SLIDE 1
TENNESSEE DEPT OF TRANSPORTION I-40/I-240 INTERCHANGE IMPROVEMENTS
SLIDE 2
Began Phase II plans - August 2006. Traffic Analysis for Weaving - December 2006. Traffic Queue analysis at Covington Pike - May 2007 Revised plans - June 2007 Update technical data for I.M.S. - 2008 Project limits extended - October 2011 Complete ROW plans - October 2012 Construction Plans - Underway
I-40/I-240 INTERCHANGE
SLIDE 3
Phase I of project. Added flyover WB I-40 (east) to
WB I-240. Added portion of ramp from WB I-40 to WB I- 40 (north)
SLIDE 4
Phase II-A - Complete ramp structure from WB I-40 (east) to WB I-40 (north). Add ramp from EB I-40 (north) to EB I-40 (east).
SLIDE 5
Phase II-A - Complete ramp structure from WB I-40 (east) to WB I-40 (north). Add ramp from EB I-40 (north) to EB I-40 (east).
SLIDE 6
Phase II-B (Now Phase III)
– Reconstruct interchange to add through lanes from I-40 (north) to I-240.
SLIDE 7
Phase II-B (Now Phase III)
– Repurpose existing roadways to serve as Collector- Distributor (CD) roads for ramps
SLIDE 8
Level of Service Traffic Analysis
– AM and PM peaks – I-40 east & north – I-240 – Covington Pike – Sam Cooper – All associated ramps
SLIDE 9
Findings for New “Phase II” and “Phase III” Freeway Sections
– I-240 WB & EB unsatisfactory (LOS E or F) by 2016 – I-40 WB (east) unsatisfactory by 2015 – Weaving sections okay but marginal – Ramp Junctions have merge/diverge problems in near future
SLIDE 10
Current Design Phase II
SLIDE 11
I-240 Addition of one (1) auxiliary lane on both east and west sides
SLIDE 12
Widen existing bridge over Greenway
SLIDE 13
Relocate Ramp from EB I-240 to EB I-40 and widen to three (3) lanes
SLIDE 14
Widen Ramps from EB I-40 (east) prior to split to four (4) lanes.
SLIDE 15
I-40 (North) - Widen existing WB I-40 bridge over Summer Avenue
SLIDE 16
Ramp to be improved and remain open for local access from WB I-40 (east) to Summer Avenue
SLIDE 17
Ramp from Summer Ave to be relocated east to allow for construction of other ramps
SLIDE 18
Ramp from WB I-40 (north) to be relocated east to allow for construction of auxiliary lanes
SLIDE 19
Construct Ramp from EB I-40 (north) to EB I-40 (east) and relocate entrance
SLIDE 20
Complete Ramp from WB I-40 (east) to WB I-40 (north)
SLIDE 21
Frontage Road relocated east and access to Summer Avenue relocated east
SLIDE 22
Sam Cooper Boulevard – Addition of one (1) lane in both the EB and WB directions. Requires a design exception be requested due to substandard shoulder widths.
SLIDE 23
I-40 (East) - Addition of auxiliary lane EB I-40 from Relocated Ramp to existing lane addition near Sycamore View Road
SLIDE 24
I-40 (East) -Addition of two (2) auxiliary lane WB
SLIDE 25
I-40 (East) -Replace Wolf River Bridge.
SLIDE 26
I-40 (North) - Add two (2) auxiliary lanes from up to Covington Pike Interchange.
SLIDE 27
I-40 (North) - Replace Covington Pike Bridge to accommodate auxiliary lanes
SLIDE 28
I-40 (North) - Continue an additional auxiliary lane WB from Covington Pike
SLIDE 29
Covington Pike Interchange - Widen Covington Pike to allow for dual left turn onto EB I-40 entrance Ramp
SLIDE 30
Covington Pike Interchange - Widen EB I-40 entrance Ramp to allow for a dual-left turn lane.
I-40/I-240 INTERCHANGE
SLIDE 31
Covington Pike Interchange - Widen and shift exit ramp EB I-40 to Covington Pike to provide additional queue storage space off I-40.
I-40/I-240 INTERCHANGE
SLIDE 32
Covington Pike Interchange - Widen Ramp from WB I-40 (north) to Covington Pike. Add exclusive right-turn lane and additional queue storage
I-40/I-240 INTERCHANGE
SLIDE 33
I-40/I-240 INTERCHANGE
SLIDE 34
I-40/I-240 INTERCHANGE
Current Design
SLIDE 35
I-40/I-240 INTERCHANGE