Synopsis of EToN 6 Technical Specification
Ken Hickson Chairman – Symology Ltd. On behalf of the EToN Developers Group
Technical Specification Ken Hickson Chairman Symology Ltd. On - - PowerPoint PPT Presentation
Synopsis of EToN 6 Technical Specification Ken Hickson Chairman Symology Ltd. On behalf of the EToN Developers Group EToN 6 Topics Inspections Section 81 Defective Apparatus Temporary Traffic Signals Applications Permit
Ken Hickson Chairman – Symology Ltd. On behalf of the EToN Developers Group
Inspections Section 81 – Defective Apparatus Temporary Traffic Signals Applications Permit Applications Modification Request Section 85 – Diversionary Works Rationalising Charge Category Codes Forward Planning Information Extended use of Attachments Other Enhancements Introduction Timetable
Only send inspections in support of…
FPN / Prosecution S74 / S74A charges
So no “Complies with conditions” outcome
Works Stopped Works in progress Works in progress – No carriageway incursion Works Stopped – Apparatus remaining Non-Compliant (with Conditions)
“Works Stopped” would only be sent if Stop notice was late Always classed as “Routine” Optional Location (point) + Attachments
Considerations / Limitations
Inconsistent practices adopted throughout the
No legal requirement on timing
Two new transactions:
Temporary Traffic Signal Application Temporary Traffic Signal Application Response
Transactions are exchanged solely between works
Application responses directly cross-reference
Notice may be given at any point after the first notice
Forward Planning notice Section 54 notice / PAA Application Section 55 notice / Permit Application Section 57 notice Actual Start Permit variation
Independent of existing noticing rules Should contain enough information for majority of
Inherits basic data elements, e.g. works description, from
existing notifications thereby reducing re-entry of information
Contact information
Signal supplier Emergency contact
Signal Configuration
2-way no junction 2-way with junction Multi-way See attached plan
Type of signal approval sought
For information, approval assumed Request Approval Request Design and Approval
Signal Operating pattern
Working Day 24 Hour Overnight Off peak Multiple configurations
500 characters free text Attachments for plans, maps and diagrams.
Approved Not approved
Following a Modification Request, the response period for the
subsequent modified permit application will be the later of:
the original application response period 2 days, starting from when the Modification Request is
received
An early start agreement on the subsequent application will
not be required
The above rules only apply if the modified application is for
the same Start/End dates as the original; otherwise it is treated as a new application, in the same way as following a refusal
The original application will not “deem” under any
circumstances, once a Modification Request is sent
Regulation 16(3)
“If a Permit Authority does not grant or refuse a
Approach
Where the Primary Notice Authority gives a
New notice
“Modification Request”. Notice can be used to
Changes to existing notices
“Refuse Permit / PAA / Variation”
Data Elements
Conditions (complete replacement if supplied) Attachments
May be cancelled if works not proceeding Updated notice may be sent if details change Section 85 Condition expires on the date
“GetRestrictions” transaction response now
Street Authority for USRN lists all authority
Works involving excavation (single promoter) Works involving excavation (collaborative working, primary promoter) Works in footpath or bridleway Works in a highway in relation to which a pedestrian planning order is in place Works in a highway whose use by vehicular traffic is prohibited by a traffic order (that applies at all times) Laying apparatus only (collaborative works, secondary promoter) Works for road purposes carried out on behalf of a highway authority Replacing poles, lamps, columns or signs in the same location Pole testing Repairing, resetting or replacing manhole or chamber covers or frames Works in non-traffic-sensitive streets that require opening of the highway, but not breaking it up Other works not involving excavation
Replacing poles, lamps, columns or signs in the same location Pole testing Repairing, resetting or replacing manhole or chamber covers or frames Other works not involving excavation Culvert/Ditch/Tunnel work – no excavation Open Cut/Machine Cut Road Breaker Minimum Dig/Thrust Boring Slab Working Other works involving excavation The codes in red are new codes to assist in providing the data required for permit applications
Works in footpath or bridleway Works in a highway in relation to which a pedestrian planning
Works in a highway whose use by vehicular traffic is prohibited by a traffic order (that applies at all times) Ideally, this data would be on the gazetteer/ASD, but the code was retained, because it was thought unlikely that the data would be provided
Attachments added to:
Works Stop Works / FPN Comments Directions and Permit Responses (except Grant) Intention to Issue S50 Licence Unattributable Works
Added Compulsory Attachment Description Support for .docx (Word) & .odt (OpenOffice) Retain one year after most recent notification or
Flag indicating works are within a Restriction Conditions added to Works Data Variation
Complete replacement or no change
Added “No carriageway incursion” Carriageway
Existing “None / signing only” becomes “Some
carriageway incursion”
Still supply most severe for the duration of the phase
Barhole Registration extended to cover Pole Testing
Removed Legacy NSG Format Specification