TA3290 Life-Cycle Modeling and Economic Evaluation CiTG, minor - - PowerPoint PPT Presentation

ta3290 life cycle modeling and economic evaluation
SMART_READER_LITE
LIVE PREVIEW

TA3290 Life-Cycle Modeling and Economic Evaluation CiTG, minor - - PowerPoint PPT Presentation

TA3290 Life-Cycle Modeling and Economic Evaluation CiTG, minor Mining and Resource Engineering Economie 3: Vervolg Investment Projects Dr.ir. Gerard P.J. Dijkema Energy & Industry Group December 15, 2011 1 Vermelding onderdeel organisatie


slide-1
SLIDE 1

December 15, 2011

Vermelding onderdeel organisatie 1

TA3290 Life-Cycle Modeling and Economic Evaluation

CiTG, minor Mining and Resource Engineering Economie 3: Vervolg Investment Projects Dr.ir. Gerard P.J. Dijkema

Energy & Industry Group

slide-2
SLIDE 2

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 2

Project (economic) evaluation Focus on a new >100M€ facility

  • What does one (management) have to do?
  • Market research
  • Life-cycle economic estimate
  • Investment & production cost
  • Economic performance
  • Funding strategy
  • Risk assessment
  • Strategic alignment – project portfolio!
  • Initial go/no go on business case
slide-3
SLIDE 3

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 3

Life cycle economic estimates

Activity

  • D – Design
  • B – Build
  • F – Finance
  • O – Operate
  • M – Maintain
  • D – Dismantle

When looking at a “project” life of decades! Estimate

  • Investment capital cost
  • Lead time (go <-> live)
  • Interest rate
  • Operating cost/revenue
  • Maintenance time & cost
  • Dismantling cost
slide-4
SLIDE 4

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 4

Industrial project life cycle

Production D e s i g n Technical perspective Optimization? B u i l d Decision perspective Where? What? How? Go? No-Go? Improve process for Environment…. Economic reasons… License to operate? Economic perspective Build Production Design Dedicated money on project Profit Go? No-Go? Slope of curve is Industry-specific!

slide-5
SLIDE 5

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 5

Hoe nu een investering evalueren?

Voor de onderneming geldt: Winstafter tax = Verkopen + Andere inkomsten – Kosten – Taxes

slide-6
SLIDE 6

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 6

Investeringsselectie

  • Bij het beoordelen en selecteren van investeringen

maken ondernemingen gebruik van cashflow of kasstroom

  • Cashflow is het verschil tussen de uitgaande en

binnenkomende kasstroom in een onderneming

  • “Cash in hand”
slide-7
SLIDE 7

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 7

Kasstroom / Cash flow

  • te gebruiken of je iets kunt betalen...
  • ...dan wel moet lenen
  • brood, benzine, huur, kleren etc.
  • kun je meestal betalen uit je lopende kasstroom
  • huis, auto, (scooter, flatscreen) niet  lenen
  • kun je de rente betalen uit je lopende kasstroom?
slide-8
SLIDE 8

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 8

Kasstromen

  • drie hoofdcategorien kasstromen
  • operating – de activiteiten van de onderneming
  • investing – merger, acquisities, investeringen
  • financing – aflossingen, dividenden, aandelen-inkoop
  • Voor het beoordelen van investeringsprojecten wordt de
  • perating cash flow gebruikt.
slide-9
SLIDE 9

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 9

Operating cash flow

  • Direct gekoppeld aan winst (uit een project)
  • Cashflow = kasstroom in – kasstroom uit
  • Winst = opbrengst – kosten
  • Omdat afschrijving wèl bij de kosten is meegerekend

(terwijl het géén uitgave is) moeten we deze afschrijvingen weer bij de winst optellen om de

  • perating cashflow te bepalen
  • Operating Cashflow = Winst + Afschrijvingen
slide-10
SLIDE 10

