Synchrotron Overview
Tadashi Koseki J-PARC center, KEK&JAEA Accelerator Laboratory, KEK ICFA mini-Workshop on Beam Commissioning for High Intensity Accelerators CSNS site, June 8, 2015
Synchrotron Overview Tadashi Koseki J-PARC center, KEK&JAEA - - PowerPoint PPT Presentation
ICFA mini-Workshop on Beam Commissioning for High Intensity Accelerators CSNS site, June 8, 2015 Synchrotron Overview Tadashi Koseki J-PARC center, KEK&JAEA Accelerator Laboratory, KEK Contents 1. High power proton synchrotrons 2. High
Tadashi Koseki J-PARC center, KEK&JAEA Accelerator Laboratory, KEK ICFA mini-Workshop on Beam Commissioning for High Intensity Accelerators CSNS site, June 8, 2015
Jie Wei / Y. Yamazaki 1 MW
Spallation Neutron Source, ORNL 1-GeV AR, 1.4 MW Main Injector, FNAL 120-GeV Synchrotron, 700 kW J-PARC, KEK&JAEA 3-GeV RCS, 1 MW / 30-GeV MR , 750 kW ISIS, STFC 800-MeV RCS, 200 kW
Front-End:
Produce a 1-msec long, chopped, H- beam
1 GeV LINAC Accumulator Ring:
Compress 1 msec long pulse to 700 nsec
2.5 MeV
LINAC LINAC Front-End Front-End
Accumulator Ring
RTBT HEBT
Injection Extraction RF Collimators
945 ns 1 ms macropulse
Current mini-pulse Chopper system makes gaps Current
1ms
Liquid Hg Target
1000 MeV
Courtesy of M. Plum
1.4 MW
Target issues
1.0 MW
power operations in April 2015.
replacement and/or condition of the ion source.
– 5 out of the last 11 targets have failed at weld joints – New designs to improve / eliminate weld joints
Leak detector fluid “bubbling” through weld failure on the Target
2014
J-PARC had a trouble on a mercury target in the end of April 2015. Tiny water leak occurred at a weld joint on the target.
Report
H- linac : accelerates H- to 400 MeV Booster : 4.2×1012 protons, 400 MeV 8 GeV at 7.5 Hz, h=84 Recycler: a permanent magnet accumulator ring in the MI tunnel Main Injector: 8 GeV 120 GeV at 1.33 s cycle time, h=588 ( 7*84) 2+6 booster batches are injected to MI using slip-stacking Simultaneous operations of NOvA and SY120 (slow extraction beam) Courtesy of S. Nagaitsev
0.5 sec. Revolution time of Recycler
MI only RR 6-batch RR 2+6-batch
Shutdown for the PIP; Recycler upgrade
MI transfer lines
MI upgrade
Installation of 700 kW target /horns
rf cavity refurbishment and tuner cooling upgrade
700 kW by February 2016 Testing 4+6 operation green line shows beam in the Recycler
Performance Parameter PIP-II Linac Beam Energy 800 MeV Linac Beam Current 2 mA Linac Beam Pulse Length 0.5 msec Linac Pulse Repetition Rate 20 Hz Linac Beam Power to Booster 13 kW Linac Beam Power Capability (@>10% Duty Factor) ~200 kW Mu2e Upgrade Potential (800 MeV) >100 kW Booster Protons per Pulse 6.4×1012 Booster Pulse Repetition Rate 20 Hz Booster Beam Power @ 8 GeV 120 kW Beam Power to 8 GeV Program (max) 80 kW Main Injector Protons per Pulse 7.5×1013 Main Injector Cycle Time @ 120 GeV 1.2 sec LBNF Beam Power @ 120 GeV* 1.2 MW LBNF Upgrade Potential @ 60- 120 GeV >2 MW
Goal: Provide >1 MW at the time of LBNF startup (~2023) 800 MeV superconducting pulsed linac + enhancements to existing complex
P I P - I I I “ m ul t i
i
A 8 GeV SRF Linac =0.838 120 GeV Main Injector 8 GeV Recycler >2-MW target P I P - I I I “ m ul t i
i
B ~2=0.8+1.2 GeV SRF Linac New 8 GeV RCS
(or “greatly upgraded” Booster?)
