Team Hindalco Welcomes You All
Hindalco Industries Limited, Renukoot
Team Hindalco Welcomes You All Hindalco Industries Limited, - - PowerPoint PPT Presentation
Team Hindalco Welcomes You All Hindalco Industries Limited, Renukoot Team Member 1. Mr. Anuj Kumar Verma 2. Mr. Vivek Agrawal 2 Hindalco Industries Limited, Renukoot Aspect of Energy Saving Ensuring Energy Security. Climate
Hindalco Industries Limited, Renukoot
Hindalco Industries Limited, Renukoot
2
Hindalco Industries Limited, Renukoot
3
Hindalco Industries Limited, Renukoot
4
Hindalco Renukoot – Profile & Process introduction Background of the Project Concept of the Project Innovation in the Project Project Savings & Economics Challenges faced in implementation Measurement and Verification Potential for Horizontal Application Estimated Life of the Project
Hindalco Industries Limited, Renukoot
5
Hindalco, the flagship company of the Aditya Birla Group and industry leader in aluminium and copper has consolidated turnover of US$17 billion & having footprint in 13 countries outside India. Finish Product Aluminium
Bauxite
Alumina Captive Power
800 MW
Hindalco-Renukoot: Fully integrated Operation
Hindalco Industries Limited, Renukoot
6
ALUMINA
BAUXITE
RED MUD STORAGE
ASH STORAGE
COAL
Power
WATER
Mud Cake Steam
Condensate
Slurry
Hindalco Industries Limited, Renukoot
7
“Caring for Energy…………….”
Hindalco Industries Limited, Renukoot
8
LTD Unit-II 145 OC Flash Tank
HTD Unit-I 245 OC HTD Unit- III 245 OC
HTD Unit- IV 245 OC
Pressure decanter Bauxite Slurry
HRD
DCW
Mud To washer
Precipita- tion Calcina- tion
Alumina To smelter
Evaporation-III Evaporation-I Evaporation-IV Evaporation-II
Steam: ~60 TPH Steam Steam FO
Spent Liquor Strong Liquor Kelly Press Spent Liquor
Evaporation-II
“Evaporation is essential step in increasing process liquor concentration & maintaining refinery water balance.”
Make Up Caustic
Total Steam Consumption: ~250 TPH
Hindalco Industries Limited, Renukoot
9
Renukoot refinery operates on 4 evaporation units. Evaporation unit-II is the oldest unit among all four with steam economy ~2.92 T/T while Evap-I & newly installed GEA Messo Evap-IV runs on ~3.8 T/T. Steam economy of Evap-II unit has been the perennial problem and could not be solved by several initiatives taken in the past. Liquor flashing unit was installed in May-12 to reduce evaporation load of existing evaporation units. As a consequence one out of two bay of Evaporation unit-II stopped.
Performance of evaporation unit is measured by “Steam Economy”. (Evaporation Rate/Steam)
Hindalco Industries Limited, Renukoot
10
Evaporation Unit-II operating with two bays i.e “HID” and “Evaporator” Post liquor flashing Unit installation, “Evaporator” side bay stopped & “HID” side bay kept in operation. Performance with this setups.
Hindalco Industries Limited, Renukoot
11
experts and vendors to improve the Evaporation-II steam economy.
technology energy efficient units ( Expensive option).
and team arrived at “Is it possible to add additional effects for improving heat recovery thus increase in steam economy?”.
evaluate the viability
the idea and establishing key engineering/process specification, process simulation model developed
along with the HID circuit and it emerged that adding 3 nos. effects is techno-feasible solution.
Hindalco Industries Limited, Renukoot
12
Total duration 4 Weeks (complete flow- sheeting & programming).
different setups/combinations (including Base case).
07/28/13 18:35:36 Project : Production_Upgradation 09Change09FC12 Evap (E:\Ameet SysCAD Work\SysCAD Projects\Final\Production_Upgradation 09Change09FC12 Evap.spf\)
UMO
Base Case 01 (with 2 Evap Effect) Case 02 (with 3 Evap Effect)
Case 03 (with 4 Evap Effect) HID body in line 3 3 3 3 Evaporation Body In line 2 3 4 Total Effect In Line 3 5 6 7 Liquor flow to New FF Tak m3/hr 600 600 600 600 Liquor Feed Flow to Evaporation m3/hr 320 320 320 320 Liquor Feed Temperature
OC
65.98 65.98 65.98 65.98 Liquor Feed Caustic Conc. gpl 246 246 246 246 Liquor Exit Temp From effect Heater to LSH
OC
107.3 111.5 112.9 114.0 LSH Htr Exit Temperature
OC
130 130 130 130 Liquor Exit Temp From last effect Flash chamber (Evaporation Discharge)
OC
91.16 86.57 85.04 83.83 Liquor Caustic Conc. From last effect Flash chamber (Evaporation Discharge) gpl 266.0 268.3 269.1 269.7 Vacuum on Barometric Condenser mmHg 600 600 600 600 Total vapor load on BC TPH 18.1 17.8 17.6 17.6 Water Required for BC @35 degC m3/hr 482 473 470 471 Water out from BC m3/hr 508 498 488 493 Water out Temp from BC deg C 56 56 56 56 Total Condansate out m3/hr 38.6 38.7 38.7 38.8 Condansate Temp
OC
61.5 61.5 61.5 61.5 Total Evaporation Rate (Evap+FFTk) TPH 33.2 35.9 36.7 37.4 Toatl steam Consumption TPH 15.7 12.8 11.8 11.0
Steam Economy T/T 2.12 2.81 3.11 3.39
Evaporation-II Phase-II (SYSCAD simulation Results)
Case no. 2 (i.e. 3 nos. Evaporator effects in line with the HID circuit) was selected for modification and implementation in the area
Hindalco Industries Limited, Renukoot
13
Engineering done to feed input stream from evaporator side instead of earlier arrangement of HID
temperature end.