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 10

Voorbeeld

slide-11
SLIDE 11

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 11

Voorbeeld

slide-12
SLIDE 12

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 12

Voorbeeld

slide-13
SLIDE 13

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 13

Voorbeeld

slide-14
SLIDE 14

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 14

Voorbeeld

slide-15
SLIDE 15

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 15

Voorbeeld

slide-16
SLIDE 16

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 16

Voorbeeld

slide-17
SLIDE 17

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 17

Investeringsselectie

  • Terugverdientijd
  • Netto contante waarde
  • Return-on-Investment
slide-18
SLIDE 18

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 18

Terugverdientijd

  • Na hoeveel tijd is de investering terugverdiend
slide-19
SLIDE 19

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 19

Terugverdientijd

  • Na hoeveel tijd is de investering terugverdiend
slide-20
SLIDE 20

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 20

Terugverdientijd vs. netto contante waarde

  • Voordeel: eenvoud
  • Nadelen:
  • Revenuen na de terugverdientijd niet meegenomen
  • Verdeling van cash-flow over de tijd
  • Geld dat eerder binnenkomt is 'meer waard'
  • Ondervangen door Netto-Contante-Waarde berekening
  • Cash flows worden contant gemaakt m.b.v.

rentevoet

slide-21
SLIDE 21

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 21

Return-on-Investment

  • Naast terugverdientijd & NCW
  • Veel gebruikt in kapitaalsintensieve industrie
  • “wat is de verdienkracht van een project over de

looptijd uitgedrukt in fictief rentepercentage”

  • ROI is gelijk aan het rentepercentage i waarbij de

NCW van de cash-flow serie over de looptijd n van het project gelijk is aan 0.

slide-22
SLIDE 22

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 22

Investeringsproject-evaluatie

  • Tot zover: financiële methoden
  • Voor deze gebruikte methoden zijn inputs nodig:
  • Te verwachten / geschatte opbrengsten
  • Te verwachten / geschatte kosten
  • Probleem: looptijd investering > 20 jaar!
slide-23
SLIDE 23

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 23

Vervolg: schatten investeringskosten

  • Project
  • Arbeid, materialen, grondstoffen enz.
  • Afzetmarkt, opbrengst produkten enz.
  • Kapitaalgoederen / bedrijfsmiddelen
  • Kapitaalsintensieve industrie: investeringskosten /

kapitaalslasten werken sterk door op elk project

slide-24
SLIDE 24

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 24

Annualized costs

  • Kt = Total Annual Cost
  • Kp = direct Production Cost
  • a = model parameter > 1 indirect production costs

  • L = direct Labour costs
  • d = parameter to convert to total Labour cost
  • i = depreciation and interest
  • f = other capital related cost
  • IB = Total On-Site Investment
slide-25
SLIDE 25

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 25

Cost Types

  • Investment related cost
  • Direct capital cost
  • Cost of working capital
  • Startup expense
  • Goodwill, engineering & license fees
  • Operating cost
  • maintenance
  • operating labor
  • overhead
  • charges, taxes, insurance
  • raw materials
  • operating materials
  • utilities

shipping/packaging

slide-26
SLIDE 26

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 26

Working capital

  • Funds required to actually operate the plant:
  • to pay for initial raw materials
  • to pay salaries
  • to fill up tanks
  • to fill up equipment
  • to buy catalysts
  • etc.
  • Estimate: 10 to 20% of capital cost
slide-27
SLIDE 27

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 27

Operating cost - I

  • raw materials
  • quotations from literature and suppliers
  • operating materials
  • safety clothing, instrument charts, etc.
  • 10% of maintenance cost
  • utilities
  • steam, power, air, water
  • depends on location
  • shipping/packaging
  • depends on product
slide-28
SLIDE 28

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 28

Operating Cost - II

  • maintenance
  • 5 to 15% of capital cost
  • operating labour, incl. supervision
  • operators in shifts plus overheads
  • appr. 15% of total operating cost, 20% extra
  • overhead
  • general management, security, etc.
  • appr. 50-100% of total labour cost
  • charges, taxes, insurance
  • 15-20% of fixed capital
slide-29
SLIDE 29

