APEC Major Projects Conference May 30, 2018
Stan Marshall APEC Major Projects Conference May 30, 2018 Muskrat - - PowerPoint PPT Presentation
Stan Marshall APEC Major Projects Conference May 30, 2018 Muskrat - - PowerPoint PPT Presentation
Stan Marshall APEC Major Projects Conference May 30, 2018 Muskrat Falls Projected In-service Capital Cost $12.7 $12.0 $2.6 $10.0 $3.7 $7.4 $8.0 ($ Billions) $1.2 $6.0 $0.9 $10.1 $2.6 $4.0 $0.7 $6.2 $5.5 $2.0 $2.9 $- Sanction
SLIDE 1
SLIDE 2
SLIDE 3
$2.9 $5.5 $0.7 $0.9 $2.6 $3.7 $1.2 $2.6 $- $2.0 $4.0 $6.0 $8.0 $10.0 $12.0 Sanction 2012 Jun-17 ($ Billions) MF LTA LIL Financing and Other
$7.4 $6.2 $12.7 $10.1
Muskrat Falls Projected In-service Capital Cost
SLIDE 4
MUSKRAT FALLS
A year of significant accomplishments
SLIDE 5
MUSKRAT FALLS GENERATION
- Enclosed the powerhouse and
intake structures
- Started the installation of the four
generating units in the powerhouse
- Finished the South dam and
stabilization work on the North Spur
- Achieved significant progress on
the North dam
SLIDE 6
SLIDE 7
MUSKRAT FALLS TRANSMISSION
- Completed construction of the
Labrador-Island Transmission Link
- Energized the AC transmission line
from Churchill Falls to Muskrat Falls
- Energized the Soldiers Pond
AC switchyard
- Maritime Link to Nova Scotia
- perational to import power
SLIDE 8
OVER 8,200 NEWFOUNDLANDERS & LABRADORIANS
SLIDE 9
LOOKING AHEAD 2018
SLIDE 10
THE SIX PHASES OF A MEGAPROJECT
- 1. Wild Enthusiasm
- 2. Disillusionment
- 3. Confusion, Panic, Hysteria
- 4. Search for the Guilty
- 5. Punishment of the Innocent
- 6. Reward the Uninvolved
SLIDE 11