Thesis 2005 Cira Centre Philadelphia Structural Redesign of - - PowerPoint PPT Presentation

thesis 2005
SMART_READER_LITE
LIVE PREVIEW

Thesis 2005 Cira Centre Philadelphia Structural Redesign of - - PowerPoint PPT Presentation

Thesis 2005 Cira Centre Philadelphia Structural Redesign of Lateral Force Resisting System Andrew Kauffman Structural Option Presentation Outline Introduction Building Description Structural System Problem Statement Solution Overview


slide-1
SLIDE 1

Thesis 2005

Cira Centre – Philadelphia Structural Redesign of Lateral Force Resisting System Andrew Kauffman Structural Option

slide-2
SLIDE 2

Presentation Outline Introduction Building Description Structural System Problem Statement Solution Overview Structural Redesign Mechanical Redesign Conclusion

slide-3
SLIDE 3

INTRODUCTION

slide-4
SLIDE 4

Introduction

Adjacent to 30th Street Train Station - Philadelphia, PA 291,000 s.f., 28 story high rise office building Convention center, restaurants and retail space Tallest building in Philadelphia, outside Center City Scheduled for completion – October 2005 Total Projected Cost – $200 million

slide-5
SLIDE 5

BUILDING DESCRIPTION

slide-6
SLIDE 6

Building Description – Project Team

Architects – Cesar Pelli and Assoc./Bower Lewis Thrower General Contractor – Turner Construction Co. Structural Engineer – Ingenium Inc. Civil Engineer – Pennoni Assoc. MEP Engineer – Jaros Baum and Bolles Lighting Design - Cline Bettridge Bernstein Acoustic Consultant - Cerami and Associates Curtain Wall Consultant - Israel Berger and Associates

slide-7
SLIDE 7

Building Description- Architectural Features

725,000 s.f. rentable space Open plan office levels: 727,725 s.f. (average) 9 ft. floor to ceiling heights Pedestrian bridge connecting to 30th Street train station Single point of entrance in main lobby, added security Highly reflective glass curtain wall

slide-8
SLIDE 8

Building Description – Building Systems

Electrical – 13.2 KV primary voltage 480Y/277 volt, 3 phase, 4 wire Secondary system Mechanical – Fan powered, VAV system Includes 4 cooling towers located in top mezzanine Conveying – 14 high speed traction elevators Low-rise, mid-rise, high-rise Configuration

slide-9
SLIDE 9

STRUCTURAL SYSTEM

slide-10
SLIDE 10

Structural System – Overview Steel frame super-structure Composite floor system Drilled pier foundation Lateral System: Combination of braced and moment frames

slide-11
SLIDE 11

Structural System – Floor System

Fully composite, 5 ¼ in. floor system, with LW concrete, metal decking, 50 ksi steel framing members W18x35 and W24x76 typical beams and girders, 30’x30’ bays, typ.

1 3 4 5 6 8 D C B A 2 7 9 10 E F 7'-11" 30' 12'-6" 30' 7'-8" 12'-6" 30' 30' 30' 30' 30' 30' 30' 30'

N
slide-12
SLIDE 12

Structural System – Vertical Framing

Drilled concrete piers with up to 21.5’ penetration into bedrock Large built-up column sizes including W36x1202 wide flange members and 829 lb/ft. built-up box sections Forking Columns Leaning Columns

slide-13
SLIDE 13

Structural System – North/South Building Section

1 3 4 5 6 8 D C B A 2 7 9 10 E F 7'-11" 30' 12'-6" 30' 7'-8" 12'-6" 30' 30' 30' 30' 30' 30' 30' 30'

N
slide-14
SLIDE 14

North/South Section

slide-15
SLIDE 15

Structural System - East/West Section

1 3 4 5 6 8 D C B A 2 7 9 10 E F 7'-11" 30' 12'-6" 30' 7'-8" 12'-6" 30' 30' 30' 30' 30' 30' 30' 30'

N
slide-16
SLIDE 16

East-West Section

MEC H RO O M MAC H RO O M MAC H RO O M C O NFERENC E
slide-17
SLIDE 17

Structural System – Lateral System

East/West - Located in building core Combination of braced frames and moment connections

2 7 9 10 E F

N EL EVAT O RS ST AI R T O WERS LAT ERAL FRAMES LAT ERAL FRAME

1 3 4 5 6 8 D C B A

slide-18
SLIDE 18

Structural System – Lateral System East – West Direction

Along column lines C & D Located in structural core Exterior braced frames Interior moment frames

slide-19
SLIDE 19

Structural System – Lateral System

North/South – Located in building core Combination of braced frames and moment connections