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 29

Capital Cost Estimation

Detailed Design Basic Design Conceptual Design Strategic How? Accuracy Phase

slide-30
SLIDE 30

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 30

Capital Cost Estimation

  • Cost of making the estimate increases from 0,1% to 2% of total project cost

Detailed cost estimation; procurement +/- 2-5% Detailed Design Refined Lang Factor method; +/- 10-15% Basic Design e.g. Guthrie + Lang Factor method; FUM +/- 20-30% Conceptual Design Indices (e.g. Nelson Refinery Index) +/- 40-50% Strategic How? Accuracy Phase

slide-31
SLIDE 31

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 31

Working with Indices

  • “Weather forecast”
  • Cost of a new plant = Last Plant * Index
  • Simplest index = Inflation
  • Order of Magnitude Estimates: Capacity*Index
  • Index may be sector specific
  • Nelson (Oil) Refinery Index
  • CE (Chem. Eng) Plant cost index
  • Or location specific
  • U.S. Gulf Coast Plant Cost Index
slide-32
SLIDE 32

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 32

Chemical Engineering Plant Cost Index (CEPI) / Producer Price Index (PPI

  • CEPI
  • 1957-1959 = 100
  • 1960 = 102
  • 1970 = 126
  • 1980 = 261
  • 1990 = 358
  • 2000 = 394
  • 2005 = 468
  • PPI
  • 1984 = 100
  • 1990 = 121
  • 2000 = 157
  • 2005 = 187
slide-33
SLIDE 33

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 33

Economy-of-scale

  • ECONOMY OF SCALE (Guthrie)
  • I = I0 * (C / C0) n
  • Process Industry: n = 0.6
  • A plant of double capacity costs only 50% more!
  • In many a sector, only world-scale plants are competitive
slide-34
SLIDE 34

(c) G.P.J. Dijkema, TU Delft, 2009

34

Evolution of Plant Size Capacity of new construction W.Europe Product X

  • 50

100 150 200 250 300 350 400

1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002

KT / Plant

slide-35
SLIDE 35

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 35

Capital cost when operating

  • DBFOM
  • Typical plant utilisation rate is 85%

(Dutch Chemical Industry)

  • AVERAGE PRODUCTION = 85% of RATED CAPACITY
slide-36
SLIDE 36

(c) G.P.J. Dijkema, TU Delft, 2009

36

Evolution of Plant Age Distribution W.Europe as of 2002; Product X

1 2 6 3 1 14 10 5 7

0% 5% 10% 15% 20% 25% 30% <=1965 1965 to 1969 1969 to 1973 1973 to 1977 1977 to 1981 1981 to 1985 1985 to 1989 1989 to 1993 1993 to 1997 >1997 Percent in Year

slide-37
SLIDE 37

(c) G.P.J. Dijkema, TU Delft, 2009

37

Evolution of Plant Size Capacity Distribution W.Europe Product X as of 2002

1 6 6 22 6 3

0% 10% 20% 30% 40% 50% 60% <=50 50 to 100 100 to 150 150 to 200 200 to 250 250 to 300 >300 2001 KTA Capacity Percent in size Distribution

slide-38
SLIDE 38

(c) G.P.J. Dijkema, TU Delft, 2009

38

Evolution of Plant Size Capacity of new construction W.Europe Product X

  • 50

100 150 200 250 300 350 400

1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002

KT / Plant

slide-39
SLIDE 39

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 39

General structure of an industrial plant:

An assemblage of unit operations

Puri- fication Recycle Flow Separation Reaction Feed Product Purge Feed preparation

T

Fuel

Dijkema, G.P.J., Process System Innovation by Design, 2004

slide-40
SLIDE 40

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 40

General structure of an industrial plant:

An assemblage of unit operations

Unit operations model and cost engineering: This model is the basis for a number of methods of cost estimation (early phase)

Puri- fication Recycle Flow Separation Reaction Feed Product Purge Feed preparation

T

Fuel

Dijkema, G.P.J., Process System Innovation by Design, 2004

slide-41
SLIDE 41

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 41

Functional Unit Method Zevnik and Buchanan (1963)

