The Introduction of Lungmen Lungmen The Introduction of Nuclear Power Plant Nuclear Power Plant Department of Nuclear Regulation Department of Nuclear Regulation Atomic Energy Council, R.O.C. Atomic Energy Council, R.O.C. 1 1 Outline


slide-1
SLIDE 1

Department of Nuclear Regulation Department of Nuclear Regulation Atomic Energy Council, R.O.C. Atomic Energy Council, R.O.C.

The Introduction of The Introduction of Lungmen Lungmen Nuclear Power Plant Nuclear Power Plant

1 1

slide-2
SLIDE 2

Outline Outline

  • The current status of LMNPP

The current status of LMNPP

  • Licensing and Inspection Activities

Licensing and Inspection Activities

  • The unusual events during

The unusual events during construction construction

  • Major observation by authority

Major observation by authority

  • Conclusion

Conclusion

2 2

slide-3
SLIDE 3

The Current Status of LMNPP The Current Status of LMNPP

3 3

slide-4
SLIDE 4

Progress of Progress of Lungmen Lungmen Project Project

Lungmen Project proposed 1980 GE ABWR Awarded 1996.6 Construction Permit issued 1999.3 Lungmen Lungmen Project Project Suspended by Suspended by DPP government DPP government 2000.10 Lungmen Project Resumed 2001.2 First Concrete pouring 2006.10 2005.3 Unit 1 RPV Sitting Unit 2 RPV Sitting 2007.7 161kV Energized (only partial electric distribution systems installed)

Present

2008.11 Unit 1 RPV Hydro test Pre-op tests start 2009.7 2010.4 ECCS Pre-op 2010.8 FIV

4 4

slide-5
SLIDE 5

Turbine Building Access Control Building Radwaste Building Auxiliary Fuel Building Rx Building Control Building Switchyard

N

Pump House

Birdview Birdview of Power Block

  • f Power Block

5 5

slide-6
SLIDE 6

Reactor Building Reactor Building

6 6

slide-7
SLIDE 7

Control Building Control Building

7 7

slide-8
SLIDE 8

Turbine Building Turbine Building

8 8

slide-9
SLIDE 9

Auxiliary Fuel Building Auxiliary Fuel Building

9 9

slide-10
SLIDE 10

Radiwaste Radiwaste Building Building

10 10

slide-11
SLIDE 11

RCCV FMCRD Reactor Internal Pump Main Control Room Reactor Pressure Vessel Turbine & Generator ECCS

Cut Cut-

  • away view

away view

11 11

slide-12
SLIDE 12

Reactor Building Reactor Building

BASE MAT

SUPPRESSION POOL ACCESS TUNNEL WET WELL

VACUUM BREAKER * 8

RPV LOWER DRYWELL HORIZ. VENT SRV MSIV

PRIMARY CONTAINMENT BOUNDARY SECOND CONTAINMENT BOUNDARY

CLEAN ZONE CLEAN ZONE

DRYWELL CONNECTING VENT * 10 FUEL POOL D/S POOL PRIMARY CONTAINMENT VESSEL

ACCESS

DRYWELL HEAD

UPPER DRYWELL

12 12

slide-13
SLIDE 13

Main Control Room Main Control Room

MCC (Main Control Console) Alarm Indication WDP (Wide Display Panels) Fixed Mimic Display Large Variable Display Video Display Unit Hard Switch Panels

SSC( Shift Supervisor Console)

Plant status tiles

Raised Floor Raised Floor

13 13

slide-14
SLIDE 14

Process Screen Process Screen

Overla y

14 14

slide-15
SLIDE 15

15 15

Current Status Current Status

The Lungmen progress issued by Taipower Company

(TPC) as follows: (As of 8/31/ 2013) Total Accumulated Progress(%)

Category

(weight)

Design (19%) Procurement (15%) Construction (58%) Startup* (8%) Total (100%)

