Status of HV power supply and HV feedthrough for the 6x6x6 C. - - PowerPoint PPT Presentation

status of hv power supply and hv feedthrough for the 6x6x6
SMART_READER_LITE
LIVE PREVIEW

Status of HV power supply and HV feedthrough for the 6x6x6 C. - - PowerPoint PPT Presentation

Status of HV power supply and HV feedthrough for the 6x6x6 C. Cantini, P. Chiu, A. Gendotti, L. Molina Bueno, S.Murphy, A. Rubbia, C. Regenfus, F. Sergiampietri High voltage system Insulation space GAr Anode LEM CRP Extraction grid Field


slide-1
SLIDE 1

Status of HV power supply and HV feedthrough for the 6x6x6

  • C. Cantini, P. Chiu, A. Gendotti, L. Molina Bueno, S.Murphy, A. Rubbia,
  • C. Regenfus, F. Sergiampietri
slide-2
SLIDE 2

2

High voltage system

Anode LEM Extraction grid CRP

300 kV Heinzinger power supply (PSU)

Insulation space Field cage Field shapers TPC LAr GAr

  • 300 kV
slide-3
SLIDE 3

2

High voltage system

1-Generation of the nominal high voltage

Anode LEM Extraction grid CRP

300 kV Heinzinger power supply (PSU)

Insulation space Field cage Field shapers TPC LAr GAr

  • 300 kV
slide-4
SLIDE 4

2

High voltage system

1-Generation of the nominal high voltage

Anode LEM Extraction grid CRP

300 kV Heinzinger power supply (PSU)

Insulation space Field cage

High Voltage cable 2-Transmission of the nominal voltage from the power supply to the cathode

Field shapers TPC LAr GAr

  • 300 kV

Connection between the HVFT and the cathode High voltage feedthrough (HVFT)

slide-5
SLIDE 5

2

High voltage system

1-Generation of the nominal high voltage

Anode LEM Extraction grid CRP

300 kV Heinzinger power supply (PSU)

Insulation space Field cage

High Voltage cable 2-Transmission of the nominal voltage from the power supply to the cathode

Field shapers TPC LAr GAr

  • 300 kV

Connection between the HVFT and the cathode High voltage feedthrough (HVFT) The shape of the field cage and the cathode should be designed to avoid critical field regions (maximal electric field above 40 kV/cm) 3-ELECTROSTATIC SIMULATIONS

slide-6
SLIDE 6

3

Where we are?

February 10th, 2017: Joint Meeting with SP to discuss about PSUs for ProtoDUNE detectors

  • rganised by Eric James:

Assistants: Eric James, Flavio Cavanna, Dario Autiero, Sarah Lockwitz, Andrew Renshaw, Franco Sergiampietri, Flor De Maria Blaszczyk, Sebastien Murphy, Laura Molina Bueno. Summary: Because of the large cost, it may not be possible to order a third 300kV Heinzinger HV supply for use as a joint ProtoDUNE-SP/ProtoDUNE-DP spare. What was agreed on the meeting was:

PSU Cable diameter [mm] Detector Heinzinger 300kV 22 3x1x1/ProtoDUNESP New Heinzinger 300 kV 38 ProtoDUNEDP 200 kV PSU from UCLA 38? Spare for ProtoDUNE-SP 100 kV 14 3x1x1

High voltage power supply

A regular, on-order-of monthly meeting, will be organised in the context of the Joint Single-Phase/ Dual-Phase HV Working Group to continue these technical discussions moving forward. From SP Francesco Pietropaolo and Bo Yu will join also these meetings and, from DP Animesh, Cosimo, Jae and Yann too.

slide-7
SLIDE 7

4

Where we are?

High voltage power supply

Order of the new PSU already done by Franco with similar characteristics to the 3x1x1 300 kV PSU + the ETHERNET option.

slide-8
SLIDE 8

5

Where we are?

High voltage cable

  • The new HV cable is already in Franco’s lab.
  • What is missing is the male connector to the feedthrough, Øin=38mm
slide-9
SLIDE 9

6

Where we are?

  • Minor changes need to be done in the design respect to the one 300kV

feedthrough already installed in the 3x1x1, to accept the new HV cable

  • 3D drawings are work in progress.

Current 300kV feedthrough installed in the 3x1x1.

New cable diameter is 38 mm.

High voltage cable

slide-10
SLIDE 10

7

Where we are?

  • Preliminary design done by Franco.
  • Options to be decided: with or without degrader

High voltage transmission from the HVFT to the cathode

slide-11
SLIDE 11

513 67.5 700 LAr Level 1 degrader less Crossing Pipe will be few mm smaller 812

8 67.5 60 60 107 8 96.6 168.6 60 LAr level CRP HDPE G10 89 degraders

Where we are?

slide-12
SLIDE 12

9

Where we are?

Electric field locally higher than our guideline, electric field in LAr below 40 kV/cm

[kV/cm]

Work in progress!

Why the field is so high? Vdegrader = -33 kV Vinner = -300 kV

slide-13
SLIDE 13

10

Where we are?

[kV/cm]

With Degraders Without Degraders

Work in progress!

*scale adjusted to be able to compare both cases

slide-14
SLIDE 14

10

Where we are?

[kV/cm]

With Degraders Without Degraders

Work in progress!

*scale adjusted to be able to compare both cases

slide-15
SLIDE 15

10

Where we are?

[kV/cm]

With Degraders Without Degraders

Work in progress!

*scale adjusted to be able to compare both cases

no degraders degraders

slide-16
SLIDE 16

Where we are?

  • Improved design done by Franco to minimise the high electric field locally.

Main changes:

  • HDPE thicker
  • New degrader

shape

  • No G10 spacers

We need to verify mechanically the design Z [mm] R [mm]

slide-17
SLIDE 17

Where we are?

  • New degrader shape
slide-18
SLIDE 18

Where we are?

  • HDPE thicker
slide-19
SLIDE 19

Where we are?

New shape + HDPE thickness of 39 mm

slide-20
SLIDE 20

Y [mm] X [mm] Cut Line at different distances between the degrader and the field cage 5 mm far from the degrader surface 50 mm far from the degrader surface 100 mm far from the degrader surface

slide-21
SLIDE 21

What is missing?

  • Electrostatic simulations of the HVFT plus its connection to the

cathode have been performed.

  • Finish the quoted drawings for the HVFT and ask for an offer
  • Decide if we use a degrader or not for the connection between

the cathode and the HVFT.