Team 18 5/5/18 Meet Team 18 Tess Anderson Photography Edwin Kpodzro, ME Nate Anderson, ME Matt Boelens, ME Hendrik Vermeulen, ME PROJECT DESIGN & OBSTACLES & 1/23 INTRO CONCLUSION FEASIBILITY BUILDING ASSESSMENT Presentation
1/23
Matt Boelens, ME Hendrik Vermeulen, ME Edwin Kpodzro, ME Nate Anderson, ME
Tess Anderson Photography
Meet Team 18
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
Presentation Outline
- Introduction
- Project feasibility
- Business model
- Design and Building
- Decisions and process
- Building Components
- Obstacles & Assessment
- Conclusion
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
2/23
Historical Background
- Separated from Sudan in
2011 (7 years)
- Limited infrastructure
- Extremely fertile (sesame)
- Tribal tension (Dinka/Nuer)
Bing.com/maps
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
3/23
http://cdn.lightgalleries.net/522489697c5a8/images/SS_LANDSCAPE_07-1.jpg
Problem Statement
Due to lack of infrastructure and split from Sudan, South Sudan is unable to capitalize on its abundant natural resources. Sesame seed oil production continues to be limited due to inefficient manual oil extraction processes.
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
4/23
How We Got Involved
Jeff Kibbie, Custom Electric MonyroorTeng, Pastor of Sudanese Evangelical Covenant Church
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
5/23
- Sesame oil extraction device
for use by neighboring farmers
- Focus on Upper Nile region
- Create an avenue for divided
tribal groups to unify around
Contribution to Solution
https://en.wikipedia.org/wiki/South_Sudan
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
6/23
Customer
James Tor Monybuny, Governor of Upper Nile region, South Sudan
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
7/23
Project Organization
NATHAN HENDRIK EDWIN MATT
- BUILDING/WORK
SHOP LEAD
- PROJECT
COORDINATOR
- CAD LEAD
- SYSTEM
INTEGRATION LEAD
- SUPPLY CHAIN
LEAD
- TECHNICAL
WRITING AND
- COMMS. LEAD
- BUSINESS/FINANCE
LEAD
- WEBSITE/MEDIA
LEAD INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
8/23
Project Organization
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
9/23
Initial Concept
INTRO PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT CONCLUSION
10/23
Projected Profit Margin
INTRO PROJECT FEASIBILITY CONCLUSION DESIGN & BUILDING OBSTACLES & ASSESSMENT
11/23
Design Decisions
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
12/23
Final Drivetrain Design
Tensioner
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
13/23
View port
Hopper Design
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
14/23
Oil Collection Bin Design
1st stage oil collector
Valve Hose to siphon
2nd stage oil collector
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
15/23
PTO Connection Design
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
16/23
Building Components
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
17/23
Building Components
INTRO PROJECT FEASIBILITY DESIGN & BUILDING CONCLUSION OBSTACLES & ASSESSMENT
18/23
Obstacles – Past and Present
- Communication
- Between team and
customer
- Between team and supplier
- Funding
- Shipping of worm
assembly
INTRO PROJECT FEASIBILITY OBSTACLES & ASSESSMENT CONCLUSION DESIGN & BUILDING
19/23
Project Assessment
- Project scope
- More thorough communication with
suppliers prior to ordering major components
- Timeline
- Estimating time to complete tasks
INTRO PROJECT FEASIBILITY OBSTACLES & ASSESSMENT CONCLUSION DESIGN & BUILDING
20/23
Situation in South Sudan
CONCLUSION PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT INTRO
21/23
Project Wrap-up
- Project financially sustainable long
term
- Drivetrain fully built
- User manuals, maintenance plans,
and design documents being created
- System fully assembled by end of
June and shipped in time for October 2018 harvest
CONCLUSION PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT INTRO
22/23
Acknowledgements
- Jeff Kibbie
- Monyroor Teng
- Governor James Tor
Monybuny
- Professor Tubergen
- Jacob Atem
- Phil Jasperse
- Bob DeKraker
- Ben Hekman
- Wesley Richards
- All Donors
CONCLUSION PROJECT FEASIBILITY DESIGN & BUILDING OBSTACLES & ASSESSMENT INTRO
23/23
Questions?
Any Questions?
Tess Anderson Photography
Projected Profit Margin Comparison
Without Expeller With Expeller Capital Investment $40,159 $64,855 Annual Cost $7,272 $5,147 Annual Revenue $34,258 $39,275 Annual Profit $26,986 $34,127 Breakeven 2 Harvests 2 Harvests Profit (EOY 10) $225,600 $276,400
INTRO PROJECT FEASIBILITY CONCLUSION DESIGN & BUILDING OBSTACLES & ASSESSMENT