Unit 1 Unit 1

99.77 100 97.70 63.63 95.71 91.5

Unit 2 Unit 2

98.96 100 96.72 20.00

*Numbers under startup represent initial test activities (Post Construction Test, Pre-op test, procedures preparation)

slide-16
SLIDE 16

16 16

Current Status of #1 Current Status of #1 -

  • Construction

Construction

 

The construction of The construction of Lungmen Lungmen Project has Project has almost completed. But there are still some almost completed. But there are still some deficiencies that should be improved, such as: deficiencies that should be improved, such as: The 18 construction improvement action items The 18 construction improvement action items

 

Currently Currently Lungmen Lungmen Project are working on the Project are working on the 18 construction improvement action items to fix 18 construction improvement action items to fix the identified problems, including those of the identified problems, including those of RCCV liner, surface mounting plate, cable tray RCCV liner, surface mounting plate, cable tray seismic enhancement, and fire protection. seismic enhancement, and fire protection.

slide-17
SLIDE 17

17 17

 

126 systems are to be tested 126 systems are to be tested

 

Currently, 119 systems have been fully Currently, 119 systems have been fully turned over and 7 partially turned over for turned over and 7 partially turned over for pre pre-

  • operational testing
  • perational testing

 

In terms of pre In terms of pre-

  • op test procedures, there
  • p test procedures, there

are 308 procedures that should be are 308 procedures that should be finished before fuel loading, 19 under finished before fuel loading, 19 under execution, 173 execution, 173( (56 % 56 % ) ) finished testing finished testing and are reviewed by SORC and are reviewed by SORC

Current Status of #1 Current Status of #1 -

  • Testing

Testing

slide-18
SLIDE 18

ECCS ECCS-

  • HPCF C

HPCF C

18 18

slide-19
SLIDE 19

LPFL C LPFL C LPFL A LPFL A

ECCS ECCS-

  • LPFL

LPFL

19 19

slide-20
SLIDE 20

20 20

Pre-FIV Post-FIV Inspection

Flow Induced Vibration Test Flow Induced Vibration Test

slide-21
SLIDE 21

21 21

JNES JNES NRC NRC

International Cooperation International Cooperation

slide-22
SLIDE 22

22 22

 

For the 308 pre For the 308 pre-

  • op test procedures, there
  • p test procedures, there

are 187 pre are 187 pre-

  • op test reports which should
  • p test reports which should

be submitted to AEC, and 65 reports have be submitted to AEC, and 65 reports have been submitted. been submitted.

 

Because of the 2 Because of the 2-

  • stage system Turnover

stage system Turnover

  • f
  • f Lungmen

Lungmen Project, the pre Project, the pre-

  • op testing
  • p testing

had been progressing partly and had had been progressing partly and had lasted for a long time. lasted for a long time. Therefore, the Therefore, the public still query the effectiveness of the public still query the effectiveness of the pre pre-

  • op testing.
  • p testing.

Current Status of #1 Current Status of #1 – – Testing Testing (cont.)

(cont.)

slide-23
SLIDE 23

23 23

For verifying system function integrity and reliability, TPC promised to perform pre-op re-test for systems finishing pre-

  • p test and approved, except ones that

can’t re-build the test conditions in 2013.

TPC calls senior engineers from other 3 NPPs to form the Reinforced Safety Evaluation Task Force, to perform turn-

  • ver package review, walkdown, and pre-
  • p re-test

Current Status of #1 Current Status of #1 – – Testing Testing (cont.)

(cont.)

slide-24
SLIDE 24

24 24

The duties of Reinforced Safety Evaluation Task Force are reviewing the system turnover package and auditing the re-test.

Both of the pre-op test reports should be submitted to AEC. The first one is reference materials; the other is the formal documents.

Currently, 60 pre-op re-test procedures have been fully completed.

Current Status of #1 Current Status of #1 – – Testing Testing (cont.)

(cont.)

slide-25
SLIDE 25

Current Status of #1 Current Status of #1 – – Improvement Action Items Improvement Action Items

The results of Post-Fukushima Safety Evaluation requires Lungmen to perform seismic and tsunami simulations, add two gas turbine generators, sea wall, and spent fuel pool instrumentation, … etc.

