SRPE AASHTO Specifications
July 19 2013 July 19, 2013
www.concrete-pipe.org
SRPE AASHTO Specifications July 19 2013 July 19, 2013 - - PDF document
SRPE AASHTO Specifications July 19 2013 July 19, 2013 www.concrete-pipe.org Steel Ribbed HDPE 2 = SRHDPE S = SRPE Now has AASHTO Design and Construction Now has AASHTO Design and Construction Specifications for SRPE. But wait there
www.concrete-pipe.org
2
Now has AASHTO Design and Construction Now has AASHTO Design and Construction Specifications for SRPE…. But wait there is more… AASHTO Bridge Design Specs - Section 12
www.concrete-pipe.org
g
3
4
5
6
www.concrete-pipe.org
7
www.concrete-pipe.org
8
www.concrete-pipe.org www.concrete-pipe.org
9
f Compressive Stresses - Yes Bending Stresses - No
www.concrete-pipe.org www.concrete-pipe.org
10
www.concrete-pipe.org www.concrete-pipe.org
11
www.concrete-pipe.org www.concrete-pipe.org
12
www.concrete-pipe.org www.concrete-pipe.org
13
12.7.2.1 – Section Properties Dimensions and properties of pipe cross- sections; minimum seam strength; mechanical and chemical requirements for aluminum corrugated and steel corrugated pipe and pipe- arch sections; and aluminum and steel corrugated structural plate pipe, pipe-arch, and arch sections, may be taken as given in Appendix
sections, and material properties for steel- reinforced thermoplastic culverts shall be provided by the pipe manufacturer.
(emphasis added)
www.concrete-pipe.org
14
C12.7.2.1 - commentary Steel-reinforced thermoplastic culverts are pipe sections in which the main load-carrying members are steel ribs encapsulated by thermoplastic material that may brace the ribs from distortion and buckling. This composite system should be evaluated independently for each manufacturer’s pipe system. Designers should obtain the required mechanical properties directly from the pipe manufacturer to determine fill heights. g
(emphasis added)
www.concrete-pipe.org
15
www.concrete-pipe.org
16
C12.7.2.7 - commentary While the steel ribs are the main load carrying member of the culvert, the thermoplastic profile braces the steel ribs from distortion or buckling under load is critical to the pipe
distribute the load between ribs. A structural evaluation of the profile alone is not required. However, an evaluation of the composite system
is important to assure that the tensile strains within the profile do not exceed the long-term strain capacity for the thermoplastic material used in the construction of the pipe. p p
(emphasis added)
www.concrete-pipe.org
17
26.1.1 Description This work shall consist of furnishing, g fabricating, installing, and inspecting metal pipe, structural plate metal pipe, arches pipe arches box structures and arches, pipe arches, box structures, and deep corrugated structures, and steel- reinforced thermoplastic pipe in conformance with these Specifications and the details shown in the contract documents documents.
www.concrete-pipe.org
18
Backfill for metal and steel-reinforced Backfill for metal and steel reinforced thermoplastic culverts shall be granular material, as specified in the contract d t d ifi ti d h ll documents and specifications, and shall be free of organic material, rock fragments larger than 3.0 in. (1.5 in. for fragments larger than 3.0 in. (1.5 in. for steel reinforced thermoplastic pipe) in the greatest dimension, and frozen lumps, d h ll h i t t t ithi and shall have a moisture content within the limits required for compaction.
www.concrete-pipe.org
19
26.3.9—Steel-Reinforced Thermoplastic Culverts Steel-reinforced thermoplastic culverts shall conform to the requirements of AASHTO MP 20.
(emphasis added)
AASHTO MP 20-11 has been approved for 12”-60”
www.concrete-pipe.org
20
26.4.2.5—Steel Reinforced Thermoplastic Culvert Joints Joints for steel reinforced thermoplastic pipe shall comply with the details shown in the contract drawings and on the approved working drawings. Each joint shall be sealed to prevent infiltration of soil (soiltight), fines (silttight), or water (watertight) as required by the contract documents. Field tests may be required by the Engineer whenever there is a question regarding compliance with the contract requirements. Joints shall be installed so that the connection of pipe sections will form a continuous surface free from irregularities in the flow line from irregularities in the flow line.
(emphasis added)
www.concrete-pipe.org
21
C26 4 2 5 t
C26.4.2.5 - commentary Joint types include bands, bell-and-spigot pipe ends, double-bell couplings, and fusion welded
Other joint types may be used provided that documentation is provided to demonstrate that p the joint meets the project requirements. Joints are often provided as soiltight or watertight Definitions of soiltight and silttight
are vague. Examples can be found elsewhere in this Section. Watertight joints are normally specified to meet ASTM D3212 Pressure specified to meet ASTM D3212. Pressure capability of joint shall be based on project
capabilities are 2 5 and 10 psi capabilities are 2, 5, and 10 psi.
