north marion school district bond projects bond oversight
play

NORTH MARION School District- Bond Projects BOND OVERSIGHT - PowerPoint PPT Presentation

NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE June 19, 2019 BOND UPDATE: SCHEDULE: High and Middle School Seismic Projects: Under Construction Moving along on schedule. Middle school work now


  1. NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE June 19, 2019

  2. BOND UPDATE: SCHEDULE: • High and Middle School Seismic Projects: • Under Construction – Moving along on schedule. • Middle school work now expanded from gym into locker rooms, now school is out. • High School Renovation Project: • Todd Construction Under Contract • Mobilized on site. • Classroom addition – trees removed and utilities being relocated. • Asbestos abatement and demo taking place in CTE Building & Music Wing • Working on Value Engineering ideas • Middle School: • SD Scope being Modified to proceed with an estimate. • Documents to be ready early 2020 for Bid / Construction after spring break 2020 • Review if Project should be added to Primary and Intermediate School Project Bid Documents

  3. HIGH SCHOOL: • CTE / MUSIC WING: • Asbestos removal started • Demolition started • Furniture order to be completed by next week • CLASSROOM WING: • All trees removed • Existing utilities being relocated

  4. HIGH SCHOOL GYM SEISMIC : • All concrete footings and slab poured. • All masonry walls and wood framed walls complete in basement. • Seismic columns being installed in basement. • Electrical and mechanical rough in proceeding • All bow truss top chords seismically enhanced

  5. MIDDLE SCHOOL GYM SEISMIC : • All demolition complete • Beam / strapping installation in gym in process • Concrete wall poured 6.18.19 • Started work in locker rooms 6.17.19 • All boiler work to commence next week.

  6. POUR DAY

  7. MIDDLE SCHOOL PARKING LOT: • ALL CONCRETE FLATWORK COMPLETE • LIGHTING POLES TO BE INSTALLED EARLY JULY • IRRIGATION COMPLETE AND PLANTING EARLY NEXTY MONTH • PAVING TAKING PLACE THIS WEEK • STRIPING TO BE COMPLETE 7 DAYS AFTER PAVING :

  8. COMMUNICATION: • Web Page: www.n.marion.k12.or.us - Page has been revised: • Current progress photos • Current bidding opportunities • Current progress reports • Current Financial Reporting sheet. • District Wide Mailers: (attached) • Next to be sent about End of August.

  9. BOND FINANICALS:

  10. QUESTIONS: NO OVERSIGHT COMMITTEE JULY – NEXT ONE AUGUST 21, 2019

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend