student services relocation efforts
play

Student Services Relocation Efforts Movezilla - PowerPoint PPT Presentation

Student Services Relocation Efforts Movezilla February 2017 History | Overview Main Goal for Movezilla is to achieve a one stop Student Services Shop in Bouillon Massive move stems


  1. Student Services Relocation Efforts “ Movezilla ” February 2017

  2. History | Overview • Main Goal for “ Movezilla ” is to achieve a one stop Student Services Shop in Bouillon • Massive move stems from a 2007 CWU South Neighborhood study focusing on consolidating student services • Geology & Physics moved into new space (Science II) summer of 2016 allowing for transitions to start

  3. 2007 South Neighborhood Study

  4. “ Movezilla ” Phasing Phase # Date Activity From To 1 Jan-17 Clean & Configure Hebeler 2 Feb-17 Move Enrollment Mgt & Admissions Mitchell (1st floor west) Hebeler 3 Feb-17 Clean & Configure Mitchell (1st floor (west)) 4 Feb-17 Move Human Resources Bouillon 140 Mitchell (1st floor (west)) 5 Mar-17 Clean & Configure Bouillon 140 6 Apr-17 Move Registar Mitchell (1st floor (east)) Bouillon 140/144 7 Apr-17 Move Payroll Mitchell (2nd floor) Mitchell (1st floor) 8 Apr-17 Move Human Resources Bouillon 203 Mitchell (1st floor) 9 Apr-17 Admission Processors Hebeler Bouillon 203 10 May-17 Move Connection Card Office SURC 131 Bouillon 104 11 5/31/2017 Substantial Completion (Lind) 12 5/31/2017 Substantial Completion (Boullion) 13 Jun-17 Move Communications Bouillon (2nd floor) Lind (1st floor) 14 Jun-17 Move ROTC Peterson Lind (2nd floor) 15 Jun-17 Clean & Configure Bouillon (Comm Space) 16 Jul-17 Move Testing Bouillon (1st floor) Bouillon (2nd Floor) 17 Jul-17 Move Financial Aid Counselors Barge 115 Bouillon (Comm Space) 18 Jul-17 Move Student Accounts & Cashiering Barge 105 Bouillon (Testing Space) 19 Aug-17 Clean & Configure Barge 115 & 105

  5. Scale of “ Movezilla ” • 175+ Staff being relocated • Seven buildings being affected

  6. What will Bouillon look like? FALL 2017 First Floor Legend Second Floor Legend Second Floor First Floor

  7. BOUILLON, LIND, OLD HEAT receiving upgrades SOUTH NEIGHBORHOOD Bouillon east entry receiving a ‘make - over’

  8. Questions? More Information & Updates Visit: www.cwu.edu/movezilla

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.