NORTH MARION School District- Bond Projects BOND OVERSIGHT - - PowerPoint PPT Presentation

north marion school district bond projects bond oversight
SMART_READER_LITE
LIVE PREVIEW

NORTH MARION School District- Bond Projects BOND OVERSIGHT - - PowerPoint PPT Presentation

NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE April 17, 2019 BOND UPDATE: PROCUREMENT SCHEDULE: High and Middle School Seismic Projects: Bid April 9 th , 2019 Received 3 bids / Had Interest from 7


slide-1
SLIDE 1

NORTH MARION School District- Bond Projects BOND OVERSIGHT COMMITTEE

April 17, 2019

slide-2
SLIDE 2

BOND UPDATE:

PROCUREMENT SCHEDULE:

  • High and Middle School Seismic Projects:
  • Bid April 9th, 2019
  • Received 3 bids / Had Interest from 7 Companies.
  • High School Renovation Project:
  • Bid April 11th, 2019
  • Received 2 bids / Four Prequalified / One Dropped when Documents issued (Just

received large project from existing client) / One could not complete number on bid day.

  • Primary and Intermediate School Projects:
  • Bids May 2nd, 2019
  • Presently 6 interested companies.
  • Middle School:
  • Received word last week from ODE that NMSD was not successful with our second grant

application.

  • Scope review discussions to commence first week of May.
  • Documents to be ready early 2020 for Bid / Construction after spring break 2020
slide-3
SLIDE 3

CONSTRUCTION:

  • MISC. PROJECTS:
  • Wilson Property:
  • Removed all nut trees from property.
  • Burnt all trees during spring Break.
  • Johnston property:
  • All hazardous Material abated.
  • Aurora Fire District used House for Training purposes every Monday evening for 2 months.
  • Aurora Fire District completed burn to learn activity March 30, 2019
  • Presently cleaning up house footprint and infilling the basement for safety.
  • Corner Lot adjacent Baseball field:
  • Rock parking lot completed – Will be laydown and trailer lot for High School Project.
  • Additional rock parking after completion of construction projects.
slide-4
SLIDE 4

CONSTRUCTION:

Parking Lots:

  • Primary School:
  • Schedule: All Complete except installation of Light Poles & Punch List
  • Completed By All-Way Excavating – On Schedule
  • Includes additional 14 parking stalls
  • 2nd Entrance to move traffic off Grim Road at drop off and pick up (Marion County

Request)

  • Middle School:
  • Schedule: Ahead of Schedule – Substantial completion Aug. 1st / Plan to be complete by early July.
  • Construction by All-Way Excavating
  • Includes an additional 63 parking stalls/new parent and bus drop off and pick up.
  • Presently 3 Change Orders
  • Relocate spoils to Wilson Property in Lieu of Johnston Property
  • Over Excavation due to unforeseen soft soils
  • Burn Wilson Property Trees & Clean Up Johnston Property House
  • Present Disruption to School:
  • No Parking – Staff at district office parking or Primary School
  • Bus Drop Off and Pick Up – Behind High School
  • School Office: Entrance at Commons Door by Buzzer System
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7

HIGH SCHOOL:

  • Bid April 11, 2019 – Bid/Budget Discussion during Financial Review
  • Ground Breaking Scheduled May 8th, 2019 @ 5:30pm
  • Furniture Vendor has been selected and design started. Procurement of Furniture will be by

Cooperative Purchasing Agreements after selections. Furniture will be procured by Phasing. PHASING:

slide-8
SLIDE 8

May 2019 to End of School Year Scope of work * Start of Classroom Wing Construction * Gym and Locker Room Seismic

slide-9
SLIDE 9

SUMMER 2019: Scope of Work for Summer: * Continue with classroom wing construction * Complete Gym and Locker Room Seismic * Remodel Music Wing * Remodel CTE Building

slide-10
SLIDE 10

Fall 2019 – Spring Break: September 2019: Following Staff Relocated: * Spanish to Room 7 * Sped to new suite in Music Wing. * ELL to Room 1 * Culinary to New Suite in CTE Building * Ag Science to Room 3 New Bus Pick Up/ Drop off @ Commons Parking No Staff Room for Duration of School Year. Scope of Work: * Construction of Classroom Wing

Construction Laydown

Safety Tunnel Student Travel Path

slide-11
SLIDE 11

Scope of Work * Demo of Existing classroom/admin wings * Construction of Admin Wing & Courtyard * Construction of Student Parking Spring Break 2020 to completion of Project (Oct/Nov 2020) Spring Break 2020 Front Entrance of School thru Commons for remainder of project Following Staff Relocated: * Admin Office Relocated to temp office set up in Commons at end of Husky Hall (Closed) * DeAnn / Ron / Cheri Relocated to new Conference rooms and offices in Music Wing. * Career Center set up in New Music Storage Room. * Counseling / Family Outreach Relocated to offices / Training room in gym 1 basement. Completion of Project: * Relocate above staff to new locations within Administration Wing September 2020: * Partial open of new student parking lot

slide-12
SLIDE 12

NEW HIGH SCHOOL LAYOUT

slide-13
SLIDE 13

HIGH SCHOOL EXTERIOR

slide-14
SLIDE 14

HIGH SCHOOL INTERIOR

slide-15
SLIDE 15

BOND EVENTS:

HIGH SCHOOL GROUND BREAKING:

  • Scheduled for May 8, 2019 @ 5:30pm
  • Speeches related to Scope, Bond and Thanking community
  • Renderings showing new construction
  • Shovels in the ground
  • School Jazz Band Playing
slide-16
SLIDE 16

COMMUNICATION:

  • Web Page: www.n.marion.k12.or.us - Page has been revised:
  • Current progress photos
  • Current bidding opportunities
  • Current progress reports
  • Current Financial Reporting sheet.
  • District Wide Mailers: (attached)
  • One Currently being mailed. Copies available at Parent Conferences.
  • Next to be sent about End of August.
  • School Specific Flyers:
  • Middle school parking lot /School Access – Sent with Report Cards.
  • Primary School – Changes to Drop off / Pick Up flyer given to parents week before Spring Break
slide-17
SLIDE 17
slide-18
SLIDE 18
slide-19
SLIDE 19

BOND FINANICALS:

slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22

QUESTIONS: