Stakeholder Meeting April 22, 2020 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this


slide-1
SLIDE 1

Stakeholder Meeting April 22, 2020

slide-2
SLIDE 2

2

This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity

  • ther than FDOT staff is not official. Any questions can be sent to FDOT-

D6PIO@dot.state.fl.us. This presentation may not be altered.

slide-3
SLIDE 3

* This schedule does not reflect days added to the contract for holidays, weather days or special events

3

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

  • Concrete pavement replacement

began on Wednesday, April 15 on southbound I-95 from NW 29 Street to south of NW 20 Street

  • Continuous (24/7) triple lane

closures are being implemented to expedite work

  • Northbound I-95 continuous

closures being considered for bridge reconstruction work at the interchange core

slide-4
SLIDE 4

* This schedule does not reflect days added to the contract for holidays, weather days or special events

4

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR:

  • Nighttime lane/ramp closure along I-95 between NW 8 Street and NW 29

Street

  • Closure hours have been adjusted based on current traffic conditions from 8

p.m. until 8 a.m.

  • Continuous lane closures (24/7) for extended periods of up to three to four

weeks for both northbound and southbound I-95

slide-5
SLIDE 5

5

  • Shifted traffic on eastbound SR 836

from NW 17 Avenue to the Miami River to the right side of the roadway

  • Shifted traffic on westbound SR 836

from the Miami River to east of NW 17 Avenue to the left side of the roadway

  • Demolition of SR 836 bridge sections
  • ver NW 12 and NW 17 Streets

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-6
SLIDE 6

6

Daytime NW 17 Avenue southbound traffic diversion for bridge demolition activities

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-7
SLIDE 7

7

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

Continuous closure of the northbound NW 12 Avenue ramp to eastbound SR 836 Replacement of the concrete pavement on eastbound SR 836 from NW 12 Street to I-95 with asphalt Continuous closure of one to two lanes from NW 12 Avenue to I-95. Two lanes will remain

  • pen during peak travel

periods. Anticipated duration: Four weeks

slide-8
SLIDE 8

8

  • Demolition of median section
  • f SR 836 to begin in May
  • Work will begin to the east
  • ver court parking area and

move to the west

  • Demolition work will take place

at night between expanded closure hours from 8 p.m. until 8 a.m.

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-9
SLIDE 9

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

9

ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR:

  • Single and double lane/ramp closures along eastbound and westbound SR 836
  • NW 17 Avenue under SR 836
  • Arterial roads under SR 836
  • Closure hours have been adjusted based on current traffic conditions from 8

p.m. until 8 a.m.

  • Continuous lane closures (24/7) are being implemented along SR 836

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-10
SLIDE 10

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

10

  • Construction the center signature

bridge foundations

  • Construction of westbound outside,

local road bridge foundations

  • Demolition of portions of existing

eastbound I-395 to allow for the construction of new bridge foundations

  • Driving of steel sheeting for

foundation coffer dams

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-11
SLIDE 11

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

11

The westbound I-395 ramp to northbound I-95 has been reduced from two lanes to

  • ne lane.

The reduction in lanes is necessary to reconstruct the section of I-95 where the eastbound SR 836 ramp and westbound I-395 ramp join I-95. The lane reduction is expected to be in place for approximately 18 months.

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-12
SLIDE 12

* This schedule does not reflect days added to the contract for holidays, weather days or special events

12

Ongoing Auger Cast Pile (ACP) Operations for Segmental Bridges and Signature Bridge

  • ACP Completed: 283/1948
  • I-395 Segmental ACP – 233/857
  • I-395 Signature ACP – 50/520
  • SR 836 Viaduct ACP - 571

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-13
SLIDE 13

* This schedule does not reflect days added to the contract for holidays, weather days or special events

13

Ongoing segmental bridge column construction

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-14
SLIDE 14

* This schedule does not reflect days added to the contract for holidays, weather days or special events

14

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

  • Westbound MacArthur Causeway

Ramp to Biscayne Boulevard has been shifted to the left to allow for the construction of a new retaining wall on the right side. Only one travel lane is available on the ramp from the MacArthur Causeway to North Bayshore Drive

slide-15
SLIDE 15

* This schedule does not reflect days added to the contract for holidays, weather days or special events

15

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway). Close Bayshore loop ramp to EB MacArthur Causeway (June 2020)

1 1 2 2

slide-16
SLIDE 16

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

16

ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:

  • Lane closures along eastbound and westbound I-395
  • Lane closures along Biscayne Boulevard and other arterial roadways adjacent

to I-395

  • I-395 to I-95 ramp closures
  • Closure hours have been adjusted based on current traffic conditions from 8

p.m. until 8 a.m.

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-17
SLIDE 17

17

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT THIS

TIME) STAKEHOLDER MEETINGS

  • Stakeholder meetings will be held “virtually” until further notice
slide-18
SLIDE 18

786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez

www.i-395miami.com

THANK YOU!