structural system redesign
play

Structural System Redesign Existing Conditions Proposal Gravity - PowerPoint PPT Presentation

Structural System Redesign Existing Conditions Proposal Gravity Design Lateral Design Cost Comparison Schedule Impact Conclusions Existing Conditions Existing Conditions Proposal Gravity Design


  1. Structural System Redesign • Existing Conditions • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  2. Existing Conditions • Existing Conditions • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact Location: New York, NY Owner: NYC HHC • Conclusions Architect: RMJM Hillier Structural Engineer: Greenman-Pedersen Inc. Construction: September 2008 – Mid 2012 Cost: $160 million overall project cost Delivery: Design-Bid-Build with multiple prime contracts

  3. Existing Conditions • Existing Conditions • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact •75,000 sq. ft. Addition to Existing Hospital • Conclusions •13 Stories •Steel Framed Addition •Concrete Existing Structure •11’ Floor-to-Floor

  4. Existing Conditions • Existing Conditions • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions 3 rd Floor Framing Plan 8 th Floor Framing Plan •Cellular Beams for all Gravity Members •Moment Frames •Braced Frames

  5. Design Choices Existing Conditions - Use of Steel Framing • Existing Conditions - Removal of Column Line - Use of Moment Frames • Proposal • Gravity Design Impact • Lateral Design - Need Cellular Beams • Cost Comparison - Heavy Lateral Members • Schedule Impact - Further Restrictions on MEP systems • Conclusions

  6. Proposal - Redesign current, steel-framed addition • Existing Conditions as a concrete structure utilizing two-way • Proposal flat plate slab and shearwalls Proposal • Gravity Design • Lateral Design Design Goals • Cost Comparison - Maintain regularity in design Slab • Schedule Impact Column • Conclusions Shearwalls - Provide design freedom for other systems - Design a more cost effective structural system

  7. Codes - ASCE7-05 • Existing Conditions - Wind Loads as per Chapter 6 • Proposal - Seismic Loads using Equivalent Later Force Proposal - ACI 318-08 • Gravity Design • Lateral Design • Cost Comparison Methodology • Schedule Impact - ETABS • Conclusions - RAM Concept - PCA Column - Microsoft Excel

  8. Gravity System Structure Overview -12” slab • Existing Conditions - f c ’ = 6ksi • Proposal - 22’ x 24’ bay -16” columns • Gravity Design - 20” columns • Lateral Design Lateral System • Cost Comparison - 6 shearwalls • Schedule Impact -16” shearwalls • Conclusions - 20” shearwalls 3 rd Floor Plan

  9. Design Loads • Existing Conditions - 26 psf Superimposed Dead Load Gravity Design - 80 psf Live Load • Proposal • Gravity Design Deflection Limits • Lateral Design - L/360 Immediate Live Load Defl. - L/480 Long-term Deflection • Cost Comparison - L/240 Long-term Deflection • Schedule Impact Creep Factor = 2 • Conclusions 20% of Live Load

  10. • Existing Conditions • Proposal Slab Design • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions Bottom Reinforcing 3 rd Floor Reinforcing Plan

  11. • Existing Conditions • Proposal Slab Design • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions Top Reinforcing 3 rd Floor Reinforcing Plan

  12. • Existing Conditions • Proposal Slab Design • Gravity Design Initial. LL Deflection: • Lateral Design 0.0555 in • Cost Comparison Allowable: L/360 = 0.80 in • Schedule Impact Max. long-term Deflection: • Conclusions 0.4438 in Allowable: L/480 = 0.60 in 3 rd Floor Deflection Plan

  13. • Existing Conditions Column Design • Proposal • Gravity Design • Lateral Design • Cost Comparison Columns supporting 6 stories: 16” x 16” f c ’= 6 ksi • Schedule Impact Columns supporting 13 stories: • Conclusions 20” x 20” f c ’= 6 ksi Typical Column Details

  14. • Existing Conditions Column Design • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions Slender Column Design

  15. • Existing Conditions Column Design • Proposal • Gravity Design • Lateral Design • Cost Comparison Column G/5.8 (6 stories): 16” x 16” f c ’= 6 ksi • Schedule Impact Column F/5.8 (13 stories): • Conclusions 22” x 22” f c ’= 6 ksi Slender Column Design

