Stakeholder Event 6 8pm Tuesday 6 July 2016 Welcome & - - PowerPoint PPT Presentation

stakeholder event
SMART_READER_LITE
LIVE PREVIEW

Stakeholder Event 6 8pm Tuesday 6 July 2016 Welcome & - - PowerPoint PPT Presentation

Stakeholder Event 6 8pm Tuesday 6 July 2016 Welcome & Introductions Cllr. Blake Pain Lead Member for Broadband 1) BTs Fibre Rollout 2) Contract 1 Update 3) Contract 2 Deployment Plans 4) Better Broadband Scheme 5) Additional


slide-1
SLIDE 1

Stakeholder Event

6 – 8pm Tuesday 6 July 2016

slide-2
SLIDE 2

Welcome & Introductions

  • Cllr. Blake Pain

Lead Member for Broadband

slide-3
SLIDE 3

1) BT’s Fibre Rollout 2) Contract 1 Update 3) Contract 2 Deployment Plans 4) Better Broadband Scheme 5) Additional Funding 6) New Technology 7) Q&A session

slide-4
SLIDE 4

BT’s UK fibre broadband roll-out

No other company in the world is investing as much in fibre without public sector support or a regulatory regime that allows for far greater returns

  • £3bn to bring fibre to around two-thirds of UK
  • Today, more than 24 million homes and

businesses passed

  • Around 8000 engineers working on the “Big

Build”

  • A mixture of fibre to the cabinet (FTTC) and fibre

to the premises technology (FTTP)

  • Fibre to the remote Node (FTTrN) – successfully

trialled and now being deployed

  • FTTP “on demand” now available in some areas
  • More than 140 service providers currently trialling
  • r selling fibre services using BT’s network
  • Extending fibre broadband availability even

further through local community projects ‘ Community Fibre Partnership’

slide-5
SLIDE 5

The Superfast Leicestershire Journey

More than 292,000 homes and business connected

  • £18.9m contract
  • 62,000 perms
  • £1.1m from

districts contributing to around 5,000 THP £9.1m contribution form BT

  • £9.1m County

Contract

  • 11,000 prems
  • £2.26m of this

is contribution form BT

  • New Leicester

City phase

  • £2.2m from

LLEP LGF

  • £2.8m

contribution from BT

  • 9,000 City

prems The Final 4% Further Funding BT Commercial Contract 1 By March 15 Contract 2 By December 17 Going Further 96% SFBB

slide-6
SLIDE 6

How we do it…

A full assessment

  • f the existing

network to provide accurate information for our engineers. Agree and plan when the new equipment will be placed inside the

  • exchange. Every

exchange is different. Surveying underground ducts and planning where the new fibre, street cabinets and over ground equipment will go. We are meeting with the Highways and Planning teams. Building the new network from the exchange to the new street cabinets.

Pre-planning Preparing the exchange Planning the network Installation

slide-7
SLIDE 7

Contract 1 Update

Over 200 miles of new fibre currently rolled out 71 exchange areas now live 307 fibre cabinets enabled 65,000 additional Leicestershire homes and businesses are now able to connect to fibre broadband 235 towns and villages have gained access to fibre broadband thanks to Superfast Leicestershire. This increases superfast coverage from 81% to 92%, and we remain

  • n target to reach 96% by the end
  • f 2017
  • 2011 Government announce

Leicestershire’s allocation from £530m of national funding

  • County Council puts forward and

secures additional funding from EU (ERDF) District, Borough and City Councils

  • Following extensive procurement

exercise, contract awarded to BT (August 2013)

  • First cabinet went live in July

2014

slide-8
SLIDE 8

We bring choice and low prices

  • Our open network brings competition, choice & low prices
slide-9
SLIDE 9

Contract 2 Plans

  • Contract signed March 2015
  • Originally County build area only. Now includes a £5m

City area build phase (LLEP and BT funded)

  • Now over £33m invested including £4m from LCC and

£8m from government (BDUK)

  • Mainly FTTC, but will also involve FFTP in rural areas

were more cost effective than FTTC

  • Will increase coverage from 92% to over 96%
  • First cabinet went live in April 2016. First areas to benefit include: Coalville, Desford,

