Stan Marshall APEC Major Projects Conference May 30, 2018 Muskrat - - PowerPoint PPT Presentation

Stan Marshall APEC Major Projects Conference May 30, 2018 Muskrat Falls Projected In-service Capital Cost $12.7 $12.0 $2.6 $10.0 $3.7 $7.4 $8.0 ($ Billions) $1.2 $6.0 $0.9 $10.1 $2.6 $4.0 $0.7 $6.2 $5.5 $2.0 $2.9 $- Sanction


slide-1
SLIDE 1

APEC Major Projects Conference May 30, 2018

Stan Marshall

slide-2
SLIDE 2
slide-3
SLIDE 3

$2.9 $5.5 $0.7 $0.9 $2.6 $3.7 $1.2 $2.6 $- $2.0 $4.0 $6.0 $8.0 $10.0 $12.0 Sanction 2012 Jun-17 ($ Billions) MF LTA LIL Financing and Other

$7.4 $6.2 $12.7 $10.1

Muskrat Falls Projected In-service Capital Cost

slide-4
SLIDE 4

MUSKRAT FALLS

A year of significant accomplishments

slide-5
SLIDE 5

MUSKRAT FALLS GENERATION

  • Enclosed the powerhouse and

intake structures

  • Started the installation of the four

generating units in the powerhouse

  • Finished the South dam and

stabilization work on the North Spur

  • Achieved significant progress on

the North dam

slide-6
SLIDE 6
slide-7
SLIDE 7

MUSKRAT FALLS TRANSMISSION

  • Completed construction of the

Labrador-Island Transmission Link

  • Energized the AC transmission line

from Churchill Falls to Muskrat Falls

  • Energized the Soldiers Pond

AC switchyard

  • Maritime Link to Nova Scotia
  • perational to import power
slide-8
SLIDE 8

OVER 8,200 NEWFOUNDLANDERS & LABRADORIANS

slide-9
SLIDE 9

LOOKING AHEAD 2018

slide-10
SLIDE 10

THE SIX PHASES OF A MEGAPROJECT

  • 1. Wild Enthusiasm
  • 2. Disillusionment
  • 3. Confusion, Panic, Hysteria
  • 4. Search for the Guilty
  • 5. Punishment of the Innocent
  • 6. Reward the Uninvolved