2 7 9 10 E F

N EL EVAT O RS ST AI R T O WERS LAT ERAL FRAMES LAT ERAL FRAME

1 3 4 5 6 8 D C B A

slide-20
SLIDE 20

Structural System – Lateral System

North - South Lateral System

Along column lines 4 & 7 Located in Structural Core Exterior Moment Frames Interior Braced Frames

slide-21
SLIDE 21

Structural System – Lateral System

2 7 9 10 E F

N EL EVAT O RS ST AI R T O WERS LAT ERAL FRAMES LAT ERAL FRAME

1 3 4 5 6 8 D C B A

North/South – Located along exterior frames Only moment frames

slide-22
SLIDE 22

Structural System – Lateral System

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24 25 26 27 28 21

North - South Lateral System

Along column lines 1 & 10 All moment frames Varying stiffness

slide-23
SLIDE 23

PROBLEM STATEMENT

slide-24
SLIDE 24

Problem Statement – Overview

Complicated Structure to Analyze

  • Varying Floor Geometry
  • Large built-up members

Complicated Lateral System 1. Combination of braced and moment frames 2. Lateral frames with varying stiffness

slide-25
SLIDE 25

Problem Statement – Lateral Load Assumptions

Lateral Loads used in actual design were developed using a wind tunnel analysis Wind Tunnel results yielded 65% of total shear and 75% of the overturning moment, compared to ASCE7-02, analytical method. Strength considerations did not control the

  • riginal design of the building.

Torsional acceleration at corner offices was the limiting factor that controlled the design

slide-26
SLIDE 26

SOLUTION OVERVIEW

slide-27
SLIDE 27

Solution Overview – Lateral System Redesign Develop wind and seismic loads based on ASCE7-02 Redesign Lateral System based on these loads. Compare cost of redesign to cost of original structure

slide-28
SLIDE 28

Solution Overview – Design Goals Gain a better understanding of lateral force resisting system design for steel buildings Investigate alternative lateral system configurations Meet the design criteria of IBC 2003. Limit interstory drift Limit overall building drift to L/400 criteria Achieve an economically feasible design Optimization of original design was not a goal

slide-29
SLIDE 29

Solution Overview - Procedure Develop wind loads using Analytical Procedure Model 2-D lateral frames using GT Struddle Determine relative stiffness based on virtual loads Distribute loads based on stiffness and torsion analysis Analyze frames for deflection and interstory drift Redesign lateral frames based on drift criteria - iterative Compare cost of redesign to original structural system

slide-30
SLIDE 30

Solution Overview – Mechanical Breadth Study

Analyze feasibility of adding enthalpy wheels to the original mechanical system. Goal: Utilize the properties of building exhaust to save $$$

slide-31
SLIDE 31

STRUCTURAL REDESIGN

slide-32
SLIDE 32

Structural Redesign – Stiffness Analysis

Created model of each lateral frame in GT Struddle 100k virtual load at top of each frame to measure relative stiffness

2 7 9 10 E F N EL EVAT O RS ST AI R T O WERS LAT ERAL FRAMES LAT ERAL FRAME 1 3 4 5 6 8 D C B A
slide-33
SLIDE 33

Structural Redesign – East/West Lateral Frames

Equal Stiffness Distribute half of total story load to each frame Equal distance from center of plan Torsion had minimal effect in this direction

Column Lines C & D

slide-34
SLIDE 34

Structural Redesign – Load Distribution

slide-35
SLIDE 35

Structural Redesign - Results

Total Deflection: 13.25” L/400 = 13.08” Acceptable based on

  • ccupancy comfort
slide-36
SLIDE 36

Structural Redesign – North/South Direction Modeled lateral frames along Column Lines 1,4,7,10 Applied Virtual Load at levels 28,20,10

2 7 9 10 E F N EL EVAT O RS ST AI R T O WERS LAT ERAL FRAMES LAT ERAL FRAME 1 3 4 5 6 8 D C B A
slide-37
SLIDE 37

Structural Redesign – North/South Direction

CL 1 CL 4/CL 7 CL 10

slide-38
SLIDE 38

Relative stiffness varied with height. Applied uniform 10 kip load to verify stiffness Plotted results and fit equation Solved equation for stiffness in terms of height

