Stormwater Management in the City of Annapolis Raycine M. Hodo - - PowerPoint PPT Presentation
Stormwater Management in the City of Annapolis Raycine M. Hodo - - PowerPoint PPT Presentation
Stormwater Management in the City of Annapolis Raycine M. Hodo Environmental Compliance Inspector City of Annapolis Watershed Implementation Plan 12 sub-watersheds 15 miles of natural streams 38.5 percent impervious Residential
City of Annapolis
Watershed Implementation Plan
- 12 sub-watersheds
- 15 miles of natural
streams
- 38.5 percent impervious
- Residential
Neighborhoods
- Commercial and
Industrial Areas
- Institutional Properties
- State and County Roads
Project Goals
- Comply with regulatory requirements including the 20%
impervious area reduction
- Improve water quality
- Reduce runoff from rain events there by reducing
localized flooding
- Improve overall health of natural resources in the City
- Support storm water utility
CHESAPEAKE BAY TMDL
TMDL in 2010 for:
- Sediment
- Nitrogen
- Phosphorus
Target Reductions for 2025
- 25% less Nitrogen
- 24% less Phosphorus
- 20% less Sediment
Target Reductions for 2017
- 60% of 2025 target reductions
to be achieved
STORM WATER MANAGEMENT INVENTORY
Summary of Inventory
Total Number Design Plan Sets Scanned 351 Total Number of Pages Scanned 1,725 Total Number of BMPs Identified 741
UPCOMING PROJECT TASKS
Pollutant Load Modeling
- Existing conditions
- Proposed conditions
Stormwater Management Concepts
- 30% design
- Detailed cost estimate
- Utilities impacts
- Environmental impacts
- Recommended maintenance
Evaluation and Ranking
- Implementation Cost
- Impervious area credits
- Pollutant Removal
Final report
Considerations
Challenge
- Funding
Solution
- Storm water utility
- Grants
- Chesapeake Bay Trust
- Maryland Department of
Natural Resources (MD DNR) Grants
Installing Stormwater Management Facilities
- Stormwater Design Manual
2000 Volume I and II serves as the guide for stormwater management principles
- Describes the Environmental
Site Design (ESD) to the Maximum Extent Practicable (MEP)
- ESD is Stormwater design
strategies that seek to replicate natural hydrology
When is a Permit Required?
- Limit of Disturbance (LOD)
– Waterfront lot with greater than 2000 SF of disturbance – Non-Waterfront lot with greater than 5000 SF
- f disturbance
- Excavation and Fill exceeds 100 CY total.
Grading Permits – The Three Phase Process
- Concept Approval
– Makes sure the overall design will work in theory – This may be covered in P&Z submission or FCA submission
- Design Approval
– Develops the design to construction ready documents – Review is completed by several departments including P&Z, DPW and DNEP
- Final Design Approval
– Final Design is sent to AASCD for approval – Collection of Bonding associated with the project – Development of Stormwater Maintenance Agreement
Stormwater Management Credit
- Stormwater Management Credit
Application for Residential
- Site Plan showing property lines
and location of stormwater management device.
- For stormwater facilities installed
through a grading permit with the City: A copy of the Stormwater Management Facility Maintenance Agreement.
- Schedule a site visit which will be
performed to verify your application.
Thanks
- AECOM
- Matthew Waters, Stormwater
Management Engineer
- Frank Biba, Chief Environmental
Programs
- Maria Broadbent, Director DNEP