120 GeV Main Injector 8 GeV Recycler >2 MW target P I P - I I I “ m ul t i
i
C 800 MeV SRF Linac new 8-12 GeV “smart” RCS i
120 GeV Main Injector 8 GeV Recycler ? >2 MW target
From “High Power Proton Beams for Particle Physics ” Sergei Nagaitsev, 11th ICFA seminar on Futre Perspective in High Energy Physics
Injection Energy 70 MeV Extraction Energy 800 MeV Injection scheme H- Charge Exchange Circumference 163.36 m Repetition 50 Hz Total beam power 0.2 MW
The beam is split between TS-1 and TS-2, 40 pps to TS-1 and 10 pps to TS-2. Typical beam powers on each targets are 0.16 MW to TS-1; 0.032 MW to TS-2
Courtesy J. Thomason
0.8-3.2 GeV RCS 0.8-3.2 GeV FFAG
TS-1 upgrade (~2019)
but expected to give at least 2 times larger neutron flux on every instrument
ISIS II – Next Generation Short Pulse Source (new machine)
Courtesy J. Thomason
Accelerator development and upgrade plans Upgrade of existing machine
into the existing ring – would give 0.5 MW
N eut ri no beam s t
M M R R H adron experi m ent al hal l M LF ( M at eri al and Li f e sci ence experi m ent al Faci l i t y) R C S Li nac
RCS is proton driver for neutron/muon production in MLF and booster for the MR.
MR has a lattice of imaginary transition and two extraction modes.
Earthquake
300 kW
Hg-target replacement Incident at Hadron Facility 532 kW
300 kW
〜560 kW ~10 months interruption due to the earthquake 593 kW ~1 month interruption due to the fire in MLF
Interruption due a trouble
500 kW 400 kW
Time (ms)
Number of particles / pulse (x1013)
8.41 x 1013 :1010 kW-eq. 6.87 x 1013 :825 kW-eq. 4.73 x 1013 :568 kW-eq. 7.86 x 1013 :944 kW-eq. 5.80 x 1013 :696 kW-eq.
2015/1/10
Reinforcement of the anode power supplies of the rf power amplifiers is planned in 2015 summer shutdown periods. After the reinforcement, 1-MW user operation will start within this JFY.
BLM signal (a.u.)
Collimator section First arc section (near the dispersion peak)
Mainly from foil scattering during injection
8.41 x 1013 6.87 x 1013 4.73 x 1013 7.86 x 1013 5.80 x 1013
Time (ms)
BLM signals @ collimator & arc sections
Longitudinal beam loss
50 100 150 200 250 300 350 400 2010/01/01 2011/01/01 2012/01/01 2012/12/31 2014/01/01 2015/01/01 MR Beam Power (kW) Date
MR Beam Power
Delivered beam power is 360 kW for the T2K experiment. Total number is > 1.1x1021 POT as of June 3.
After the long shutdown for 1 year and 11 months due to the radioactive material leak incident, beam operation resumed for users in the hadron experimental facility.
2 2
JFY 2014 2015 2016 2017 2018 2019
Event
30 -> 50 mA
FX [kW] (study/trial) SX [kW] (study/trial) 240-320
24~50 ~400 >50 >400 50~100 ~750 ~100 >750 100 Period of magnet PS New magnet PS 2.48 s 1.3 s Present RF system High gradient rf system Ring collimators
Back to JFY2012 (2kW)
C,D
E,F
Injection system FX system SX collimator / Local shields Ti ducts and SX devices with Ti chamber Beam ducts ESS
R&D Mass production Kicker PS improvement, Septa manufacture /test Kicker PS improvement, LF & HF septa manufacture /test Local shields
FX: The high rep. rate scheme is adopted to achieve the design beam intensity, 750 kW.
SX: After replacement of stainless steel ducts to titanium ducts to reduce residual radiation dose, 50 kW operation for users will be started. Beam power will be gradually increased toward 100 kW carefully watching the residual activity. Local shields will also be installed if necessary.
Manufacture, installation & test
Low cost R&D New power supply Buildings
RCS intensity Loss Loss power at 25 Hz 1.0 MW ~0.3% 400 W 1.1 MW ~0.3% 440W 1.2 MW ~0.3% 480 W 1.3 MW ~0.3% 520 W 1.4 MW ~0.3% 560 W 1.6 MW ~0.5% 1067 W 1.8 MW ~0.7% 1680 W 2.0 MW ~1.5% 4000 W
Loss (%)
Injection beam parameters: Energy : 400 MeV Peak current : 50 mA~100 mA Pulse length: 0.5 ms Chopper-beam on duty : 0.53
Beam intensity
RCS collimator limit ~4 kW → RCS has a feasibility to operate 2 MW
R&D of ion source / long pulse operation of linac
….
