school improvement bond update bond accountability
play

School Improvement Bond Update Bond Accountability Committee - PowerPoint PPT Presentation

School Improvement Bond Update Bond Accountability Committee Meeting January 23, 2019 January 2019 January 2019 1 Agenda Welcome & Introductions Public Comments Balanced Scorecard Program Update Grant HS Presentation


  1. School Improvement Bond Update Bond Accountability Committee Meeting January 23, 2019 January 2019 January 2019 1

  2. Agenda • Welcome & Introductions • Public Comments • Balanced Scorecard • Program Update • Grant HS Presentation • Project Reports • Questions • Wrap-Up and Adjourn January 2019 2

  3. Public Comment January 2019 3

  4. Program Update – Balanced Scorecard January 2019 4

  5. Program Update – Balanced Scorecard January 2019 5

  6. Budget Update: Hand Out January 2019 6

  7. Budget Update: January 2019 7

  8. Budget Update: January 2019 8

  9. Budget Update: January 2019 9

  10. Program Update – Balanced Scorecard January 2019 10

  11. Program Update – Balanced Scorecard January 2019 11

  12. Program Update – Balanced Scorecard January 2019 12

  13. Schedule Update: Hand Out January 2019 13

  14. Schedule Update: Hand Out January 2019 14

  15. 2012/2017 Bond Program Accomplishments Next Steps � Continued collaboration with peer organizations � Performance auditors report out – 2017 Bond Amount Analysis � Contracted with RLB to address cost/sf equivalency � RLB cost comparison study � On-site visits with performance auditors � Overhaul to OSM approval processes to incorporate DoC � Coming back up to speed after the holidays � OCIP renewal � A/R/R study of Summer 2018 projects � VE process report out � Fernwood/Lewis/King Challenges & Opportunities � New Chief Operating Officer – Dan Jung and New Director of Construction – Dave Ruth � OSM bond management approach moving forward � Market conditions – subcontractor attitudes towards work � Seeing indicators for market slow down…primarily in multi-family housing � Communications program � 2012 Performance Audit Tracking � On-call service contracts � Legal, moving, cleaning January 2019 15

  16. Grant HS Presentation January 2019 16

  17. Progress Update: January 2019 17

  18. Progress Update: Mechanical Room Exterior Mock Up Classroom Main Commons New Gym January 2019 18

  19. Budget Update: � Additional Risks Include: � Additional General Requirements and General Conditions (.75M) � Limited recovery of funds from Auditorium Fire (.5M) � Subcontractor Claims Adjustments (.5M) � Future RFI’s (1.2M) � Buyout Allowance Overruns (2M) � Due diligence for items with ANCO and subcontractors will need to be completed including verification of cost validation, and are compensable � Projected values for potential claims, GC’s and GR’s are not included at face value. We anticipate final costs will be at reduced value � Projected value of future RFI’s are based on historical trends � Buyout packages are nearly complete. A few minor scopes remain i.e. signage, final cleaning. January 2019 19

  20. Schedule Update: � Project continues to be on schedule � Project team has overcome over 120 days of critical path schedule impacts � Challenges this past quarter have been: � AHU Delivery � Existing Structure � Abatement � Waterproofing existing conditions � Project team has completed detailed plan for installation of FF&E and Move-In � Commissioning process has begun and is on track � Detailed schedule for training PPS and GHS Administrative Staff will be developed this quarter January 2019 20

  21. Grant HS Modernization Accomplishments Next Steps � Rapid progress towards completing the project � Continuing progress towards TCO � $6M+ billing last month � On-going move logistics planning � Master planning work continuing for “Bowl” � Assessing budget status as claims are finalized � GHS Community and FAM Connections � Preparing GHS for the move back � Positive outcome with Grant Bowl � SIS schedule oversight � Updated Pay App Review Process � Overcoming all of the structural and haz mat issues Challenges & Opportunities � Subcontractor claims � Neighbor claims January 2019 21

