status of hv power supply and hv feedthrough for the 6x6x6
play

Status of HV power supply and HV feedthrough for the 6x6x6 C. - PowerPoint PPT Presentation

Status of HV power supply and HV feedthrough for the 6x6x6 C. Cantini, P. Chiu, A. Gendotti, L. Molina Bueno, S.Murphy, A. Rubbia, C. Regenfus, F. Sergiampietri High voltage system Insulation space GAr Anode LEM CRP Extraction grid Field


  1. Status of HV power supply and HV feedthrough for the 6x6x6 C. Cantini, P. Chiu, A. Gendotti, L. Molina Bueno, S.Murphy, A. Rubbia, C. Regenfus, F. Sergiampietri

  2. High voltage system Insulation space GAr Anode LEM CRP Extraction grid Field cage TPC Field shapers power supply (PSU) 300 kV Heinzinger LAr -300 kV 2

  3. High voltage system Insulation space GAr Anode LEM CRP Extraction grid Field cage TPC Field shapers power supply (PSU) 300 kV Heinzinger LAr 1-Generation of -300 kV the nominal high voltage 2

  4. High voltage system 2-Transmission of the nominal voltage from the power supply Insulation space to the cathode GAr Anode LEM CRP High voltage Extraction feedthrough grid (HVFT) High Voltage cable Field Connection cage between the HVFT TPC Field shapers and the cathode power supply (PSU) 300 kV Heinzinger LAr 1-Generation of -300 kV the nominal high voltage 2

  5. High voltage system 2-Transmission of the nominal voltage from the power supply Insulation space to the cathode GAr Anode LEM CRP High voltage Extraction feedthrough grid (HVFT) High Voltage The shape of the field cage and the cable cathode should be designed to avoid critical field regions (maximal electric Field Connection field above 40 kV/cm) cage between the HVFT TPC Field shapers and the cathode power supply (PSU) 300 kV Heinzinger 3-ELECTROSTATIC SIMULATIONS LAr 1-Generation of -300 kV the nominal high voltage 2

  6. Where we are? High voltage power supply February 10th, 2017: Joint Meeting with SP to discuss about PSUs for ProtoDUNE detectors organised by Eric James: Assistants: Eric James, Flavio Cavanna, Dario Autiero, Sarah Lockwitz, Andrew Renshaw, Franco Sergiampietri, Flor De Maria Blaszczyk, Sebastien Murphy, Laura Molina Bueno. Summary: Because of the large cost, it may not be possible to order a third 300kV Heinzinger HV supply for use as a joint ProtoDUNE-SP/ProtoDUNE-DP spare. What was agreed on the meeting was: PSU Cable diameter [mm] Detector Heinzinger 300kV 22 3x1x1/ProtoDUNESP New Heinzinger 300 kV 38 ProtoDUNEDP 200 kV PSU from UCLA 38? Spare for ProtoDUNE-SP 100 kV 14 3x1x1 A regular, on-order-of monthly meeting, will be organised in the context of the Joint Single-Phase/ Dual-Phase HV Working Group to continue these technical discussions moving forward. From SP Francesco Pietropaolo and Bo Yu will join also these meetings and, from DP Animesh, Cosimo, Jae and Yann too. 3

  7. Where we are? High voltage power supply Order of the new PSU already done by Franco with similar characteristics to the 3x1x1 300 kV PSU + the ETHERNET option. 4

  8. Where we are? High voltage cable • The new HV cable is already in Franco’s lab. • What is missing is the male connector to the feedthrough, Ø in =38mm 5

  9. Where we are? High voltage cable • Minor changes need to be done in the design respect to the one 300kV feedthrough already installed in the 3x1x1, to accept the new HV cable • 3D drawings are work in progress. Current 300kV feedthrough installed in the 3x1x1. New cable diameter is 38 mm. 6

  10. Where we are? High voltage transmission from the HVFT to the cathode • Preliminary design done by Franco . • Options to be decided: with or without degrader 7

  11. Where we are? 168.6 Crossing Pipe will 700 be few mm smaller 96.6 107 8 60 67.5 60 812 CRP 513 LAr Level LAr level 67.5 HDPE G10 89 degraders 60 1 degrader less 8

  12. Where we are? [kV/cm] Work in progress! Why the field is so high? Vdegrader = -33 kV Vinner = -300 kV Electric field locally higher than our guideline, electric field in LAr below 40 kV/cm 9

  13. Where we are? With Degraders Without Degraders [kV/cm] Work in progress! * scale adjusted to be able to compare both cases 10

  14. Where we are? With Degraders Without Degraders [kV/cm] Work in progress! * scale adjusted to be able to compare both cases 10

  15. Where we are? With Degraders Without Degraders [kV/cm] no degraders Work in progress! degraders * scale adjusted to be able to compare both cases 10

  16. Where we are? • Improved design done by Franco to minimise the high electric field locally . Main changes: Z [mm] • HDPE thicker • New degrader shape • No G10 spacers We need to verify mechanically the design R [mm]

  17. Where we are? • New degrader shape

  18. Where we are? • HDPE thicker

  19. Where we are? New shape + HDPE thickness of 39 mm

  20. 5 mm far from the degrader surface Cut Line at different distances Y [mm] between the degrader and the field cage X [mm] 100 mm far from 50 mm far from the degrader the degrader surface surface

  21. What is missing? • Electrostatic simulations of the HVFT plus its connection to the cathode have been performed. • Finish the quoted drawings for the HVFT and ask for an offer • Decide if we use a degrader or not for the connection between the cathode and the HVFT.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend