NORTH MARION School District- Bond Projects BOND OVERSIGHT - - PowerPoint PPT Presentation

north marion school district bond projects bond oversight
SMART_READER_LITE
LIVE PREVIEW

NORTH MARION School District- Bond Projects BOND OVERSIGHT - - PowerPoint PPT Presentation

NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE February 19, 2020 BOND UPDATE: SCHEDULE: High School Renovation Project: All structural framing complete. Exterior weather Barrier On going dependent on


slide-1
SLIDE 1

NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE

February 19, 2020

slide-2
SLIDE 2

BOND UPDATE:

SCHEDULE:

  • High School Renovation Project:
  • All structural framing complete.
  • Exterior weather Barrier On going dependent on weather.
  • Installation of Exterior wall panels to commence next week.
  • Vapor barrier installed on roof. Roofing occurring when weather permits.
  • Windows 85% installed.
  • Mechanical and electrical rough in continuing.
  • Drywall installed on 2/3rds of building.
  • Staircases installed.
  • Painting commenced this week.
  • 2nd floor gypcrete floor installed on 2/3rds of building
  • Opening of classroom wing – Has been moved to end of April (Parent Conference Week)
  • Middle / Intermediate /Primary School:
  • Project will be bid as one project.
  • Project Bids February 25th, 2020
  • Construction start date to be negotiated with Successful Contractor – Probably evenings after

spring break.

slide-3
SLIDE 3

HIGH SCHOOL:

  • CLASSROOM WING EXTERIOR:
slide-4
SLIDE 4
  • CLASSROOM WING INTERIOR:
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7

PRIMARY SCHOOL SCOPE: New Restroom New Vestibule / Admin Remodel Scope Includes but limited to:

  • New Restroom
  • New Vestibule / Admin Remodel
  • Paint Exterior of Building
  • Cameras
  • Access Control
slide-8
SLIDE 8

INTERMEDIATE SCHOOL: SCOPE Includes but not Limited to:

  • New Vestibule / Admin

Remodel

  • New exterior Doors
  • New Mech and lighting

In Library

  • New Restrooms
  • New Classroom Locks
  • New Roof
slide-9
SLIDE 9

MIDDLE SCHOOL: SCOPE Includes but not limited to:

  • New Mechanical System
  • New Roof
  • New Vestibule & Admin Remodel
  • Access Control.
  • Locker room remodel
  • New Restrooms
  • New Finishes in Student restrooms
slide-10
SLIDE 10

New Vestibule / Admin Remodel Locker Room Remodel

slide-11
SLIDE 11

SITE WORK:

slide-12
SLIDE 12

BOND FINANCIALS:

slide-13
SLIDE 13
slide-14
SLIDE 14

QUESTIONS:

WELCOME TO ATTEND PROJECT WALK WITH BOARD: February 24, 2020 at 5:15pm NEXT OVERSIGHT COMMITTEE March 18, 2020