I-345 Public Meeting December 2, 3 and 5, 2019
Interstate 345 (I-345) Feasibility Study
From I-30 to Woodall Rodgers Freeway
Public Meeting CSJ: 0092-14-094
December 2, 3 and 5, 2019
Interstate 345 (I-345) Feasibility Study From I-30 to Woodall - - PowerPoint PPT Presentation
Interstate 345 (I-345) Feasibility Study From I-30 to Woodall Rodgers Freeway Public Meeting CSJ: 0092-14-094 December 2, 3 and 5, 2019 I-345 Public Meeting December 2, 3 and 5, 2019 Table of contents 6 1 Introduction Study and Project
I-345 Public Meeting December 2, 3 and 5, 2019
Public Meeting CSJ: 0092-14-094
December 2, 3 and 5, 2019
I-345 Public Meeting December 2, 3 and 5, 2019
Table of contents
Introduction Project Overview Dallas CityMAP Project Development Process Feasibility Study Study and Project Goals and Objectives Public/Agency Outreach and Involvement 1
2
2 3 4 5 6 7 Next Steps 8 Contact Information 9 Thank You 10 10
I-345 Public Meeting December 2, 3 and 5, 2019
Project Overview
3
infrastructure
next 25 years
feasibility study to plan for the future of the roadway
stakeholders, traffic data and current and future development plans to develop and assess conceptual alternatives
I-345 Public Meeting December 2, 3 and 5, 2019
Project Overview - Feasibility Study Location Map
4
From I-30 to Woodall Rodgers Freeway (Spur 366)
I-345 Public Meeting December 2, 3 and 5, 2019
Project Overview - Project Approach
5
I-345 Public Meeting December 2, 3 and 5, 2019
Project Overview - Significant Adjacent Projects
6
The East Corridor Project (Under Study) Mill Creek Tunnel Project (City of Dallas Project Under Construction) SM Wright Project Phase I (Under Construction) I-345 Feasibility Study (Under Study) The Horseshoe Project (Completed) The Canyon (Under Study) Lowest Stemmons Project (Under Construction) SM Wright Project Phase II (Final Design) DART D2 Project (Under Study)
I-345 Public Meeting December 2, 3 and 5, 2019
Project Overview - Project History
connection from I-45 to US 75
begin in 1956
street grid
design, at the time
7
Interstate 345 under construction in 1969 Source: The Dallas Library
I-345 Public Meeting December 2, 3 and 5, 2019
Project Overview - Project History
intended to:
the bridge
maintenance and preservation activities
held November and December 2012
extend service life
8
Source: AIA
I-345 Public Meeting December 2, 3 and 5, 2019
Dallas CityMAP
9
system surrounding Downtown Dallas
interstates
developed through the current study will also be considered
I-345 Public Meeting December 2, 3 and 5, 2019
Dallas CityMAP Scenarios - No Build
10
I-345 Public Meeting December 2, 3 and 5, 2019
Dallas CityMAP Scenarios - Below Grade Freeway
11
I-345 Public Meeting December 2, 3 and 5, 2019
Dallas CityMAP Scenarios - Removal
12
I-345 Public Meeting December 2, 3 and 5, 2019
Dallas CityMAP Scenarios– Reconstruct and Elevate with Ramp Modifications
13
I-345 Public Meeting December 2, 3 and 5, 2019
Other Feasible Alternatives
14
I-345 Public Meeting December 2, 3 and 5, 2019
Project Development Process
15
Identify Need Feasibility Study Preliminary Design and Schematic Environmental Study and Documentation
Final Design Right of Way Acquisition Construction
I-345 Public Meeting December 2, 3 and 5, 2019
Feasibility Study
16
I-345 Public Meeting December 2, 3 and 5, 2019
Study and Project Goals and Objectives
17
Have an inclusive, transparent and collaborative public involvement process Work collaboratively with stakeholders Review recommendations from previous studies Provide the best solution that maintains safety, mobility and
Incorporate TxDOT and community goals Work toward technically preferred alternatives
I-345 Public Meeting December 2, 3 and 5, 2019
Public/Agency Outreach & Involvement
18
Surveys
public meeting series
alternative concepts
Meetings with Key Stakeholders and the Public
Other Outreach
I-345 Public Meeting December 2, 3 and 5, 2019
Next Steps
– Present preliminary traffic analysis – Present conceptual alternatives based on stakeholder feedback, traffic data and existing land use and economic development studies/plans
19
I-345 Public Meeting December 2, 3 and 5, 2019
Next Steps
20
I-345 Public Meeting December 2, 3 and 5, 2019
Contact Information
21
TxDOT Project Manager & Project Website: TxDOT Dallas District ATTN: Travis Campbell, P.E.
4777 E. US Highway 80 Mesquite, Texas 75150
345study@txdot.gov www.345study.com (214) 320-6100
I-345 Public Meeting December 2, 3 and 5, 2019