  • Investment = f (capacity, complexity)
  • A plant is divided into “functional units”
  • IB = Investment estimated
  • CI = plant cost index (e.g. 361.3 in 1991; 1970=100)
  • Cf,i = complexity factor per functional unit
  • Pi = capacity per functional unit; m = 0.6
slide-42
SLIDE 42

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 42

Functional Unit Methode (2)

  • Complexity factor
  • Ft =Temperature
  • Fp =Pressure Factor
  • Fm= Material Factor”
  • Steel, wood = 0
  • Al, Cu, Bronz, 400-steel = 0.1
  • Monel, Ni, Inconel 300 = 0.2
  • Hastelloy etc. = 0.3
  • Precious Metals = 0.4
slide-43
SLIDE 43

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 43

Functional Unit Method

  • Advantages?
  • Disadvantages?
slide-44
SLIDE 44

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 44

Capital Cost Estimation - Lang

  • Modified Lang factor method
  • A plant is thought to be composed of a collection of

(major) equipment items, each with their own cost characteristics

  • These determine the cost of the item
slide-45
SLIDE 45

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 45

Capital Cost Estimation – Lang (2)

  • The plant cost is given by

Cf = ∑ fL,i * Ce,i Where

  • Cf = Fixed capital cost
  • Ce,i = Cost of major equipment i

(from quotes or estimates)

  • FL,i = Lang factor of equipment i:

3.1 for solids processing 4.7 for fluids processing 3.6 for solid/fluid processing

slide-46
SLIDE 46

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 46

Equipment cost estimation

Ce = C*Sn

  • Ce = equipment cost
  • C = cost constant
  • S = size parameter
  • n = index for that

equipment (-1.0 to 1.3) Ce = C*Sn

  • Ce = equipment cost
  • C = cost constant
  • S = size parameter
  • n = index for that

equipment (-1.0 to 1.3) 100 101 102 103 102 103 104 Vessel height V e s s e l c

  • s

t D=1 m D=2 m

slide-47
SLIDE 47

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 47

Compounded Lang factor

  • fL = Σ fi
  • f1 = equipment erection
  • f2 = pipes
  • f3 = instrumentation
  • f4 = electrical
  • f10-12 = design and engineering, contractor
  • Compounded Lang factor helps estimating the total

fixed capital cost

slide-48
SLIDE 48

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 48

Capital cost when operating

  • DBFOM
  • Typical plant utilisation rate is 85%

(Dutch Chemical Industry)

  • AVERAGE PRODUCTION = 85% of RATED CAPACITY
slide-49
SLIDE 49

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 49

Aluminium smelters in Ijsland

Alcoa Fjardaál smelter in Reydarfjordur, Iceland Opened June 2007

  • System perspective (?
  • The author of an anti-smelter book says

efforts to please aluminum giants like Alcoa have created a "heroin economy" and worries that leaders are "diverting the whole ecosystem of the east.“

  • Er zijn niet alleen effecten in Ijsland

(alumina smelting) maar ook elders (bauxiet-mining, red-mud)

  • Aluminium-boom  overcapaciteit drijft

prijzen naar beneden; boom &bust cyclus?

  • enz. enz.
slide-50
SLIDE 50

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 50

Literature

  • Investment Estimation Theory
  • Thane Brown (2007), Engineering Economics and Economic

Design for Process Engineers, CRC Press, Boca Raton, Chapter 1 & 3 (in electronic reader)

slide-51
SLIDE 51

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 51

Industrial design

technology/system

Design of new production facilities has become more efficient:

  • Computer aided design methods.
  • Better understanding of underlying engineering problems.

Process efficiency Time Theoretical maximum efficiency Design efficiency gains 50’s 2003 Operational efficiency

slide-52
SLIDE 52

(c) G.P.J. Dijkema, TU Delft, 2009

December 15, 2011 52

ta3290

Vragen, Discussie?

Dr.ir. Gerard P.J. Dijkema

Faculty of Technology, Policy and Management Energy and Industry Group

PO Box 5015, 2600 GA Delft-NL