25 25

slide-26
SLIDE 26

26 26

Fuel Loading Permit Fuel Loading Permit

AEC required TPC to complete 75 tasks, including the approval of System Function Test Reports, before applying the fuel loading permit

slide-27
SLIDE 27

Licensing and Inspection Licensing and Inspection Activities Activities

27 27

slide-28
SLIDE 28

Basic Regulatory Laws Basic Regulatory Laws

  • Nuclear Reactor Facilities Regulation Act

Nuclear Reactor Facilities Regulation Act

Article 5 Article 5

For the construction of nuclear reactor facilities, an For the construction of nuclear reactor facilities, an application for application for construction permit construction permit shall be filed with the shall be filed with the competent authorities, and the construction shall not competent authorities, and the construction shall not commence until the application has been reviewed and commence until the application has been reviewed and approved by the competent authorities to meet with the approved by the competent authorities to meet with the following standards and requirements and the competent following standards and requirements and the competent authorities have issued a construction permit authorities have issued a construction permit… …

28 28

slide-29
SLIDE 29

Basic Regulatory Laws (cont.) Basic Regulatory Laws (cont.)

Article 6 Article 6

Even after the completion of construction of nuclear reactor Even after the completion of construction of nuclear reactor facilities, the facilities facilities, the facilities shall not be loaded with the nuclear shall not be loaded with the nuclear fuel, unless the competent authorities have reviewed and fuel, unless the competent authorities have reviewed and approved its final safety analysis report approved its final safety analysis report, and the corrective , and the corrective actions of inspection findings during the construction and actions of inspection findings during the construction and the system functional tests thereof have been passed the system functional tests thereof have been passed.

.

Unless the competent authorities have Unless the competent authorities have reviewed and reviewed and approved the power test approved the power test therefore and then issued an an

  • perating license
  • perating license therefore, no nuclear reactor facilities,

therefore, no nuclear reactor facilities, having been loaded with the nuclear fuel, shall be formally having been loaded with the nuclear fuel, shall be formally

  • perated.
  • perated.

29 29

slide-30
SLIDE 30

Basic Regulatory Laws (cont.) Basic Regulatory Laws (cont.)

Article 14 Article 14

During the construction or the operation period of nuclear reactor facilities, the competent authorities may dispatch the the competent authorities may dispatch the inspector to inspect the facilities at anytime inspector to inspect the facilities at anytime, , and may require the licensee to submit relevant materials; wherein, the licensee shall not evade, interfere with or refuse the same. If there is anything not conform to the prescription or if the public health/safety or environmental ecology may be endangered, the competent authorities shall order the licensee to improve the situation or take any other necessary measures within a prescribed time period. If the situation is serious, the licensee does not improve it nor take necessary measures within the prescribed period, the competent authorities may order the licensee to cease the working on cease the working on the scene, or operation thereof, or may revoke the license or the scene, or operation thereof, or may revoke the license or permit the operation only under a limited power. permit the operation only under a limited power. … …. .

30 30

slide-31
SLIDE 31
  • A two-step licensing review process is

adopted for nuclear plant in Taiwan.

  • For Lungmen Project, a construction

permit was issued following a preliminary safety analysis report (PSAR) being satisfactorily reviewed in March 1999.

  • AEC started the construction inspection,

including resident inspection, after issuing construction permit.

The Process of licensing to LMNPP

31 31

slide-32
SLIDE 32
  • Taipower Company submitted first version
  • f FSAR in August 2007 for AEC’s review.
  • After over 3 years of review, AEC is

currently preparing a draft safety evaluation report (SER).

  • AEC will conduct readiness inspections

for Lungmen plant to confirm the FSAR commitment before issuing fuel loading permit.

The Process of licensing to The Process of licensing to LMNPP LMNPP (cont.)

(cont.)

