TfL update on Ludgate Circus Stuart Reid, TfL Interim Director of - - PowerPoint PPT Presentation

tfl update on ludgate circus
SMART_READER_LITE
LIVE PREVIEW

TfL update on Ludgate Circus Stuart Reid, TfL Interim Director of - - PowerPoint PPT Presentation

TfL update on Ludgate Circus Stuart Reid, TfL Interim Director of Vision Zero Vision Zero our targets Short term: Medium term: Long term: TARGETS 65% reduction in 70% reduction in Zero KSIs by KSIs by 2022 KSIs by 2030 2041 against


slide-1
SLIDE 1

TfL update on Ludgate Circus

Stuart Reid, TfL Interim Director of Vision Zero

slide-2
SLIDE 2

Vision Zero – our targets

Short term: 65% reduction in KSIs by 2022 against the 2005-09 baseline Medium term: 70% reduction in KSIs by 2030 against the new 2010-14 baseline Long term: Zero KSIs by 2041 Bus casualty targets:

  • 1. 70% reduction in KSIs in, or by,

buses by 2022 against 2005-09 baseline

  • 2. No one killed in, or by, a bus by

2030 TARGETS

slide-3
SLIDE 3

Rationale for the current design at Ludgate Circus

Cycle flows at Ludgate Circus – March 2017 Morning Peak (0700- 0930) Southbound 900 Northbound 1990 Evening Peak (16:00 – 19:00) Southbound 1580 Northbound 925

slide-4
SLIDE 4
  • Collective partnership between TfL and

the City of London

  • Recognising the importance of reducing

waiting time for pedestrians as much as possible

  • Changing the signal timings to encourage

pedestrians to cross safely

Finding the right safety solution

slide-5
SLIDE 5
  • Removing east-west movements

turning south into New Bridge Street would allow one of the most critical crossings to run in parallel with traffic and remove traffic from this bus corridor.

  • Restricting turning movements

could make a real difference to the pedestrian crossing experience.

Our proposals to improve road safety at Ludgate Circus

slide-6
SLIDE 6
  • Diverted traffic from Ludgate Hill

could travel to Blackfriars Bridge via Queen Victoria Street where there is spare green

Our proposals to improve road safety at Ludgate Circus

slide-7
SLIDE 7

Timescales for delivery of the new proposals

  • Safety is always our number one

priority

  • We are currently going through that

design process which when complete will to go to our contractors for installation.

  • We will aim to have these works

completed within 3 months and will continue to update City officers and Members on progress

slide-8
SLIDE 8

Questions?