Beta & Dispersion for 1-superperiod
x,y (m) x,y (m)
H & V
s (m)
The 8-GeV booster ring
(x,x’) (y,y’) @ 3GeV @ 8GeV >125.5 ~0.04% >54 ~0.06% Phase plot @ inj.(3GeV) & extr.(8GeV)
0.1 0.2 0.3 0.4 0.5 0.6 0.7 20 25 30 35 40 45 50 MS00 MS10 MS20 KM01 2.36 mrad KM02 2.36 mrad KM03 2.36 mrad Collimator QFP004 QDT005 QFR006 QDR007 BP01 BP02 ZSH006 Injection Beam 81 pi Baseline design x(m) s(m)
8 GeV injection in the MR using new septa&kickers RCS : 1.6 MW MR > 2.6 MW RCS : 2 MW MR > 3.2 MW
INJ+COLL RF CAVs RF CAVs EXT
Injection energy 3 GeV Extraction energy 8 GeV Circumference 696.666 m Superperiodicity 4 Transition gamma ~15 GeV Collimator Aperture 126π.mm.mrad Physical Aperture 189 π.mm.mrad
Linac
Project Phase I II Beam Power on target [kW] 100 500 Proton energy [GeV] 1.6 1.6 Average beam current [μA] 62.5 312.5 Pulse repetition rate [Hz] 25 25 Linac energy [MeV] 80 250 Linac type DTL +Spoke Linac RF frequency [MHz] 324 324
15 40 Macropulse duty factor 1.0 1.7 RCS circumference [m] 228 228 RCS harmonic number 2 2 RCS Acceptance [mm-mrad] 540 540
Courtesy S. Wang
Lattice of 4-fold symmetry, triplet. 227.92m circumference. Four long straight sections for injection, acceleration, collimation and extraction. 24 main dipoles with one power supply. 48 main quadrupoles with 5 power supplies. Ceramic vacuum chambers for the AC&pulsed magnets. 8 RF ferrite loaded cavities to provide 165 kV.
27
RCS Tunnel is now ready for installation
24 dipoles and 48 quadrupoles for RCS have been fabricated and delivered to CSNS. The field measurements for dipoles have been
been measured. The first set of the power supply for RCS main magnets is completed and the other 5 sets are under mass production.
The first set of the power supply
The first ferrite-loaded cavity and high power RF source have been successfully manufactured and tested. The remaining 7 sets will be delivered to CSNS site soon.
Ferrite-loaded cavity
RF power supply All 25 ceramic chambers for main dipoles and most
fabricated and delivered to CSNS site. TiN coating have been started for the ceramic chambers. Dipole ceramic chamber under vacuum check Newly invented RF cage
2 bump power supplies have been manufactured and tested with dummy load. The prototype kicker power supply has been upgraded, and tested. Based on the upgraded design, mass production has been started.
Power supply for bump magnets. Power supply for kicker magnet.
The fabrication and test of diagnostics and control components are on schedule. Test of BLM in a proton cyclotron
FCC-hh16T magnets)
Courtesy of O. Bruning
Energy frontier should be a global project because of the ambitious scope, high cost, huge manpower, and long R&D time. It needs more long time to realize than the accelerators in the past.
Linac 0 - 50 MeV PSB 0.05 - 1.4 GeV PS 1.4 - 26 GeV SPS 26 - 450 GeV LHC 0.45 - 7 TeV
CERN proton accelerator chain
HL-LHC LHC Injector Upgrade (LIU)
RUN 1 : Integrated luminosity ~ 30 fb-1 2010: Commissioning Integrated Luminosity ~ 0.04 fb-1 CM energy ~7 TeV 2011: .. exploring limit Integrated Luminosity ~ 6.1 fb-1 CM energy ~7 TeV 2012: .. production Integrated Luminosity ~ 23.3 fb-1 CM energy ~8 TeV
From “LHC upgrade: High Luminosity” Frederick Bordry, 11th ICFA seminar on Futre Perspective in High Energy Physics
2015 : 10 fb-1 RUN2: ~100 -120 fb-1
RUN1 RUN2 RUN3
LIU in LS2:
RUN4 RUN5
Goal of 3,000 fb-1 by mid 2030ies 300 fb-1 before LS3
Courtesy of O. Bruning
KEKB: 1998 — 2010
Design luminosity 8 x 1035 cm-2s-1
Peak luminosity 2.1 x 1034 cm-2s-1
35
40 times higher luminosity 2.1x1034 --> 8x1035 cm-2s-1 Nano-Beam scheme extremely small y
*
low emittance Beam current double
New e+ Damping Ring
e- :7 GeV, 2.6A e+ :4 GeV, 3.6A
L 2er
e
1 y
*
x
*
Iy y
*
RL Ry
Redesign the lattice to squeeze emittance (replace short dipoles with longer ones, increase wiggler cycles) Upgrade Belle II detector
