Siting/Conventional Facilities Status Steve Dixon PIP-II Machine Advisory Committee Meeting 15-17 March 2016 Agenda Progress over the last year Current Activities Plans for CD-1 2 S. Dixon | 2016 P2MAC 3/15/2016 Progress Over


slide-1
SLIDE 1

Siting/Conventional Facilities Status

Steve Dixon PIP-II Machine Advisory Committee Meeting 15-17 March 2016

slide-2
SLIDE 2

Agenda

  • Progress over the last year
  • Current Activities
  • Plans for CD-1

3/15/2016

  • S. Dixon | 2016 P2MAC

2

slide-3
SLIDE 3

Progress Over the Past Year

  • Developed a cooling strategy for Linac and Transfer Line

based on equipment loads

3/15/2016

  • S. Dixon | 2016 P2MAC

3

Participants: M. Ball, C. Cameron, E. Huedem, J. Hunt, V. Lebedev, A. Vivoli

slide-4
SLIDE 4

Progress Over the Past Year

3/15/2016

  • S. Dixon | 2016 P2MAC

4

Mu2e Booster

PIP-2 Linac

Wilson Hall G-2

Transport Line

  • Technical Board Meeting –

December 2015

– Accommodate Future Linac Extension – Accommodate Future Beamline to Muon Campus – Transport Line Crosses Above Main Ring (8’-0” clear) – Investigate Depth of Linac

slide-5
SLIDE 5

Progress Over the Past Year

3/15/2016

  • S. Dixon | 2016 P2MAC

5

Mu2e Booster

PIP-2 Linac

Wilson Hall G-2

Transport Line

  • Technical Board Meeting –

December 2015

– Accommodate Future Linac Extension – Accommodate Future Beamline to Muon Campus – Transport Line Crosses Above Main Ring (8’-0” clear) – Investigate Depth of Linac See following slides

slide-6
SLIDE 6

Progress Over the Past Year

3/15/2016

  • S. Dixon | 2016 P2MAC

6

Mu2e Booster

PIP-2 Linac

Wilson Hall G-2

Transport Line

  • Technical Board Meeting –

December 2015

– Accommodate Future Linac Extension – Accommodate Future Beamline to Muon Campus – Transport Line Crosses Above Main Ring (8’-0” clear) – Investigate Depth of Linac

PIP-2 Transport Line to Booster

slide-7
SLIDE 7

Progress Over the Past Year

3/15/2016

  • S. Dixon | 2016 P2MAC

7

Mu2e Booster

PIP-2 Linac

Wilson Hall G-2

Transport Line

  • Technical Board Meeting –

December 2015

– Accommodate Future Linac Extension – Accommodate Future Beamline to Muon Campus – Transport Line Crosses Above Main Ring (8’-0” clear) – Investigate Depth of Linac

slide-8
SLIDE 8

Current Activities – Through August 2016

  • Conceptual Design (phase 1)

– Document the spatial and infrastructure requirements; – Develop conceptual design drawings; – Weekly meetings with stakeholders;

Meeting Minutes (PIP-II-doc-70)

  • Wetland Delineation Update

– Spring of 2016

  • Siting Alternatives
  • One-for-One Replacement (space bank) Strategy

3/15/2016

  • S. Dixon | 2016 P2MAC

8

slide-9
SLIDE 9

Planned Activities for CD-1

  • Architect/Engineer Selection (September/October 2016)

– Work Scope based on Phase 1 drawings – Establish Source Evaluation Board – Send RFI to Candidate Firms

  • Conceptual Design (phase 2) (November 2016 – CD-1 Review)

– Site Characterization – Soil Borings; – Further develop conceptual design drawings; – Detailed Cost Estimate – Detailed Schedule

  • Develop Resource Loaded Schedule

3/15/2016

  • S. Dixon | 2016 P2MAC

9

slide-10
SLIDE 10

Planned Activities for CD-1

  • CD-1 Requirements (from 413.3B, 11-29-2010)

– Acquisition Strategy – Project Execution Plan – Risk Management Plan – Independent Cost Estimate Review – One-for-One Replacement – High Performance and Sustainable Building – Preliminary Hazard Analysis Report – Integrated Safety Management Plan – Quality Assurance Program – Safeguards and Security Requirements – NEPA Strategy – Environmental Compliance Strategy

3/15/2016

  • S. Dixon | 2016 P2MAC

10

slide-11
SLIDE 11

Siting Strategies

3/15/2016

  • S. Dixon | 2016 P2MAC

11

Mu2e Booster

PIP-2 Linac

G-2

Transport Line

slide-12
SLIDE 12

Siting Strategies

3/15/2016

  • S. Dixon | 2016 P2MAC

12

slide-13
SLIDE 13

Cross Section

3/15/2016

  • S. Dixon | 2016 P2MAC

13

Linac Enclosure Gallery

Typical Section

slide-14
SLIDE 14

Cross Section

3/15/2016

  • S. Dixon | 2016 P2MAC

14

Equipment Envelope Preliminary Linac Enclosure Section

slide-15
SLIDE 15

Site Context

3/15/2016

  • S. Dixon | 2016 P2MAC

15

From Fermilab Campus Master Plan View from Northwest

slide-16
SLIDE 16

Questions

3/15/2016

  • S. Dixon | 2016 P2MAC

16