Redmile, Castle Donnington, Hugglescote, Wigston, Barwell, Glenfield, Hathern, Loughborough, Ellistown, Kegworth, Medbourne, Melton Mowbray, Thringstone, Bilstone, Atherstone, Barton on the Wolds and Stoney Stanton

slide-10
SLIDE 10

Contract 2 Progress

  • Around 100 surveys have been

completed to date

  • 35 cabinets are already live and

receiving

  • rders,

serving

  • ver

2,000 premises

  • Survey work completed on the first

60 miles of new fibre cabling

  • Over

400 structures planned, most of which are green roadside fibre

  • cabinets. However, some

will be new technologies not previous used, such as Fibre to the Premise and Fibre to the Remote Node.

  • Average of more than 6 new

cabinets a month in Contract 2 so far, which is set to increase over the coming months Legend Contract 1 Cabinets Contract 2 Cabinets

slide-11
SLIDE 11

Better Broadband Scheme (1)

Network Operations Centre

Modem

Internet backbone

Satellite dish VOIP Devices Download Speeds 10-24 Mbps The Satellite connection is provided by two

  • perators, Avanti and
  • Eutelsat. They provide

wholesale access to 11 RSPs on the scheme, each offering different product ranges: e.g. download speed limits and usage caps at different prices Upload Speeds 2-6 Mbps RSPs provide equipment Internet

slide-12
SLIDE 12

Better Broadband Scheme (2)

Fibre Cable Backhaul Wireless signal

  • Available from June 2016 locally
  • Download speeds: 20-100Mbps
  • Typical product offers: 10-30Mbps
  • Five providers:
  • Maximum contract length is 24 months
  • Maximum yearly cost is £400
  • Around 3,000 properties eligible
  • Scheme open until end of January 2018
  • Services available until end of December 2022
  • Summer 2016 scheme relaunch
slide-13
SLIDE 13

Public Consultation  Identify areas  Identify priorities: 1) Community completion 2) Rural areas  Instruct BT  BT model new phase of build Contract 1 delivered

  • n time and under

budget  Significant underspend amount will become available  Council committed to reinvesting  Will seek to invest £2m - £3m late 2016 / early 2017 New commercial deployments  Seek additional funding support from District and Borough Councils  Investigate all future funding

  • pportunities

 Advise community groups seeking their

  • wn solution

Gainshare funding (Take-up over 30%) Potential further funding Other providers

The Final 4%

slide-14
SLIDE 14

Other Commercial Providers

  • Fixed fibre for business parks (FTTC)
  • Primarily in City area with expansion

plans for Great Central Ind. Estate, Northgate Ind. Estate and Frog Island Ind. Estate, amongst others

  • New coverage or additional choice for customers
  • Project Lightening -

£3bn investment

  • Demand led – Cable

my Street

  • Ratby and Broughton

Astley

  • New wireless provider

(January 2016)

  • Covering significant

areas of east Harborough

  • Offer 30Mbps download
  • Significant coverage and plans

in Welland Valley area

  • FTTP on demand

led basis

  • Wireless provider
  • Covering Buckminster

estate and surrounding area

slide-15
SLIDE 15

New Technology

Consumers

FTTP G.fast

  • >11m homes passed by 2020 through mix of G.fast and FTTP
  • Continue G.fast trials
  • Pilot G.fast at 25,000 homes in 16/17, with proposed future

specification in Cherry Hinton, Cambridgeshire and Gillingham, Kent

  • Ready for commercial deployment in 17/18 (subject to regulatory

certainty)

More FTTP

  • Ambition to increase mix of FTTP in ultrafast roll out
  • Continue trials to improve cost to deploy and customer

experience

  • FTTP for new build homes, rural areas, apartment blocks,

businesses and where it makes sense

FTTP

For business

  • Up to 1m to have ultrafast available by 2020 including

Business FTTP in high streets and business parks

slide-16
SLIDE 16

Our network is open and future proof…

slide-17
SLIDE 17

Questions?

Contact Details: Email: broadband@leics.gov.uk Twitter: @LeicsCountyHall Website: www.superfastleicestershire.org.uk