Collision Point
Reinforce RF systems for higher beam currents Upgrading (LER) and new (HER) wiggler sections Replace beam pipes with TiN-coated beam pipes with antechambers New superconducting final focusing magnets near the IP Magnets installed for DR Low emittance RF electron gun Upgrade positron capture section
JFY2010 Dismantle KEKB
KEKB
Startup, Conditioning, etc
JFY2011 JFY2012 JFY2013 JFY2014 JFY2015 JFY2016 JFY2017 For about 10 years QCS install Belle II roll in Phase 1 Phase 2, 3 ・・・ ・・・ DR
RUN # Beam power [kw] Painting condition Average foil hit number #57-60 300 100 37.5 #61 300 to 400 100 37.5 #62 400 to 500 150 18.4
–2014/10/22 (12:00:31)
#57
–2014/11/03 (00:00:30)
#58
–2014/11/26 (00:00:22)
#59
–2015/01/05 (09:54:04)
#60
–2015/02/19 (03:00:00)
#61
Experience of J-PARC RCS in the routine operation with 300 - 500 kW
4x10
18
3 2 1
injection particle
2014/10/01 2014/11/01 2014/12/01 2015/01/01 2015/02/01 2015/03/01 2015/04/01
RUN 57 - 62
4x10
21
3 2 1
total inj. particle
RUN57 RUN58 RUN59 RUN60 RUN61 RUN62
Accumulate particles from Linac Beam Power [kW] 300 [kW] 400 [kW] 500 [kW] HBC (Hybrid Boron doped Carbon Thickness:340μg/cm2 Irradiation history: Start: November 22th 2014 Total dose @April 18th 2015
4.40x1021
through the foil (including circulating particles at RCS):1.56x1023
Innovative methods like laser stripping are developed for the future much higher beam power.
electrons when power >1.2 MW
Courtesy M. Plum
ID Trans.-paint ( mm mrad) RF V2/V1 (%) (deg) dp/p (%) 1
100
4
5
6 100 80
7 100 80
8 100 80
○ Einj=181 MeV, 540 kW-eq. ○ Einj=400 MeV, 553 kW-eq. ○ Einj=400 MeV, 553 kW-eq.
Beam intensity (x1013) Einj=181 MeV Einj=400 MeV Time (ms)
Collimators plays an important role to reduce uncontrolled beam loss and keep low residual radioactivity for hands-on maintenance.
by Roderik Bruce, CERN LHC from WS at ESS Lund, May 2014
LHC Collimator system:
momentum cleaning.
J-PARC MR
Space charge can limit performance of high intensity synchrotrons. For high power beam operation, it is necessary to avoid betatron resonances in the presence of space charge tune shift .
J-PARC MR :
Correction of linear coupling resonance with skew quadrupoles in J-PARC MR
(22.41, 20.76)
SQs OFF SQs ON
Skew-Q off ---
Number of protons ( x1013 ppp) Two bunches, 3-GeV accumulation (not accelerated) 4.0 6.0 SQs reduces the beam loss > 1kW for 330 kW beam operation.
This correction makes possible to adopt higher vertical tune to reduce the effect of the half-integer resonance. Correction of third-order resonances with trim sextupoles in J-PARC MR
Trim-SFA048 = 0.3 A To correct Qx+2Qy=64
Number of protons ( x1012 ppb)
2nd harmonic RF voltage in J-PARC MR
(V1, V2) = (100 kV, 0 kV) Bunching factor is increased by the 2nd rf voltage (V1, V2) = (100 kV, 36 kV) Beam survival ratio for 360 kW operation
2nd on 2nd off
Transverse instabilities are observed at the injection and the beginning of acceleration at the MR. The instabilities are suppressed by the bunch feedback systems.
BxB FB since 2012
Acceleration start 4 times beam injection
400 ms
Intra-bunch FB since 2014
Without FB BxB on intra-B on
Feedback ON Feedback OFF
Bunch signal at 100 turns
Feedback ON Feedback OFF
Without FB BxB FB on intra-bunch FB on
Oscillation of one bunch slice
In the ISIS synchrotron, the head-tail beam instability causes beam loss at 2
Courtesy J. Thomason
BPM electrode sum (top), difference (bottom) Head Tail Instability Signal
Injection, capture, head tail loss A new beam feedback system to damp the instabilities is under development.
Synchrotron and rings have much higher residual activation. But they should be improved by better understanding beam loss mechanism and reducing uncontrolled beam losses in spite of beam intensity increasing.