Structural Redesign – North/South Direction

Relative Lateral Frame Stiffness

y = 23584x - 2049.3 y = 2088.6x - 122.41 y = -3839.6x + 1640.3 50 100 150 200 250 300 350 400 0.1 0.2 0.3 0.4 0.5 K - Relative Stiffness Building Height (ft.) CL4 CL10 CL1 Linear (CL1) Linear (CL10) Linear (CL4)

slide-39
SLIDE 39

Structural Redesign – North/South Direction

Performed torsion analysis at each level based on center of rigidity Included 5% eccentricity per code, and determined loads on frames

1 3 4 5 6 7 D C B A 2 7 8 10 E F N

L e ve l 20

Ce ntre
  • f
Rig idty

390 PSF

21' 1,900 F
  • t. Kips
90 Kips
slide-40
SLIDE 40

Structural Redesign – North/South Direction

Applied load to models in GT Struddle and analyzed results

slide-41
SLIDE 41

Structural Redesign – Results

Each lateral frame deflected equal amounts. All frames deflected well over the L/400 limit.

19.99” 17.16” 19.92”

slide-42
SLIDE 42

Structural Redesign – Solution

Alleviate interstory drift problems Limit overall building drift to 12” Started with exterior frames

2 7 9 10 E F

N EL EVAT O RS ST AI R T O WERS L AT ERAL FRAMES L AT ERAL FRAME

1 3 4 5 6 8 D C B A

slide-43
SLIDE 43

Structural Redesign – North/South Direction

Analyzed several bracing configurations using iterative procedure. Eliminated interstory drift problems, limited total drift to 12”

slide-44
SLIDE 44

Structural Redesign – North/South Direction

Used same procedure for interior lateral frames along column lines 4 & 7 Could not limit drift to 12”

2 7 9 10 E F N ELEVAT O RS ST AI R T O WERS LAT ERAL FRAMES LAT ERAL FRAME 1 3 4 5 6 8 D C B A
slide-45
SLIDE 45

Structural Redesign – North/South Direction

Increased stiffness of exterior lateral frames W14x145 bracing members Additional chevron braces to these frames Limited total drift to 9” Changed bracing of interior frames W14x159 bracing members Increased stiffness of girders to W33x221 Reapplied stiffness analysis and torsion calculations Calculated new story loads

slide-46
SLIDE 46

Results

slide-47
SLIDE 47

Structural Redesign – Cost Analysis

Used R.S. Means to estimate total cost of original structure 20% total building cost = $ 40 million Performed take-off to calculate cost of lateral system redesign Compared additional cost to overall structural cost Cost Increase = 0.6% Structure Cost Cost Increase = 0.1% Structure Cost

slide-48
SLIDE 48

Mechanical Redesign

slide-49
SLIDE 49

Mechanical System Redesign

Fan powered VAV system Supply Air: 80% return, 20% outdoor air Exhaust: based on 150 cfm/toilet, 20 cfm/sink Typical Air Handler Size: 23,500

System Description Procedure

Use ASHRAE Bin data to analyze a full year cycle Based on 2 design condition: on peak – business hours,

  • ff peak – evenings and weekends

Calculated total building load with/without use of enthalpy wheel Compared loads and calculate savings

slide-50
SLIDE 50

Mechanical System Redesign – Typical Floor

Total Savings = Sensible Load savings + Latent Load savings Enthalpy wheels turned off when no energy is saved Additional energy can be saved by modulating wheel

slide-51
SLIDE 51

Mechanical System Redesign - Results

Using Peco Energy Rates: Total Energy Savings: 671,236 kwh Total Cost Savings: $28,506/year

slide-52
SLIDE 52

CONCLUSION

slide-53
SLIDE 53

Conclusion Based on lateral load assumptions used for this analysis, the lateral frames in the North/South direction should be designed with increased stiffness based on occupancy comfort criteria. Redesign of lateral force resisting system is an economic solution compared to overall cost of structure Enthalpy wheels should be utilized by the mechanical system to increase overall efficiency and save $$$.

slide-54
SLIDE 54

Acknowledgments

AE Faculty and Staff

  • Dr. Memari and Dr. Geschwindner
  • Dr. Hanangan and Prof. Parfitt

Jeff Weinstein and Andy Bush, Brandywine Realty Trust

  • Dr. Banavalker, Ingenium Inc.

Peter Jennings, Jaros, Baum, and Bolles My Family and Friends My wife Nicole

slide-55
SLIDE 55