Evaporation Unit # 2 New Scheme ( HID side with Add. Effects in Operation – Phase II
Hindalco Industries Limited, Renukoot
14
Another major challenge was vacuum system for evaporator effects with this configuration:
worked out and found suitable & implemented.
Evaporation Unit # 2 New Scheme ( HID side with Add. Effects in Operation – Phase II
Hindalco Industries Limited, Renukoot
15
Another area requiring engineering modifications was flexibility to revert in old configuration as during rainy season evaporation load may increase. Facility implemented with suitable provisions.
Evaporation Unit # 2 New Scheme ( HID side with Add. Effects in Operation – Phase II
Hindalco Industries Limited, Renukoot
16
Hindalco Industries Limited, Renukoot
17
Saving realization after Project completion
S # Parameters UMO Before After Total Diff (After- Before) Dec-12 to Apr-14 May-14 to May- 15
1
Steam Economy
t/t 2.95 3.42
0.47
2
Steam Consumption
TPH 13.4 10.9
3 LSH Temperature
OC
130 130 0.06
4 Evaporation Flow
m3/hr 315 325 9.65
Power Saving:
Hindalco Industries Limited, Renukoot
Pumps Pump Nos./HP Pumps Running (Nos.) Pumps Motor, HP Before After Before After
VT pumps 2 * 60 HP 3 NIL 310 2 * 125 HP Circulation Pump 270 + 250 HP 1 1 270 270 Discharge pump 1 * 40 HP 1 1 40 40 FF Tk. (N) Feed pump 2 * 75 HP 1 1 75 75 HID Feed Pump 2 * 215 HP 1 1 215 215 PLD Pump 2 * 40 HP 1 1 40 40 HID cond. Pump 2 * 10 HP 1 1 10 10 Evap cond. Pump 2 * 20 HP 1 1 20 20 IWR pumps 3 * 180 HP 3 2 540 360 Total 13 9 1520 1030
Power Savings (Before - After), HP (Motor loading assumed 85 %) 417 Power Savings (Before - After), KW 311
18
S # Item
Size
Quantity Cost (Rs/Unit) Rs (lacs) Dia Length, mtr
1 Sh-40 Pipe 12" 50 3520 1.76 2 Sh-40 Pipe 10" 40 3433 1.37 3 T/F flange 12" 10 1236 0.12 4 T/F flange 10" 10 1236 0.12 5 Pipe Fabrication and Erection cost 12" 50 325.4 0.16 6 Pipe Fabrication and Erection cost 10" 40 271.8 0.11 7 Miscellaneous 0.10
Total Investment in Rs Lacs 3.75
Total Investment in $ ( 1 $ = 66.30 Rs as on 01-01-2016) $5,659
1
Steam Saving (Saving for 10
months from May-14 to May-15) 2.46 TPH 890 157.9
Total Saving in MTOE 1467 Total saving in $ ( @ 300 USD / MTOE) $4,40,100
1
Power Saving (For 275 days per year) 310.71 KW 2.89 59.3 Total Saving in MTOE 176.36 Total saving in $ ( @ 300 USD / MTOE) 52908
Total Saving ( B + C ), $ USD/Annum $4,93,008
Pay Back Period (Days) 4.0
Hindalco Industries Limited, Renukoot
19
Flexibility to revert on earlier configuration. Cost economics
Space constraint Congested Layout of the unit
Hindalco Industries Limited, Renukoot
20
Key Parameters UMO Measurement Formula/Reference Verification Method
Steam Economy T/T Calculated = Evaporation Rate (TPH) / Steam Consumption (TPH) Evaporation Rate TPH Calculated = Feed Flow – [ Feed Flow * (Caustic in / Caustic Out)] Feed Flow M3/hr Flow Element Online Data from PHD Log Sheet: Doc No: DIG-LS-09-R2 FE Calibrated mid of the Month Caustic IN (Feed) gpl LAB instrument Sample Analysis in the LAB, Frequency: Every 4 hrs LAB: Potentiometric Titration Calibrated with Std. Solution. Caustic Out (Discharge) gpl LAB instrument Sample Analysis in the LAB, Frequency: Every 4 hrs LAB: Potentiometric Titration Calibrated with Std. Solution. Steam Consumption TPH Mass flow meter Online Data from PHD Log Sheet: Doc No: DIG-LS-09-R2 FE Calibrated mid of the Month
Hindalco Industries Limited, Renukoot
21