NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE June 19, 2019 BOND UPDATE: SCHEDULE: High and Middle School Seismic Projects: Under Construction Moving along on schedule. Middle school work now


slide-1
SLIDE 1

NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE

June 19, 2019

slide-2
SLIDE 2

BOND UPDATE:

SCHEDULE:

  • High and Middle School Seismic Projects:
  • Under Construction – Moving along on schedule.
  • Middle school work now expanded from gym into locker rooms, now school is out.
  • High School Renovation Project:
  • Todd Construction Under Contract
  • Mobilized on site.
  • Classroom addition – trees removed and utilities being relocated.
  • Asbestos abatement and demo taking place in CTE Building & Music Wing
  • Working on Value Engineering ideas
  • Middle School:
  • SD Scope being Modified to proceed with an estimate.
  • Documents to be ready early 2020 for Bid / Construction after spring break 2020
  • Review if Project should be added to Primary and Intermediate School Project Bid Documents
slide-3
SLIDE 3

HIGH SCHOOL:

  • CTE / MUSIC WING:
  • Asbestos removal started
  • Demolition started
  • Furniture order to be completed by next week
  • CLASSROOM WING:
  • All trees removed
  • Existing utilities being relocated
slide-4
SLIDE 4

HIGH SCHOOL GYM SEISMIC:

  • All concrete footings and slab poured.
  • All masonry walls and wood framed walls complete in basement.
  • Seismic columns being installed in basement.
  • Electrical and mechanical rough in proceeding
  • All bow truss top chords seismically enhanced
slide-5
SLIDE 5
slide-6
SLIDE 6

MIDDLE SCHOOL GYM SEISMIC:

  • All demolition complete
  • Beam / strapping installation in gym in process
  • Concrete wall poured 6.18.19
  • Started work in locker rooms 6.17.19
  • All boiler work to commence next week.
slide-7
SLIDE 7

POUR DAY

slide-8
SLIDE 8

:

MIDDLE SCHOOL PARKING LOT:

  • ALL CONCRETE FLATWORK COMPLETE
  • LIGHTING POLES TO BE INSTALLED EARLY JULY
  • IRRIGATION COMPLETE AND PLANTING EARLY NEXTY MONTH
  • PAVING TAKING PLACE THIS WEEK
  • STRIPING TO BE COMPLETE 7 DAYS AFTER PAVING
slide-9
SLIDE 9
slide-10
SLIDE 10

COMMUNICATION:

  • Web Page: www.n.marion.k12.or.us - Page has been revised:
  • Current progress photos
  • Current bidding opportunities
  • Current progress reports
  • Current Financial Reporting sheet.
  • District Wide Mailers: (attached)
  • Next to be sent about End of August.
slide-11
SLIDE 11

BOND FINANICALS:

slide-12
SLIDE 12
slide-13
SLIDE 13

QUESTIONS:

NO OVERSIGHT COMMITTEE JULY – NEXT ONE AUGUST 21, 2019