(emphasis added)
www.concrete-pipe.org
22
www.concrete-pipe.org
23
www.concrete-pipe.org
24
www.concrete-pipe.org
25
www.concrete-pipe.org
26
www.concrete-pipe.org
27
AASHTO Section 26 Metal
www.concrete-pipe.org
28
www.concrete-pipe.org
29
www.concrete-pipe.org
30
AASHTO Section 26 Metal
www.concrete-pipe.org
31
www.concrete-pipe.org
32
www.concrete-pipe.org
33
Pi O t id ASTM AASHTO AASHTO Pipe Diameter Outside Diameter ASTM 2321 AASHTO
AASHTO
30 30.9 50.6 58.4 NA* 36 37 1 58 4 67 7 NA* 36 37.1 58.4 67.7 NA* 42 43.2 66.0 76.8 NA* 48 49.5 73.9 86.3 NA* 54 55.5 81.4 95.3 NA* 60 61.4 88.8 104.1 NA* 66 67 8 96 8 113 7 NA* 66 67.8 96.8 113.7 NA 72 73.7 104.1 122.6 NA* 84 85.9 119.4 140.9 NA* 96 97.8 134.3 158.7 NA*
*For trench conditions, the trench shall be excavated to the width, depth, and grade shown in the contract documents
www.concrete-pipe.org
and grade shown in the contract documents.
34
26.5.7.1 – Visual Inspection
p Final internal inspections shall be conducted on all buried installations to evaluate issues that may affect long-term performance Final inspections affect long term performance. Final inspections shall be conducted no sooner than 30 days after completion of installation and final fill.
(emphasis added) (emphasis added)
www.concrete-pipe.org
35
26.5.7.1 - Visual Inspection
p Steel reinforced thermoplastic pipe shall be inspected prior to backfilling to ensure that the external reinforcing ribs do not lean an external reinforcing ribs do not lean an average of more than 15 degrees off of vertical within any 24.0 in. long continuous section of the pipe If this condition exists that section of the pipe. If this condition exists, that portion of the pipe shall be remediated or
spigot pipe ends double-bell couplings and spigot pipe ends, double bell couplings, and fusion welded joints.
(emphasis added)
www.concrete-pipe.org
36
26.5.7.2.2 – Installation Deflection for Steel-
Reinforced Thermoplastic Culverts The pipe shall be evaluated to determine whether the internal diameter of the barrel has been the internal diameter of the barrel has been reduced more than five percent when measured not less than 30 days following completion of installation installation.
www.concrete-pipe.org
37
26.5.7.2.2 – Installation Deflection for Steel-
Reinforced Thermoplastic Culverts Pipes shall be checked for deflection using a mandrel or any other device approved by the mandrel or any other device approved by the Engineer that can physically verify the dimensions of the pipe and that is not limited by poor lighting waterflow pipe length or other poor lighting, waterflow, pipe length, or other limiting conditions of the installed environment. Pipes larger than 24.0 in. may be entered and deflection levels measured directly deflection levels measured directly.
www.concrete-pipe.org
38
26.5.7.2.2 – Installation Deflection for Steel-
Reinforced Thermoplastic Culverts In all pipe installations, at least ten percent of the total pipe footage on the project shall be the total pipe footage on the project shall be randomly selected by the Engineer and inspected for deflection. Also, as determined by the 100 percent visual inspection in Article the 100 percent visual inspection in Article 26.5.7.1, all areas in which deflection can be visually detected shall be inspected for deflection deflection.
www.concrete-pipe.org
39
26.5.7.2.2 – Installation Deflection for Steel- Reinforced Thermoplastic Culverts
Where direct measurements are made, a measurement shall be taken once every 10.0 ft for the length of the pipe and a minimum of four measurements per pipe installation are required installation are required. If a mandrel is used for the deflection test, it shall be a nine- (or greater odd number) arm mandrel and shall be sized and inspected by the Engineer prior to testing. A sized and inspected by the Engineer prior to testing. A properly sized proving ring shall be used to check or test the mandrel for accuracy. The mandrel shall be pulled through the pipe by hand with a rope or cable. Where applicable p lle s ma be incorporated in the s stem to applicable, pulleys may be incorporated in the system to change the direction of pull so that inspection personnel need not physically enter the pipe or manhole.
www.concrete-pipe.org
40
26.5.7.2.2 – Installation Deflection for Steel- Reinforced Thermoplastic Culverts
For locations where pipe deflection exceeds five percent of the inside diameter, an evaluation shall be conducted by the Contractor utilizing a Professional Engineer and submitted to the Engineer for review and approval, taking into consideration the severity of the deflection, structural integrity, environmental conditions, and the design service life of the pipe. Pipe remediation
where the evaluation finds that the deflection could be problematic. For locations where pipe deflection exceeds 7.5 percent of the inside p diameter, remediation or replacement of the pipe is required.
www.concrete-pipe.org
41
www.concrete-pipe.org
42
www.concrete-pipe.org
43
0 014
www.concrete-pipe.org
44
45
www.concrete-pipe.org
46
S f S f
www.concrete-pipe.org www.concrete-pipe.org
SRPE Manufacture Specification 1-9-2012
47
Nominal Pipe Size
Min Waterway Wall Thickness
Min Waterway Wall Thickness ASTM F2562
i h i h i h inch inch inch 30 .082 .059 36 .082 .067 42 .082 .071 48 .130 .071 54 .130 .079 54 .130 .079 60 .130 .079 66 .220 .087 72 220 087 72 .220 .087 84 .220 NA 96 .220 .118 120 .220 .118
www.concrete-pipe.org
48
www.concrete-pipe.org
49
www.concrete-pipe.org
50
Manufactured “with a pressure rated resin
Manufactured with a pressure rated resin with predictable performance properties the engineer can depend on”
crack growth (pipe cracking and delamination) C ti l HDPE h d
buckling issues
buckle
www.concrete-pipe.org
p
51
www.concrete-pipe.org
52
www.concrete-pipe.org
53
www.concrete-pipe.org