The Introduction of Lungmen Lungmen The Introduction of Nuclear - PowerPoint PPT Presentation

The Introduction of Lungmen Lungmen The Introduction of Nuclear Power Plant Nuclear Power Plant Department of Nuclear Regulation Department of Nuclear Regulation Atomic Energy Council, R.O.C. Atomic Energy Council, R.O.C. 1 1 Outline


  1. The Introduction of Lungmen Lungmen The Introduction of Nuclear Power Plant Nuclear Power Plant Department of Nuclear Regulation Department of Nuclear Regulation Atomic Energy Council, R.O.C. Atomic Energy Council, R.O.C. 1 1

  2. Outline Outline • The current status of LMNPP • The current status of LMNPP • Licensing and Inspection Activities • Licensing and Inspection Activities • The unusual events during • The unusual events during construction construction • Major observation by authority • Major observation by authority • Conclusion • Conclusion 2 2

  3. 3 3 The Current Status of LMNPP The Current Status of LMNPP

  4. Progress of Lungmen Lungmen Project Project Progress of 1980 Lungmen Project proposed 1996.6 GE ABWR Awarded 1999.3 Construction Permit issued Lungmen Project Project Lungmen First Concrete pouring 2000.10 Suspended by Suspended by DPP government DPP government 2006.10 Unit 2 RPV Sitting 2001.2 Lungmen Project Resumed Unit 1 RPV 2005.3 2008.11 Hydro test Unit 1 RPV Sitting 2007.7 ECCS Pre-op 161kV Energized (only 2010.4 FIV partial electric distribution 2009.7 systems installed) 2010.8 Pre-op tests start Present 4 4

  5. Rx Building Switchyard Radwaste Building Control Building Auxiliary Fuel Building Turbine Building N Pump House Access Control Building Birdview of Power Block of Power Block Birdview 5 5

  6. Reactor Building Reactor Building 6 6

  7. Control Building Control Building 7 7

  8. Turbine Building Turbine Building 8 8

  9. Auxiliary Fuel Building Auxiliary Fuel Building 9 9

  10. Radiwaste Building Building Radiwaste 10 10

  11. Cut- -away view away view Cut Turbine & Generator Reactor Pressure Vessel RCCV Main Control Room Reactor ECCS Internal FMCRD Pump 11 11

  12. Reactor Building Reactor Building SECOND CONTAINMENT BOUNDARY DRYWELL CONNECTING VENT * 10 PRIMARY CONTAINMENT VESSEL DRYWELL HEAD D/S POOL FUEL POOL SRV CLEAN MSIV ZONE UPPER DRYWELL RPV ACCESS CLEAN VACUUM BREAKER * WET WELL ZONE 8 ACCESS TUNNEL LOWER SUPPRESSION DRYWELL POOL HORIZ. BASE MAT PRIMARY CONTAINMENT 12 12 VENT BOUNDARY

  13. Main Control Room Main Control Room Alarm Large Indication Variable Fixed Mimic Display WDP (Wide Display Panels) Display Plant status tiles MCC (Main Control Video Console) Hard Switch SSC( Shift Supervisor Raised Floor Raised Floor Display Unit Panels Console) 13 13

  14. 14 14 Overla y Process Screen Process Screen

  15. Current Status Current Status The Lungmen progress issued by Taipower Company (TPC) as follows: (As of 8/31/ 2013 ) Total Accumulated Progress(%) Category Design Procurement Construction Startup* Total (19%) (15%) (58%) (8%) (100%) (weight) 99.77 100 97.70 63.63 95.71 Unit 1 Unit 1 98.96 100 96.72 20.00 91.5 Unit 2 Unit 2 *Numbers under startup represent initial test activities (Post Construction Test, Pre-op test, procedures preparation) 15 15

  16. Current Status of #1 - - Construction Construction Current Status of #1 The construction of Lungmen Lungmen Project has Project has The construction of   almost completed. But there are still some almost completed. But there are still some deficiencies that should be improved, such as: deficiencies that should be improved, such as: The 18 construction improvement action items The 18 construction improvement action items Currently Lungmen Lungmen Project are working on the Project are working on the Currently   18 construction improvement action items to fix 18 construction improvement action items to fix the identified problems, including those of the identified problems, including those of RCCV liner, surface mounting plate, cable tray RCCV liner, surface mounting plate, cable tray seismic enhancement, and fire protection. seismic enhancement, and fire protection. 16 16

