

t s v a r i a b l e O & M c

  • s

t s f u e l c

  • s

t w a s t e d i s p

  • s

a l d e c

  • m

m c

  • s

t i n f l a t i

  • n

r a t e O & M r e a l e s c a l a t i

  • n

r a t e f u e l r e a l e s c a l a t i

  • n

r a t e t a x r a t e d e b t f r a c t i

  • n

d e b t r a t e e q u i t y r a t e Percent Change Nuclear CCGT

24

slide-25
SLIDE 25

Nuclear Construction & Operational Cost Assumptions

AP1000: Advanced Pressurized Water Reactor

  • Once-through fuel cycle
  • 40-year economic life (see below for a 60-year economic life LCOE estimate)
  • Capacity factor: 90% (increased from Du and Parsons [2009] study with new information)
  • Heat rate: 10,400 Btu/kWh
  • Overnight cost in 2007 dollars: $4,000/kWe
  • O&M fixed costs: $56.44/kW/yr
  • O&M variable costs: 0.42 mills/kWh
  • O&M real escalation rate: 1%/yr
  • Incremental capital costs: $40/kW/yr
  • Fuel costs: $0.67/mmBtu
  • Inflation rate: 3%/yr
  • Real fuel escalation rate: 0.5%/yr
  • Tax rate: 37%
  • Construction period: 5 years
  • Financing:
  • Equity return: 15% nominal net of income taxes
  • Debt return: 8% nominal
  • Inflation: 3% annual
  • Income Tax rate (applied after expenses, interest & tax depreciation): 37%
  • Equity: 50%
  • Debt: 50%
  • Weighted Avg. cost of capital: 10%
  • Depreciation: 15-year MACRS schedule
  • Waste fee: 1 mill/kWh
  • Decommissioning cost: $700 million in 2007 dollars
  • Construction schedule: startup year - 5=10%, year - 4=25%, year - 3=31%, year - 2=25%, year - 1=10%

25

slide-26
SLIDE 26

CCGT Construction & Operational Cost Assumptions

Natural Gas CCGT

  • 40-year economic life
  • Capacity factor: 85%
  • Heat rate: 6,800 Btu/kWh
  • Overnight cost in 2007 dollars: $850/kWe
  • Incremental capital costs: $10.20/kWh/yr
  • O&M fixed costs: $12.65/kW/yr
  • O&M variable costs: 0.41 mills/kWh
  • O&M real escalation rate: 1%/yr
  • Fuel cost: $7.00/mmBtu
  • Inflation rate: 3%/yr
  • Real fuel cost escalation rate: 0.5%/yr
  • Tax rate: 37%
  • Construction period: 2 years, half in each year
  • Financing:
  • Equity return: 12% nominal net of income taxes
  • Debt return: 8% nominal
  • Inflation: 3%/yr
  • Income Tax rate: 37%
  • Equity: 40%
  • Debt: 60%
  • Weighted Avg. cost of capital: 7.8%
  • Depreciation: 15-year MACRS schedule (identical to the nuclear plant)
  • Carbon intensity: 14.5 kg-C/mmBtu
  • Carbon Cost: $0/tCO2
  • Construction schedule: startup year - 2=50%, year - 1=50%

26

slide-27
SLIDE 27

LCOE Values & Variations

  • These assumptions => $0.079/kWh for

nuclear & $0.065/kWh for CCGT

  • 60-year nuclear economic life =>

LCOEnuc=$0.076

  • 1.64% gas escalation rate => LCOEgas =

$0.079/kWh

  • $41.17/tCO2 tax => LCOEgas =

$0.079/kWh (RGGI price = $1.90/tCO2)

27

slide-28
SLIDE 28

Fuel Diversity

Source: Edison Electric Institute, May 2010.

28

slide-29
SLIDE 29

Fuel Diversity

  • Shannon-Weiner Index:

– pi is the proportional representation of option i in the portfolio under consideration

  • One considers a range of portfolios each

with a different combination of fuels &/or technologies

  • Taken together, these portfolios form an

efficient frontier of diversification choices

) ln(

1 i I i i a

p p

=

− = ∆

29

slide-30
SLIDE 30

Fuel Diversity

  • The efficiency frontier shows a range of

possible diversification choices that the region may adopt based on its preferences for certain fuels/technologies and risk.

  • ISO-NE’s 2007 study shows that adding

5,400 MWe of capacity from a single, non- gas technology does not change the region’s disproportionate dependence on gas.

30

slide-31
SLIDE 31

The RGGI

  • Ten states in 2005 formed a regional

carbon market.

  • RGGI capped CO2 production for 2009

through 2013 that will be reduced from 2014 through 2018 by 2.5% when CO2 production will be capped 10% below the initial cap.

  • Allowances auctioned and sold directly

are permission to produce one ton of CO2

31

slide-32
SLIDE 32

The RGGI

0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.95 1.00 1.05 2000 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10

Connecticut Other RGGI States

Source: RGGI

Index: 2000 = 1.00

Trend in CO2 Production for Connecticut and Other RGGI States

32

slide-33
SLIDE 33

The RGGI

  • As of the March 2011 auction, 346 million

transactions occurred since the 2009 start.

  • Cumulative proceeds amount to $860

million in the RGGI states.

  • RGGI distributes 91.5% of proceeds from

auctions to states.

33

slide-34
SLIDE 34

The RGGI

51.6% 69.5% 10.7% 23.0%

0% 20% 40% 60% 80% 100% Region Connecticut

Energy Efficiency Renewable Energy Other GHG Reduction Programs Direct Energy Bill Assistance Program Admin. State Budget Deficit Reduction

Source: RGGI, Inc. http://www.rggi.org/docs/Investment_of_RGGI_Allowance_Proceeds.pdf

4.5% 17.4% 14.1% 1.1% 4.8%

Allocation of Auction Proceeds by Categories, 2009

34

slide-35
SLIDE 35

Takeaways

  • LR economic impacts are small (~1%)

– Large in construction period – Most conservative assumptions

  • Region’s heavy dependence on gas is not

changed with a single 1,000 MWe addition.

– Fuel diversity not impacted until we displace 6,000 Mwe

  • Price of gas ↑ makes nuclear relatively

attractive.

– But, no competitive disadvantage to CT

  • RGGI raised CT costs but increased efficiency

and alt. energy deployment (CCEF & CEEF).

35

slide-36
SLIDE 36

Thank you! Questions???

36