Bolton Reserve Stormwater Retention and Re-use System Innovative - - PowerPoint PPT Presentation

bolton reserve stormwater retention and re use system
SMART_READER_LITE
LIVE PREVIEW

Bolton Reserve Stormwater Retention and Re-use System Innovative - - PowerPoint PPT Presentation

Bolton Reserve Stormwater Retention and Re-use System Innovative Stormwater Harvesting Project! Project Summary Stormwater harvesting system designed to collect and store up to 7 million litres of stormwater per year Stormwater is


slide-1
SLIDE 1

Bolton Reserve Stormwater Retention and Re-use System

Innovative Stormwater Harvesting Project!

slide-2
SLIDE 2

Project Summary

  • Stormwater harvesting system designed to

collect and store up to 7 million litres of stormwater per year

  • Stormwater is diverted from the Council

underground drainage network. It is then treated and stored in underground storage tanks (1 million litre capacity) ready to be reused for:

– Flushing of toilets at the Box Hill City Oval – Irrigation of the Oval and surrounding reserve – Street cleansing, drain cleaning and plant watering via a hydrant and trucks

slide-3
SLIDE 3

Project Details

  • Project Team

– Project Management & Construction Supervision – City of Whitehorse – Detailed Design – Fisher & Fisher – Construction – Entracon Civil

  • Project Budget

– $740,000 including $150,000 grant from the State Government’s Stormwater and Urban Water Conservation Fund

slide-4
SLIDE 4

Project Objectives

  • To treat and reuse stormwater to save

potable water

  • To ensure the system is affordable and

easy to maintain

  • To address under capacity in the

existing stormwater system

slide-5
SLIDE 5

Innovative Design Elements

  • The system diverts stormwater from underground

drains and treats the stormwater by passing through a CDS gross pollutant trap and a sand bio-retention system.

  • The stormwater is stored in 4 underground tanks.
  • The tanks comprise of excavations that are lined with a

geosynthetic clay liner and geofabric.

  • The tanks are filled with scoria aggregate.
  • The water is stored in the voids of the aggregate.
  • The tanks are covered with a geofabric layer, sand, fill

material and topsoil.

  • Electric pumps, water purity monitors , delivery piping

and other piping works are installed.

slide-6
SLIDE 6

Site Location

Bolton Reserve prior to works commencing. Site is to be restored back to this condition upon completion. Site Location Bolton Reserve Box Hill City Oval

slide-7
SLIDE 7
slide-8
SLIDE 8

Step 1 - Excavation

slide-9
SLIDE 9

Step 2 - Storage Tank Lining

  • Bentofix thermal lock geosynthetic clay liner
  • verlayed with geofabric and sand on the base
slide-10
SLIDE 10

Step 3 - Filter Media

  • Storage media 25mm scoria aggregate
slide-11
SLIDE 11

Step 4 – Pit Installation

  • Pump pits
  • Access & sampling pits
  • Gross pollutant trap
  • Bio retention filter
slide-12
SLIDE 12

Step 5 - Reinstatement

  • Scoria covered with geofabric, sand, fill

material and then top soil and grass

slide-13
SLIDE 13

Step 5 – Plumbing & Reticulation

  • Pumps and reticulation pumps installed
slide-14
SLIDE 14

Project Successes

  • Communication and consultation with key stakeholders

during project development including maintenance personnel

  • Open space is retained as the system is buried

underground and reinstated as parkland

  • Savings in potable water of up to 7 million litres per

year giving Council the resources to use water during water restrictions

  • Innovative cost effective design eliminating the need to

construct detailed and expensive structures

  • Improves drainage capacity of network by providing

storage volume both underground and above ground