  17. Current Status of #1 - - Testing Testing Current Status of #1 126 systems are to be tested 126 systems are to be tested   Currently, 119 systems have been fully Currently, 119 systems have been fully   turned over and 7 partially turned over for turned over and 7 partially turned over for pre- -operational testing operational testing pre In terms of pre- -op test procedures, there op test procedures, there In terms of pre   are 308 procedures that should be are 308 procedures that should be finished before fuel loading, 19 under finished before fuel loading, 19 under ( 56 % ) execution, 173 ( 56 % ) finished testing execution, 173 finished testing and are reviewed by SORC and are reviewed by SORC 17 17

  18. 18 18 -HPCF C HPCF C ECCS- ECCS

  19. 19 19 LPFL C LPFL C -LPFL LPFL ECCS- ECCS LPFL A LPFL A

  20. Flow Induced Vibration Test Flow Induced Vibration Test Pre-FIV Post-FIV Inspection 20 20

  21. 21 21 International Cooperation International Cooperation NRC NRC JNES JNES

  22. Current Status of #1 – – Testing Testing (cont.) Current Status of #1 (cont.) For the 308 pre- -op test procedures, there op test procedures, there For the 308 pre   are 187 pre- -op test reports which should op test reports which should are 187 pre be submitted to AEC, and 65 reports have be submitted to AEC, and 65 reports have been submitted. been submitted. Because of the 2- -stage system Turnover stage system Turnover Because of the 2   of Lungmen Lungmen Project, the pre Project, the pre- -op testing op testing of had been progressing partly and had had been progressing partly and had lasted for a long time. Therefore, the Therefore, the lasted for a long time. public still query the effectiveness of the public still query the effectiveness of the pre- -op testing. op testing. pre 22 22

  23. Current Status of #1 – – Testing Testing (cont.) Current Status of #1 (cont.) For verifying system function integrity  and reliability, TPC promised to perform pre-op re-test for systems finishing pre- op test and approved, except ones that can’t re-build the test conditions in 2013. TPC calls senior engineers from other 3  NPPs to form the Reinforced Safety Evaluation Task Force, to perform turn- over package review, walkdown, and pre- op re-test 23 23

  24. Current Status of #1 – – Testing Testing (cont.) Current Status of #1 (cont.) The duties of Reinforced Safety  Evaluation Task Force are reviewing the system turnover package and auditing the re-test. Both of the pre-op test reports should be  submitted to AEC. The first one is reference materials; the other is the formal documents. Currently, 60 pre-op re-test procedures  have been fully completed. 24 24

  25. Current Status of #1 Current Status of #1 – Improvement Action Items Improvement Action Items – The results of Post-Fukushima  Safety Evaluation requires Lungmen to perform seismic and tsunami simulations, add two gas turbine generators, sea wall, and spent fuel pool instrumentation, … etc. 25 25

  26. Fuel Loading Permit Fuel Loading Permit AEC required TPC to complete 75 tasks,  including the approval of System Function Test Reports, before applying the fuel loading permit 26 26

  27. 27 27 Licensing and Inspection Licensing and Inspection Activities Activities

  28. Basic Regulatory Laws Basic Regulatory Laws  Nuclear Reactor Facilities Regulation Act  Nuclear Reactor Facilities Regulation Act Article 5 Article 5 For the construction of nuclear reactor facilities, an For the construction of nuclear reactor facilities, an application for construction permit construction permit shall be filed with the shall be filed with the application for competent authorities, and the construction shall not competent authorities, and the construction shall not commence until the application has been reviewed and commence until the application has been reviewed and approved by the competent authorities to meet with the approved by the competent authorities to meet with the following standards and requirements and the competent following standards and requirements and the competent authorities have issued a construction permit… … authorities have issued a construction permit 28 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.