32 32

slide-33
SLIDE 33

1st check point

The Process of licensing to LMNPP

Site selection Preliminary design (PSAR)

Construction, PCT, Pre-OP Start-up testing

FSAR TPC AEC

N O W

2nd check point 3rd check point 4th check point

Review PSAR Issue PSAR SER Issue Construction License Review FSAR Issue FSAR SER Review 75 tasks Issue Fuel loading permit Review Startup testing Report Issue Operation License

33 33

slide-34
SLIDE 34
  • As plant operators play a key role in their

dynamic responses to normal operations and anomalies, their qualification and ability are among the main themes for nuclear safety.

  • Plant operators and senior operators are

required to pass stringent tests, including written examination, plant walk-through and simulator operation, before they are allowed to work at the main control room of the plant.

The Qualification of The Qualification of LMNPP LMNPP’ ’s s Operator Operator

34 34

slide-35
SLIDE 35

Construction Tests Pre-Operational Tests Startup Tests

  • Construction Program Inspection
  • Design Change Process Inspection
  • Construction testing Inspection
  • Pre-Op Testing Inspection
  • Operation Program Inspection
  • Lo-Power testing Inspection
  • Power ascension Insp.
  • Operation Readiness Inspection
  • Operation Readiness Insp.
  • ROP transition Insp.

Construction Inspection Framework Construction Inspection Framework

(Initial Test Program)

Construction

Post Construction Test Pre-Op Test Startup Test

Phase Ⅰ Phase Ⅱ Phase Ⅲ Commercial

(Construction / Installation/ Test Procedure ) (Startup Administrative Manual, SAM) (In-service Procedure)

JTG

TPC Nuclear Project Quality Assurance Program

The Taipower Nuclear Operation Quality Assurance Program

Construction Office LMNPP 35 35

slide-36
SLIDE 36

Overview of Regulatory Activities Overview of Regulatory Activities

(1) Routine Inspection (1) Routine Inspection

The resident inspection, periodic inspection, and The resident inspection, periodic inspection, and special taskforce inspection special taskforce inspection

(2) Quality Control Inspection (2) Quality Control Inspection

TPC NED,NSD, and AE TPC NED,NSD, and AE--

  • -S&W , etc

S&W , etc

(3) Quality Inspection of Contractors /Vendors (3) Quality Inspection of Contractors /Vendors

  • Domestic Contractors /Vendors

Domestic Contractors /Vendors – –New Asia Co., New Asia Co., CSBC, and CTCI, etc CSBC, and CTCI, etc

  • Oversea Contractors/Vendors

Oversea Contractors/Vendors --

  • - Hitachi, IHI, and

Hitachi, IHI, and Toshiba, etc. (Japan) Toshiba, etc. (Japan) General General Electric,DRS Electric,DRS, and Invensys , etc. (USA) , and Invensys , etc. (USA)

36 36

slide-37
SLIDE 37

(4) Safety Analysis Review (4) Safety Analysis Review

  • Review of 119 follow

Review of 119 follow-

  • up items of PSAR

up items of PSAR

  • Review of PSAR Amendments, and

Review of PSAR Amendments, and

  • Review of FSAR.

Review of FSAR.

(5) (5) Lungmen Lungmen Regulatory Meeting Regulatory Meeting (6) (6) Other Special Regulatory Activities Other Special Regulatory Activities

  • Review of Seismic Analysis

Review of Seismic Analysis

  • digital I & C

digital I & C

Overview of Regulatory Activities Overview of Regulatory Activities (cont.)

(cont.)

37 37

slide-38
SLIDE 38

Place Place: :Job Site of Job Site of LMNPP LMNPP Activity Activity: :Periodic Periodic inspection, special inspection, special taskforce inspection taskforce inspection

38 38

slide-39
SLIDE 39

Place Place: :Toshiba/ Toshiba/ IHI Factory IHI Factory (Japan) (Japan) Activity Activity: :Quality Quality Inspection of Inspection of Overseas Vendors Overseas Vendors

39 39

slide-40
SLIDE 40

Place Place: :CTCI & CSBC CTCI & CSBC Factory Factory Activity Activity: :Quality Quality Inspection of Inspection of Domestic Vendors Domestic Vendors

40 40