Tailings Storage and Heap Leaching in a Combined Facility A First - - PowerPoint PPT Presentation

tailings storage and heap leaching in a combined facility
SMART_READER_LITE
LIVE PREVIEW

Tailings Storage and Heap Leaching in a Combined Facility A First - - PowerPoint PPT Presentation

Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry Thomas F. Kerr, P.E., Knight Pisold and Co. Michael G. Skurski, P.E., Newmont Mining Co. Peter D. Duryea, Ph.D., P.E., Knight Pisold and


slide-1
SLIDE 1

“Tailings Storage and Heap Leaching in a Combined Facility – A First for the Mining Industry”

Thomas F. Kerr, P.E., Knight Piésold and Co. Michael G. Skurski, P.E., Newmont Mining Co. Peter D. Duryea, Ph.D., P.E., Knight Piésold and Co.

slide-2
SLIDE 2

Overview

 New La Quinua gold mill at the Yanacocha Mine

has a thickened tailings storage facility (TTSF) contained entirely within a large (530 Mt and 130 m high) active heap leach pad (HLP)

 Unprecedented in the mining industry  Provides the operator with cost, land use and

closure efficiencies

 Constructed between 2006 and 2008 as part of

the staged expansion of the La Quinua HLP – tailings deposition commenced in April 2008

2

slide-3
SLIDE 3

General Arrangement Plan

3

slide-4
SLIDE 4

Artificial Oblique View Looking North

4

slide-5
SLIDE 5

Aerial View Looking West During Construction

5

slide-6
SLIDE 6

Key Design Issue

 Leach ore embankments retaining tailings

needed to provide the high level of security required of other major tailings dams

 However, the leach ore is placed in thick

(16 m) uncompacted lifts to maintain adequate permeability for leaching and is irrigated with a high solution rate (10 L/hr/m2)

 Loose structure made static and dynamic

liquefaction a key issue

6

slide-7
SLIDE 7

Design Approach

Keep the ore that becomes saturated or near saturated when under leach well-removed from the outer faces of the embankments and contained behind large unsaturated structural shells

7

slide-8
SLIDE 8

Design Solution

Provide the embankments with wide cross sections to support loading and leaching and thus wide shells

Place the ore in coarser (lower) and finer (higher) zones to promote vertical downward drainage and reduce lateral spread of flow

Thicken the tailings to reduce the amount of water entering the combined facility

Use a rotational tailings deposition method from the inside crests of the embankments to build drained and stable beaches against the embankments

8

slide-9
SLIDE 9

Wide Zoned Cross Sections

10

slide-10
SLIDE 10

Drained Beach Development

11

slide-11
SLIDE 11

Hydraulic Model Results

Saturated zone is in center of embankment – flow vectors are vertically down – consistent with design objective 12

slide-12
SLIDE 12

Seismic Risk of the Site

Maximum Design Earthquake (MDE) is equal to the Maximum Credible Earthquake (MCE) Deep intraplate event below the Andes Magnitude 8.0 Distance and depth 90 and 100 km, respectively Resulting peak horizontal ground acceleration at the site is 0.41 g

13

slide-13
SLIDE 13

Design Earthquake

 Maximum Design Earthquake (MDE) is

equal to the Maximum Credible Earthquake (MCE)

 Deep intraplate event below the Andes  Magnitude 8.0  Distance and depth 90 and 100 km,

respectively

 Resulting peak horizontal ground

acceleration at the site is 0.41 g

14

slide-14
SLIDE 14

Dynamic Stability Model Results

Shear bands from earthquake loading closely match the critical slip surfaces from static limit equilibrium analyses – along liner interface

15

slide-15
SLIDE 15

Dynamic Stability Model Results

Contours of total deformation

  • Maximum horizontal 15 cm along liner
  • Maximum vertical 25 cm at crest

16

slide-16
SLIDE 16

Actual Leach Ore Placement

 Sonic drill used to provide continuous

samples of ore in the HLP

 Not adequate differentiation of fines content

in designated zones

 Operation will put more emphasis on

maintaining adequate unsaturated outer shells via controls on leach solution application and monitoring of instrumentation

17

slide-17
SLIDE 17

Heap Leach Ore Piezometer Results Section B

MINERA YANACOCHA S.R.L.

Figure A.20 MSSF - La Quinua Heap Leach Pad Stage 4&5 - Cross Section B' - Vibrating Wire

Piezometers Data

  • 3
  • 2
  • 1

1 2 3 09-Oct-07 08-Nov-07 08-Dec-07 07-Jan-08 06-Feb-08 07-Mar-08 06-Apr-08 06-May-08 05-Jun-08 05-Jul-08 04-Aug-08 03-Sep-08 03-Oct-08 02-Nov-08 02-Dec-08 01-Jan-09 31-Jan-09 02-Mar-09 01-Apr-09 01-May-09 31-May-09 30-Jun-09

Date Presure Head (meters of water)

LQMYVP07-04 LQMYVP07-05 LQMYVP08-02 LQMYVP08-03 LQMYVP08-04 LQMYVP08-06

19

slide-18
SLIDE 18

Tailings Facility Piezometer Results

MINERA YANACOCHA S.R.L.

Figure A.27 MSSF - La Quinua Heap Leach Pad Stage 5&6 - DAM - Vibrating Wire Piezometers Data

  • 3
  • 2
  • 1

1 2 3 4 5 10-Aug-07 09-Sep-07 09-Oct-07 08-Nov-07 08-Dec-07 07-Jan-08 06-Feb-08 07-Mar-08 06-Apr-08 06-May-08 05-Jun-08 05-Jul-08 04-Aug-08 03-Sep-08 03-Oct-08 02-Nov-08 02-Dec-08 01-Jan-09 31-Jan-09 02-Mar-09 01-Apr-09 01-May-09 31-May-09 30-Jun-09

Date Presure Head (meters of water)

3500 3510 3520 3530 3540 3550 3560 3570 3580 3590 3600

Average elevation (m)

LQMYVP07-06 LQMYVP07-07 LQMYVP07-08 LQMYVP07-09 LQMYVP07-10 LQMYVP07-11 LQMYVP07-12 LQMYVP07-13 LQMYVP07-14 LQMYVP07-15 LQMYVP07-16 LQMYVP07-17 Avg Elevation of Mill

Initial Discharge of Mill Sands

21

slide-19
SLIDE 19

Water Management System

23

slide-20
SLIDE 20

Tailings Deposition System

24

slide-21
SLIDE 21

Conclusions

The La Quinua TTSF is unique

Contrary to standard tailings dam practice, it contains embankments of leach ore placed in thick, uncompacted lifts that are subject to application of large quantities of leach solution and percolation flows

Dynamic analyses have shown that there is the potential for liquefaction or strain softening of saturated or near saturated internal zones but the overall predicted deformations are minimal

Ultimate control on stability is by leach solution application rate

Operation to date is meeting design objectives

A comprehensive geotechnical investigation will be completed with follow-up dynamic deformation analyses based on actual materials placed 25