Thanks all the contributors;
Sheng Wang (CSNS)
Takano, F. Tamura, T. Toyama (J-PARC)
KEKB tunnel:
200 m x 4 = 800 m
the next straight section. 550 m x 4 = 2200 m Feasibility of 9 GeV proton linac in straight sections of 800 m. ⇒ High acceleration field is required. ⇒ ILC cavity is adopted. We start discussion as one of the post-Super KEKB project.
1.2 GeV 3.3 GeV 6.2 GeV 9 GeV 1.3 GHz g = 1.0 1.3 GHz g = 1.0 1.3 GHz g = 0.93 9 GeV
3.3 + 2.9 x 2 = 9.0 GeV
9000 MeV x 0.1 A x 1 % = 9 MW
: βg = 0.93
: 0.30 π・mm・mrad
To Kamioka
650 MHz rebuncher x 3 1.3 GHz rebuncher x 3 1.3 GHz rebuncher x 3
55
PB1 ,2 PB3 ,4 QF L Q DL SB 1 SB 2 SB 3 SB 4
x
ISEP 1,2
1st foil
s
MWPM3 MWPM4 MWPM5 2nd foil 3rd foil
H- H- H0
Circulating beam
H+
H- H0
H+
Beginni ng of paintin g End of paintin g
exchange
(400MeV)
2015/03/21
Horizontal painting: by a horizontal closed orbit variation during injection Vertical painting: by a vertical injection angle change during injection Transverse painting makes use of a controlled phase space offset between the centroid of the injection beam and the ring closed orbit to form a different particle distribution of the circulating beam from the multi-turn injected beam.
Typical painting emittance is tp= 100 – 150 mm mrad
No transverse painting 100 correlated painting Horizontal Vertical
Numerical simulations Transverse beam distribution just after the beam injection (at 0.5 ms)
Longitudinal painting makes use of a controlled momentum offset to the rf bucket in combination with superposing a second harmonic rf to get a uniform bunch distribution after the multi-turn injection. Momentum offset injection
p/p=0, 0.1, 0.2%
RF voltage pattern
Uniform bunch distribution is formed through emittance dilution by the large synchrotron motion excited by momentum
The second harmonic rf fills the role in shaping flatter and wider rf bucket potential, leading to better longitudinal motion to make a flatter bunch distribution.
Fundamental rf Second harmonic rf
V2/V1=80%
V2/V1=0
Vrf=V1sinV2sin{2(s)+2} Phase sweep of the second harmonic rf
2=100 deg 2=50 deg 2=0
The second harmonic phase sweep method enables further bunch distribution control through a dynamical change of the rf bucket potential during injection.
Additional knob in the longitudinal painting ; phase sweep of V2
2=100 to 0 deg
V2/V1=80%
No longitudinal painting V2/V1=80% 2=-100 to 0 deg p/p= 0.0% V2/V1=80% 2=-100 to 0 deg p/p=-0.1% V2/V1=80% 2=-100 to 0 deg p/p=-0.2%
Measurements (WCM) Numerical simulations Longitudinal beam distribution just after the beam injection (at 0.5 ms) Bunching factor : ~0.15 ⇒ >0.4
Bf=0.15 Bf=0.40
Wiggler magnets Nikko-side (L-side) of IR Beam pipes installed in Tsukuba IR area (Nikko side)
IP Arc
Horizontal type collimator
e- e+
6 ARES cavities in D5 relocated from HER to LER 6 ARES cavities in D5 relocated from HER to LER
Iron support and concrete floor already set at IP for Phase 1 Beam pipes at IP
Additional shielding walls will be constructed in Oct. 2015. IR cover and large gate concrete shields will be set to IR in autumn 2015.
Wiggler magnets Nikko-side (L-side) of IR Beam pipes installed in Tsukuba IR area (Nikko side)
IP Arc
Horizontal type collimator
e- e+
6 ARES cavities in D5 relocated from HER to LER 6 ARES cavities in D5 relocated from HER to LER
Completed ESL compensation
divided into 12 small solenoids.
Assemblies of the quadrupole magnets and corrector magnets are progressing for the construction of the QCSL cryostat.
– Construction of the tunnel and buildings was completed. – Magnet installation was completed for the beam transport lines (LTR and RTL). – Installation of high power cables in the ring was completed. – All power supplies for the magnets were delivered. (except for steerings) – Beam pipes for the arcs were delivered and TiN coating is going on. – Beam pipes for straights are in fabrication. – Two RF cavities have been fabricated. Results of HP test exceeded specifications.
– Installation and startup work continues in JFY2015. – Commissioning of DR will start in JFY2016 in the transition period between Phase 1 and 2.
Cross section Antechamber-type beam pipe for arcs Magnets in tunnel Cross section DR RF cavity Magnets in LTR