Stakeholder Update Meeting February 10, 2020 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this


  1. Stakeholder Update Meeting February 10, 2020

  2. This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity other than FDOT staff is not official. Any questions can be sent to FDOT- D6PIO@dot.state.fl.us. This presentation may not be altered. 2

  3. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing concrete pavement saw cutting in preparation for concrete replacement. * This schedule does not reflect days added to the contract for holidays, weather days or special events TRAFFIC SHIFT: All travel lanes will be shifted to the right on southbound I-95 from SR 836 to NW 8 Street to allow the contractor to construct new bridge foundations (Tuesday, February 11) 3

  4. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD * This schedule does not reflect days added to the contract for holidays, weather days or special events ANTICIPATED NIGHTTIME LANE CLOSURES ON THE I-95 CORRIDOR: • Nighttime lane closures along I-95 between NW 8 Street and NW 29 Street • Continuous weekend lane closures for pavement work • Closure of I-95 entrance ramp at NW 8 Street • I-95 ramps to I-395 and SR 836 4

  5. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Traffic on the SR 836 Miami River Bridge 5shifted to the outside in * This schedule does not reflect days added to the contract for preparation for demolition holidays, weather days or special events activities in the median 5

  6. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing bridge widening on eastbound SR 836 from NW 17 Avenue to the Miami River 6

  7. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Pouring concrete for the new bridge deck on SR 836 7

  8. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing bridge widening on eastbound SR 836 from NW 12 Avenue to I-95 8

  9. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Supplemental parking for court facilities 9

  10. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES WEDNESDAY, FEBRUARY 12 THROUGH MONDAY, FEBRUARY 17 - NW 10 Avenue will be continuously closed from NW 13 Street to NW 14 Street starting at 10 a.m. on Wednesday, February 12 until 5:30 a.m. on Monday, February 17. The continuous closure will allow the contractor to safely drive concrete piles into the ground for new bridge foundations. 10

  11. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR: • Single and double lane closures along eastbound and westbound SR 836 • NW 17 Avenue under SR 836 • SR 836 ramps to northbound and southbound I-95 • Arterial roads under SR 836 • NW 17 Avenue and NW 12 Avenue ramps to SR 836 11

  12. UPCOMING & ONGOING 2 CONSTRUCTION ACTIVITIES 1. Removal of median separator between the eastbound I-395 mainline and the westbound mainline (Ongoing) 2. Construction of westbound outside, 3 local road lanes. Foundation work SR 836 UPCOMING CONSTRUCTION ACTIVITIES started at NE 2 Avenue and is moving 1 towards the west (Ongoing) 3. Begin demolition of portions of existing eastbound I-395 to allow for the construction of new bridge foundations (February) 12

  13. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES SR 836 UPCOMING CONSTRUCTION ACTIVITIES I-395 steel sheet pile driving for Signature Bridge center pier 13

  14. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES SR 836 UPCOMING CONSTRUCTION ACTIVITIES I-395 bridge demolition 14

  15. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Auger Cast Pile (ACP) Operations for Segmental Bridges started in late December 2019 * This schedule does not reflect days added to the contract for • ACP Completed: 160/1948 holidays, weather days or special events I-395 Segmental ACP – 857 o I-395 Signature ACP – 520 o o SR 836 Viaduct ACP - 571 15

  16. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events Shift traffic to the left on the westbound MacArthur Causeway approach to Biscayne Boulevard exit (February 17, 2020) 16

  17. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events Lane shift (to south side) on the westbound MacArthur Causeway ramp to Biscayne Boulevard to allow for clearing and grubbing activities. This will allow for construction of new retaining wall (February 17, 2020) 17

  18. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 2 1 * This schedule does not reflect days added to the contract for holidays, weather days or special events Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. 1 Shift lanes to the outside. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway) Close Bayshore loop ramp to EB MacArthur Causeway (March 2020) 2 18

  19. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR: • Lane closures along eastbound and westbound I-395 • Lane closures along Biscayne Boulevard and other arterial roadways adjacent to I-395 • I-395 to I-95 ramp closures 19

  20. COMMUNITY OUTREACH PROJECT WEBSITE • www.i-395miami.com • Sign-up for project alerts/updates Lane closure information Upcoming construction activities Presentations • Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY • 1035 NW 3 Avenue, Miami, Florida 33136 STAKEHOLDER MEETINGS • Ongoing individual stakeholder meetings and presentations • Next stakeholder meeting – March 16, 2020 20

  21. THANK YOU! www.i-395miami.com Contact: Oscar Gonzalez 786-280-0983 OGonzalez@mrgmiami.com 21

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.