  16. Transfer Beam Design Column Shift - Control Deflections • Existing Conditions - Match Floorplan • Proposal Layout • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions 9 th Floor Plan

  17. - 60” deep beam Transfer Beam Design Column Shift - 20” width - Control Deflections • Existing Conditions - Match Floorplan • Proposal Layout • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  18. - 60” deep beam Transfer Beam Design - 20” width • Existing Conditions • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  19. Design Assumptions ETABS - Diaphragms modeled as Rigid and Semi-Rigid • Existing Conditions Lateral Design - Shearwalls modeled as Membranes • Proposal - 0.7 f 22 modifier for shearwalls • Gravity Design -0.35 I 3 modifier for coupling beam -Deflection: H/400 for wind • Lateral Design 0.015h x for seismic 3.00” overall floor deflection • Cost Comparison 3.50” overall deflection at roof • Schedule Impact • Conclusions 12.12.3 Building Separation. All portions of the structure shall be designed and constructed to act as an integral unit in resisting seismic forces unless separated structurally by a distance sufficient to avoid damaging contact under total deflection ( δ x ) as determined in Section 12.8.6

  20. Seismic Forces Lateral Design - Seismic Equivalent Lateral Force Procedure - Seismic Design Category SDC = B • Existing Conditions - Importance Factor I = 1.15 • Proposal - Response Modification Coeff. R = 4 - Deflection Amplification Factor Cd = 4 • Gravity Design - Base Shear V = 303 k • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  21. Seismic Deflection Lateral Design - Seismic ETABS Elastic Analysis - EX Overall Deflection = 1.6257” • Existing Conditions - EY Overall Deflection = 1.1233” • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  22. Final Seismic Deflection Lateral Design - Seismic Accidental Torsion - Force applied at 5% eccentricity • Existing Conditions - Amplification of torsion: • Proposal A= (d max /(1.2*d avg )) 2 (Figure 12.8-1) • Gravity Design d max = 1.693” A x = 0.804 therefore A x = 1.00 d avg = 1.573” • Lateral Design Amplified Seismic Deflections - Amplification of Elastic Output • Cost Comparison δ x =C d δ xe /I *(T a /T) (eq 12.8-15) • Schedule Impact -Maximum Overall Floor Deflection • Conclusions 2.9393” (EXMZ) < 3.00” upper limit -Maximum Overall Roof Deflection 3.2132” (EXMZ) < 3.50” upper limit -Maximum Story Drift < 0.015 max allowable 0.0022 (EXMZ)

  23. Wind Forces Lateral Design - Wind - Basic Wind Speed V = 100mph - Importance Factor I = 1.15 • Existing Conditions - Base Shear X-dir V = 382 k • Proposal - Base Shear Y-dir V = 314 k • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  24. Controlling Case - Seismic Deflection governed design - Wind Combinations produced highest forces • Existing Conditions Lateral Design - Provide Minimum Reinforcing: • Proposal (2) #5 bars @ 12” O.C. Each Way • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  25. Existing vs. Proposed - Compared elements of structure that change Cost Comparison - Assumed 3% O&P • Existing Conditions - Materials, Labor, and Equipment • Proposal - Moment Connections not considered • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  26. Existing vs. Proposed - Existing Foundation $ 901,050 Cost Comparison - Proposed Foundation $ 1,281,495 • Existing Conditions - Percent Increase ~ 40% • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  27. Existing vs. Proposed Cost Comparison • Existing Conditions • Proposal • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  28. Existing vs. Proposed - Existing Structure $ 10,329,667 - Proposed Structure $ 9,760,392 Cost Comparison • Existing Conditions - Percent Saving ~ 5% • Proposal - Overall Project Cost $ 130,000,000 • Gravity Design • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

  29. Existing vs. Proposed - Existing Structure sequenced in two portions - Existing Duration 6.5 Months Schedule Impact • Existing Conditions - Proposed Structure sequenced in three portions • Proposal ~ 3 weeks per floor • Gravity Design - Proposed Duration 12 Months • Lateral Design • Cost Comparison • Schedule Impact • Conclusions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend