thesis 2005
play

Thesis 2005 Cira Centre Philadelphia Structural Redesign of - PowerPoint PPT Presentation

Thesis 2005 Cira Centre Philadelphia Structural Redesign of Lateral Force Resisting System Andrew Kauffman Structural Option Presentation Outline Introduction Building Description Structural System Problem Statement Solution Overview


  1. Thesis 2005 Cira Centre – Philadelphia Structural Redesign of Lateral Force Resisting System Andrew Kauffman Structural Option

  2. Presentation Outline Introduction Building Description Structural System Problem Statement Solution Overview Structural Redesign Mechanical Redesign Conclusion

  3. INTRODUCTION

  4. Introduction Adjacent to 30 th Street Train Station - Philadelphia, PA 291,000 s.f., 28 story high rise office building Convention center, restaurants and retail space Tallest building in Philadelphia, outside Center City Scheduled for completion – October 2005 Total Projected Cost – $200 million

  5. DESCRIPTION BUILDING

  6. Building Description – Project Team Architects – Cesar Pelli and Assoc./Bower Lewis Thrower General Contractor – Turner Construction Co. Structural Engineer – Ingenium Inc. Civil Engineer – Pennoni Assoc. MEP Engineer – Jaros Baum and Bolles Lighting Design - Cline Bettridge Bernstein Acoustic Consultant - Cerami and Associates Curtain Wall Consultant - Israel Berger and Associates

  7. Building Description- Architectural Features 725,000 s.f. rentable space Open plan office levels: 727,725 s.f. (average) 9 ft. floor to ceiling heights Pedestrian bridge connecting to 30 th Street train station Single point of entrance in main lobby, added security Highly reflective glass curtain wall

  8. Building Description – Building Systems Electrical – 13.2 KV primary voltage 480Y/277 volt, 3 phase, 4 wire Secondary system Mechanical – Fan powered, VAV system Includes 4 cooling towers located in top mezzanine Conveying – 14 high speed traction elevators Low-rise, mid-rise, high-rise Configuration

  9. STRUCTURAL SYSTEM

  10. Structural System – Overview Steel frame super-structure Composite floor system Drilled pier foundation Lateral System: Combination of braced and moment frames

  11. Structural System – Floor System Fully composite, 5 ¼ in. floor system, with LW concrete, metal decking, 50 ksi steel framing members W18x35 and W24x76 typical beams and girders, 30’x30’ bays, typ. 7'-11" 30' 30' 30' 30' 30' 30' 30' 7'-8" A 12'-6" B 30' N C 30' D 30' E 12'-6" F 1 2 3 4 5 6 7 8 9 10

  12. Structural System – Vertical Framing Drilled concrete piers with up to 21.5’ penetration into bedrock Large built-up column sizes including W36x1202 wide flange members and 829 lb/ft. built-up box sections Forking Columns Leaning Columns

  13. Structural System – North/South Building Section 7'-11" 30' 30' 30' 30' 30' 30' 30' 7'-8" A 12'-6" B 30' N C 30' D 30' E 12'-6" F 1 2 3 4 5 6 7 8 9 10

  14. North/South Section

  15. Structural System - East/West Section 7'-11" 30' 30' 30' 30' 30' 30' 30' 7'-8" A 12'-6" B 30' N C 30' D 30' E 12'-6" F 1 2 3 4 5 6 7 8 9 10

  16. East-West Section MAC H RO O M MAC H RO O M RO O M MEC H C O NFERENC E

  17. Structural System – Lateral System East/West - Located in building core Combination of braced frames and moment connections A B LAT ERAL FRAMES EL EVAT O RS ST AI R N T O WERS C LAT ERAL FRAME D E F 10 1 2 3 4 5 6 7 8 9

  18. Structural System – Lateral System East – West Direction Along column lines C & D Located in structural core Exterior braced frames Interior moment frames

  19. Structural System – Lateral System North/South – Located in building core Combination of braced frames and moment connections A B LAT ERAL FRAMES EL EVAT O RS ST AI R N T O WERS C LAT ERAL FRAME D E F 10 1 2 3 4 5 6 7 8 9

  20. Structural System – Lateral System North - South Lateral System Along column lines 4 & 7 Located in Structural Core Exterior Moment Frames Interior Braced Frames

  21. Structural System – Lateral System North/South – Located along exterior frames Only moment frames A B LAT ERAL FRAMES EL EVAT O RS ST AI R N T O WERS C LAT ERAL FRAME D E F 10 1 2 3 4 5 6 7 8 9

  22. Structural System – Lateral System 28 27 North - South Lateral System 26 25 24 Along column lines 1 & 10 23 22 21 20 All moment frames 19 18 17 16 Varying stiffness 15 14 13 12 11 10 9 8 7 6 5 4 3 2

