Siting/Conventional Facilities Status Steve Dixon PIP-II Machine - PowerPoint PPT Presentation

Siting/Conventional Facilities Status Steve Dixon PIP-II Machine Advisory Committee Meeting 15-17 March 2016 Agenda Progress over the last year Current Activities Plans for CD-1 2 S. Dixon | 2016 P2MAC 3/15/2016 Progress Over


  1. Siting/Conventional Facilities Status Steve Dixon PIP-II Machine Advisory Committee Meeting 15-17 March 2016

  2. Agenda • Progress over the last year • Current Activities • Plans for CD-1 2 S. Dixon | 2016 P2MAC 3/15/2016

  3. Progress Over the Past Year • Developed a cooling strategy for Linac and Transfer Line based on equipment loads Participants: M. Ball, C. Cameron, E. Huedem, J. Hunt, V. Lebedev, A. Vivoli 3 S. Dixon | 2016 P2MAC 3/15/2016

  4. Progress Over the Past Year • Technical Board Meeting – December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac 4 S. Dixon | 2016 P2MAC 3/15/2016

  5. Progress Over the Past Year • Technical Board Meeting – December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac See following slides 5 S. Dixon | 2016 P2MAC 3/15/2016

  6. Progress Over the Past Year PIP-2 Transport • Technical Board Meeting – Line to Booster December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac 6 S. Dixon | 2016 P2MAC 3/15/2016

  7. Progress Over the Past Year • Technical Board Meeting – December 2015 – Accommodate Future Linac Mu2e Extension – Accommodate Future Beamline to Muon Campus G-2 – Transport Line Crosses Above Main Ring (8’-0” clear) Booster Wilson – Investigate Depth of Linac Hall Transport Line PIP-2 Linac 7 S. Dixon | 2016 P2MAC 3/15/2016

  8. Current Activities – Through August 2016 • Conceptual Design (phase 1) – Document the spatial and infrastructure requirements; – Develop conceptual design drawings; – Weekly meetings with stakeholders; Meeting Minutes (PIP-II-doc-70) • Wetland Delineation Update – Spring of 2016 • Siting Alternatives • One-for-One Replacement (space bank) Strategy 8 S. Dixon | 2016 P2MAC 3/15/2016

  9. Planned Activities for CD-1 • Architect/Engineer Selection (September/October 2016) – Work Scope based on Phase 1 drawings – Establish Source Evaluation Board – Send RFI to Candidate Firms • Conceptual Design (phase 2) (November 2016 – CD-1 Review) – Site Characterization – Soil Borings; – Further develop conceptual design drawings; – Detailed Cost Estimate – Detailed Schedule • Develop Resource Loaded Schedule 9 S. Dixon | 2016 P2MAC 3/15/2016

  10. Planned Activities for CD-1 • CD-1 Requirements (from 413.3B, 11-29-2010) – Acquisition Strategy – Project Execution Plan – Risk Management Plan – Independent Cost Estimate Review – One-for-One Replacement – High Performance and Sustainable Building – Preliminary Hazard Analysis Report – Integrated Safety Management Plan – Quality Assurance Program – Safeguards and Security Requirements – NEPA Strategy – Environmental Compliance Strategy 10 S. Dixon | 2016 P2MAC 3/15/2016

  11. Siting Strategies Mu2e G-2 Booster Transport Line PIP-2 Linac 11 S. Dixon | 2016 P2MAC 3/15/2016

  12. Siting Strategies 12 S. Dixon | 2016 P2MAC 3/15/2016

  13. Cross Section Gallery Linac Enclosure Typical Section 13 S. Dixon | 2016 P2MAC 3/15/2016

  14. Cross Section Equipment Envelope Preliminary Linac Enclosure Section 14 S. Dixon | 2016 P2MAC 3/15/2016

  15. Site Context View from Northwest From Fermilab Campus Master Plan 15 S. Dixon | 2016 P2MAC 3/15/2016

  16. Questions 16 S. Dixon | 2016 P2MAC 3/15/2016

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.