SPS Beam Dump Facility Project Design Challenges
- M. Calviani (CERN)
- n behalf of the BDF Project team
SPS Beam Dump Facility Project Design Challenges M. Calviani (CERN) - - PowerPoint PPT Presentation
SPS Beam Dump Facility Project Design Challenges M. Calviani (CERN) on behalf of the BDF Project team Outlook BDF as a high intensity slow extracted beam in the CERNs NA Beam operational scenarios and compatibility with existing FT
18-22/09/2017
2
18-22/09/2017
3
4
Rav = 1.1 km
LSS2: slow-extraction LSS3: RF LSS6: fast extraction LSS4: fast extraction LSS5 TI2: LHC Beam 1 TI8: LHC Beam 2
AD LEIR 2 ELENA ISOLDE
LSS1: injection, internal beam dump AWAKE (formerly CNGS)
LINAC3
LHC
BEAM DIRECTION
HiRadMat
LINAC4 nTOF
[1] J.B. Adams, The CERN 400 GeV Proton Synchrotron, 1977
North Area (NA): max 450 GeV
18-22/09/2017
Beam Dump Facility
18-22/09/2017
5
18-22/09/2017
6
Beam losses (and activation)
18-22/09/2017
7
8
2015 in a period without LHC filling
main magnet current Fixed Target Fixed Target test beam test beam beam intensity
18-22/09/2017
18-22/09/2017
9
CERN-SHiP-NOTE-2015-004
18-22/09/2017
10
CERN-SHiP-NOTE-2015-004
Higher proton rate for TCC2 primary targets experiment SHiP goal
Shorter flat-top for TCC2 fixed target cycle implies § Higher average proton flux and higher activation in the splitter region § Increasing total POT for SHiP and TCC2 experiments, increasing radiation in SPS
18-22/09/2017
11
18-22/09/2017
12
18-22/09/2017
13
BDF setup
18-22/09/2017
14
18-22/09/2017
15
Beam direction He-vessel wall Target hall surface
Target
18-22/09/2017
16
WATER AND GROUND ACTIVATION RADIOACTIVE WASTE AIR AND HELIUM ACTIVATION PROMPT AND RESIDUAL RADIATION RADIATION PROTECTION
18-22/09/2017
17
18-22/09/2017
18
Proximity shielding cast iron
25 kW, water cooled
Target (320 kW)
Beam delivery
Magnetisation coil
US1010 hadron absorber shielding (1.8 T zone)
4.5 m 3.2 m 7.9 m 11.2 m 11.2 m 7.9 m 6.4 m
18-22/09/2017
19
1.4 T
18-22/09/2017
20
Helium Vessel Beam Line Cooldown Area Services Area
18-22/09/2017
21
Mobile Shielding Above Coil Shielding US1010 Shielding Collimator Proximity Shielding Target 8 m 12 m
8 m
Target + water cooled shielding and collimators installed on pillars, w/ space routing for services
18-22/09/2017
22
Mobile Shielding Proximity Shield Block Vessel Lid Crane Target
18-22/09/2017
23
18-22/09/2017
24
Target water Target helium Proximity shielding water
18-22/09/2017
25
Helium Vessel Hot Cell Trolley Beam Line Smaller cool-down area and services room included for non-target operations.
18-22/09/2017
26
In beam position Out beam position
Collimator (and surrounding shielding) US1010 Shielding Above Coil Shielding Mobile Shielding Concrete Shielding Proximity Shielding (water-cooled) Remaining space inside the helium vessel is filled with Cast Iron shielding blocks Magnetic Coil
18-22/09/2017
27
§ Less connection inside the vessel
18-22/09/2017
28
Target In-Vessel Cast Iron shielding Concrete shielding Helium Vessel Door (EPDM seals) ‘Dead Zone’ to line up with Hot Cell when trolley is forward Services Area
Wheels continue along Dead Zone and Services area –
18-22/09/2017
29
18-22/09/2017
30
In-Cell crane
(TBC) 2x twin MSM workstations Containment between services and Hot Cell (TBC) Man- Accessible area (TBC)
18-22/09/2017
31
Factor Crane Trolley Component installation Simple crane positioning Complicated by requirement to seal the vessel Service Connections Complex passive sealing design Simpler connection with MSMs Risk Ability to make/break leak-proof seals remotely Concept - Feasibility of the cantilever Operational - Reliability of the wheels. Radiation Protection All operations involve exposure of activated elements within cooldown area More contained operations on target – performed in hot cell (except for target disposal) Operation Duration Any operations require the removal of shielding blocks Target can be removed directly using the trolley RH Operations Only simple operations effected through crane deployed tooling and spreaders More complex operations via MSMs
18-22/09/2017
32
18-22/09/2017
33
18-22/09/2017
34
18-22/09/2017
35
18-22/09/2017
36