  23. STATEMENT PROBLEM

  24. Problem Statement – Overview Complicated Structure to Analyze • Varying Floor Geometry • Large built-up members Complicated Lateral System 1. Combination of braced and moment frames 2. Lateral frames with varying stiffness

  25. Problem Statement – Lateral Load Assumptions Lateral Loads used in actual design were developed using a wind tunnel analysis Wind Tunnel results yielded 65% of total shear and 75% of the overturning moment, compared to ASCE7-02, analytical method. Strength considerations did not control the original design of the building. Torsional acceleration at corner offices was the limiting factor that controlled the design

  26. SOLUTION OVERVIEW

  27. Solution Overview – Lateral System Redesign Develop wind and seismic loads based on ASCE7-02 Redesign Lateral System based on these loads. Compare cost of redesign to cost of original structure

  28. Solution Overview – Design Goals Gain a better understanding of lateral force resisting system design for steel buildings Investigate alternative lateral system configurations Meet the design criteria of IBC 2003. Limit interstory drift Limit overall building drift to L/400 criteria Achieve an economically feasible design Optimization of original design was not a goal

  29. Solution Overview - Procedure Develop wind loads using Analytical Procedure Model 2-D lateral frames using GT Struddle Determine relative stiffness based on virtual loads Distribute loads based on stiffness and torsion analysis Analyze frames for deflection and interstory drift Redesign lateral frames based on drift criteria - iterative Compare cost of redesign to original structural system

  30. Solution Overview – Mechanical Breadth Study Analyze feasibility of adding enthalpy wheels to the original mechanical system. Goal: Utilize the properties of building exhaust to save $$$

  31. STRUCTURAL REDESIGN

  32. Structural Redesign – Stiffness Analysis Created model of each lateral frame in GT Struddle 100k virtual load at top of each frame to measure relative stiffness A B LAT ERAL EL EVAT O RS FRAMES ST AI R N T O WERS C LAT ERAL FRAME D E F 1 2 3 4 5 6 7 8 9 10

  33. Structural Redesign – East/West Lateral Frames Column Lines C & D Equal Stiffness Distribute half of total story load to each frame Equal distance from center of plan Torsion had minimal effect in this direction

  34. Structural Redesign – Load Distribution

  35. Structural Redesign - Results Total Deflection: 13.25” L/400 = 13.08” Acceptable based on occupancy comfort

  36. Structural Redesign – North/South Direction Modeled lateral frames along Column Lines 1,4,7,10 Applied Virtual Load at levels 28,20,10 A B LAT ERAL EL EVAT O RS FRAMES ST AI R N T O WERS C LAT ERAL FRAME D E F 1 2 3 4 5 6 7 8 9 10

  37. CL 10 Structural Redesign – North/South Direction CL 4/CL 7 CL 1

  38. Structural Redesign – North/South Direction Relative stiffness varied with height. Applied uniform 10 kip load to verify stiffness Plotted results and fit equation Solved equation for stiffness in terms of height Relative Lateral Frame Stiffness 400 y = 23584x - 2049.3 350 300 CL4 Building Height (ft.) 250 CL10 CL1 200 Linear (CL1) y = 2088.6x - 122.41 Linear (CL10) 150 Linear (CL4) 100 y = -3839.6x + 1640.3 50 0 0 0.1 0.2 0.3 0.4 0.5 K - Relative Stiffness

  39. Structural Redesign – North/South Direction Performed torsion analysis at each level based on center of rigidity Included 5% eccentricity per code, and determined loads on frames L e ve l 20 A B N C Ce ntre of Rig idty 21 ' 90 Kips D 1,900 F t. Kips E F 1 2 3 4 5 6 7 7 8 10 390 PSF

  40. Structural Redesign – North/South Direction Applied load to models in GT Struddle and analyzed results

  41. Structural Redesign – Results Each lateral frame deflected equal amounts. All frames deflected well over the L/400 limit. 19.92” 19.99” 17.16”

  42. Structural Redesign – Solution Alleviate interstory drift problems Limit overall building drift to 12” Started with exterior frames A B L AT ERAL FRAMES EL EVAT O RS ST AI R N T O WERS C L AT ERAL FRAME D E F 1 2 3 4 5 6 7 8 9 10

  43. Structural Redesign – North/South Direction Analyzed several bracing configurations using iterative procedure. Eliminated interstory drift problems, limited total drift to 12”

  44. Structural Redesign – North/South Direction Used same procedure for interior lateral frames along column lines 4 & 7 Could not limit drift to 12” A B LAT ERAL ELEVAT O RS FRAMES ST AI R N T O WERS C LAT ERAL FRAME D E F 1 5 7 10 2 3 4 6 8 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend