Split Rock to Lakefield Junction 345 kV Transmission Line SD PUC - - PowerPoint PPT Presentation

split rock to lakefield junction 345 kv transmission line
SMART_READER_LITE
LIVE PREVIEW

Split Rock to Lakefield Junction 345 kV Transmission Line SD PUC - - PowerPoint PPT Presentation

Split Rock to Lakefield Junction 345 kV Transmission Line SD PUC Docket No. EL05-023 Split Rock to Lakefield Junction 345 kV Project Brandon, SD to Lakefield, MN 86 Mile 345 kV line 9.6 Miles in SD Expansion of Split Rock


slide-1
SLIDE 1

Split Rock to Lakefield Junction 345 kV Transmission Line

SD PUC Docket No. EL05-023

slide-2
SLIDE 2

Split Rock to Lakefield Junction 345 kV Project

  • Brandon, SD to Lakefield, MN

– 86 Mile 345 kV line – 9.6 Miles in SD

  • Expansion of Split Rock substation (Brandon)
slide-3
SLIDE 3
slide-4
SLIDE 4

Exhibit C.1a – Project Route Segments Split Rock to Lakefield Junction 345KV Line Xcel Energy Minnehaha County, South Dakota

slide-5
SLIDE 5

Exhibit C.1b – Project Route Segments Split Rock to Lakefield Junction 345KV Line Xcel Energy Minnehaha County, South Dakota

South Dakota Minnesota

slide-6
SLIDE 6

Project Need

  • Development of wind energy in SW

Minnesota and in South Dakota.

– Increases firm outlet capacity to 825 MW

  • Present transmission system cannot support

existing wind generation

  • Enhances transmission system reliability and

capacity for Sioux Falls.

slide-7
SLIDE 7

Project Status

  • Permits Acquired

– MN Certificate of Need – MN Route Permit – MN DOT Permit – SD DOT Permit – Corps of Engineers Permit – Construction Stormwater Permit

  • ROW acquisition

– 28 of 34 easements acquired

slide-8
SLIDE 8

Existing Line Proposed Line

slide-9
SLIDE 9

Proposed Split Rock Substation Modifications

slide-10
SLIDE 10

Schedule

  • SD line construction will begin once the

Facilities Permit is approved and all easements are acquired.

  • Project construction expected to be complete

by Fall 2008.

slide-11
SLIDE 11

Siting & Construction Issues

  • Placement of 345 kV line adjacent to I-90 fence to

minimize impacts

  • Schedule construction work to avoid impacts to Bald

Eagle nest

  • Best Management Practices during construction

– Erosion control measures – Winter construction

  • Landowners compensated for damages caused by

construction

slide-12
SLIDE 12

Stipulation Agreement

  • Xcel Energy and the Commission Staff have entered

into a settlement agreement.

slide-13
SLIDE 13

Xcel Energy respectfully requests approval of the Facilities Permit requested in EL05-023.