  22. Roosevelt HS Modernization Accomplishments Next Steps � Continued progress to addressing outstanding issues � Wrap up of Ph 3 � Progressing with Ph 3 work � Some work will carry over � Stormwater planters � Address outstanding mechanical issues to bring the entire system online � Subgrades/site improvements � Fields adjustments/corrections as weather dries � Cx efforts on-going out Challenges & Opportunities � Mechanical system continues to be challenging � On-going challenges with Preventive and Deferred Maintenance support � OSM considering new approach to address mechanical system issues � South façade heat gain issues January 2019 22

  23. H&S Program Accomplishments Next Steps � A/A/R Study field work � A/A/R report out � Design work continues for summer 2019 work � Finishing designs � Tabled Chapman roof till summer 2020 � ITBs � Planning efforts for Asbestos and Painting projects � Complete design and procurement for first round of security projects � New approach for water fixture replacement � Coordinating building closures for Asbestos � Security improvements coordination Abatement and Lead Paint Stabilization projects Challenges & Opportunities � Prep for Summer 2019 projects � Termination of Fernwood contractor � Addressing Fernwood leak potentials � Addressing self perform work with possible M/W/ESB contractor � A/R/R interviews � New water fixture requirements from State…significant uptick in number of “taps” we have to address January 2019 23

  24. Kellogg MS Replacement Accomplishments Next Steps � Reviews of contract, Div 0 & 1 and GCs � RFP process to shortlist bidders � Building permit documentation � Building permit submission � On-going design efforts wrapping up � Finalization of design for bidding � Addressed outstanding issues with demolition contractor and erosion issues � 50% CD estimate on budget Challenges & Opportunities � Latest estimates show KMS on track for meeting budget � CoP permitting timeline/resources � Bid market January 2019 24

  25. Madison HS Modernization Accomplishments Next Steps � 50% CD estimate shows MHS within budget target � Bid package #3 on the streets by approx. $2M � Land use approval � Bid packages 1 & 2 active in subcontracting market � Building permit processing � Destructive testing on-going…rounds 2 & 3 � Finalization of design � On-going design efforts � Transportation Plan communcations � Transition planning Challenges & Opportunities � CoP permitting – requirements of staff, turn around times and multiple “incompletes” � ODOT right-of-way acquisition from neighbor January 2019 25

  26. Lincoln HS Modernization Accomplishments Next Steps � SDs completed, DDs underway � Continuing Design and Destructive Testing � Pathway to budget � Constructability review � TVD process � TVD process w/ Hoffman � VE process � DAG #7 � CM/GC procurement complete � 75% DD Cost Estimate � Phasing of permit to allow for early start � Review of VE process with BAC Challenges & Opportunities � VE process – over $30M savings through process � Coordinating athletic swing space � Land use process and CoP � Follow up tour? January 2019 26

  27. Lincoln HS Modernization January 2019 27

  28. Lincoln HS Modernization January 2019 28

  29. Lincoln HS Modernization January 2019 29

  30. Lincoln HS Modernization January 2019 30

  31. Lincoln HS Modernization January 2019 31

  32. Benson HS Modernization Accomplishments Next Steps � Schematic stakeholder engagement � Design Advisory Group (DAG) pre-design work sessions � Continued DAG work sessions and DAG tours of GHS, RHS, FHS � Programming & Site Specific Ed Spec & Master Plan completion � Coordination with PPR regarding south driveway/Buckman field connection � Board Work sessions & Meetings for approval � CMGC RFP and selection � Additional geotechnical testing � Master plan revisions for Board by end of March � AIA Historic Resources Panel project review Challenges & Opportunities � Occupied site planning & considerations � Determine feasibility & impacts of off-site swing to Marshall � Multiple Pathways to Graduation schools & program placement � Value Engineering Charrette & Study January 2019 32

  33. BAC Discussion Questions Next Board Presentation TBC Next BAC Meeting Date: TBD Place: TBD January 2019 33

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend