The Township of Lyndhurst New Middle School
Project Status-Pathway to Completion "Quality and Safety Enabling Improved Education and Community Facilities." Benecke Economics June 9, 2020
1
The Township of Lyndhurst New Middle School Project Status-Pathway - - PowerPoint PPT Presentation
The Township of Lyndhurst New Middle School Project Status-Pathway to Completion "Quality and Safety Enabling Improved Education and Community Facilities." Benecke Economics June 9, 2020 1 Lyndhurst Middle School Critical Path
1
5/29/2020 Critical Path Confirmed Railings, Lockers, Seats BE 6/1/2020 TCO Process Started Permit List Created Epic/Township 6/2/2020 Conditions for Turnover Presented to BOC BE 6/3/2020 Punch List Updated Three Building Section DRA 6/4/2020 Emergency Access Installed Ridge Road Epic 6/8/-6/9/2020 Punch List Update DRA 6/10/2020 Clean up continues Epic 6/17/2020 Furniture Install Begins BE/Epic 6/26/2020 Training Day-systems Epic 7/7/2020 Locker Equipment Install Realistic Target Date Epic/DRA 7/30/2020 Auditorium Seat Install Realistic Target Date Epic/DRA 7/30/2020 Landscape Install Review CO Target Date Epic 7/30/2020 Furniture Install Substantially Complete Realistic Target Date Epic/BE 8/3/2020 Week of Final Conditions Work/Details ALL 8/10/2020 School Prepared for Turnover Training Continues on Systems ALL 9/3/2020 Grand Opening Community Event BOC 9/7/2020 Estimated Start of School Year Subject to School Meeting Turnover Conditions. BOE
2
Traditional Classrooms 27 Science Classrooms 5 Culinary Teaching Stations 7 Think Tank Classroom 1 Maker Space Classroom 1 Art Classroom 1 Music Classrooms 2 Small Group Instruction Rooms 6 Teacher Resource Rooms 3 General Offices 11 Security Offices 2 Administrative Workstations 7 Conference Rooms 4 Media Center 1 Number of Lockers 818 Cafeteria Seats 316 Faculty Dining Seats 30 Auditorium Capacity (Total Seats) 706 Gymnasium Bleacher Seats (Approximate) 700 Building entrance vestibule (double entry type for security) Full sized performance stage with curtains Video monitoring system Wrestling room/auxiliary gymnasium Outdoor classroom area- footings for potential school expansion Workout/training room Outdoor patio area-adjacent to cafeteria/culinary lab Two locker rooms (boys/girls) OEM communications room with equipment installed-on site Traditional school kitchen/serving cafeteria-with pizza oven Lower field reconstruction for multiple outdoor sports Separate receiving/loading area Lower field lighting for night activities New skating rink Fieldhouse-with bathrooms Parking spaces-122 on site upper level. 28 Lower level.
3
Township of Lyndhurst – School Project Flow Chart June 9, 2020
I
OEM-POLICE-FIRE Coordination
4
5
6
Examples: 1-Skylands Engineering, Don Hamnet, PE, on February 20, 2019, cleared the building “the slab and the foundation wall are sound and have the ability to support all design intended loading.” Hamnet also consulted on the original geotechnical study. 2-During the period of November 1, 2018 through January 2019 we had a concern about masonry work-a focus on the northeast corner. This include block workmanship, sheathing and other issues. We had a comprehensive review and BE brought in RT Engineering for an additional opinion. Remedies were made and the building and masonry were “triple” inspected. Hamnet was also involved. 3-During the spring of 2020 we had issues with roofing “lips” and corners. Also, issues with upper siding-a focus on the southeast corner {both building sides}, panels were and roofing re-inspected. 4-The elevator subcontractor (manufacturer) had issues with certain features (electric, temporary shelter during work, etc.). We worked directly with the subcontractor to solve some serious logistics. 5-The driveway and parking areas of the school have been constructed utilizing the traditional three layer flexible pavement design. The first layer soil is dense graded aggregate base course, this material is quarry mixed product that meets the NJDOT specifications and consists
approved mix) and the last layer is hot mix asphalt surface course, mix 9.5m64 (NJDOT approved mix). As certain areas of the site are subjected to different weight vehicles and in an effort to provide the most fiscal responsible project the site was constructed utilizing a heavy duty pavement section (areas subjected to trucks, buses, etc.) and a light duty pavement section (areas subjected to parked cars). The heavy duty pavement section consists of 10” thick of dense graded aggregate base course, 6” thick of hot mix asphalt base course, mix 19M64 and 2” thick of hot mix asphalt surface course, mix 9.5M64 and the light duty pavement section consists of 6” thick of dense graded aggregate base course, 3” thick of hot mix asphalt base course, mix 19M64 and 2” thick of hot mix asphalt surface course, mix 9.5M64.
7
8
9
10
11