schedule structure budget evm safety people 2013 a
play

Schedule, Structure, Budget, EVM, Safety, People, 2013 : a memorable - PowerPoint PPT Presentation

Schedule, Structure, Budget, EVM, Safety, People, 2013 : a memorable year ! First beam accelerated by the RFQ, 13.3.2013 Klystrons and modulators installed in the Linac4 Hall 22.11.2013: 3 MeV beam in the tunnel 12.12.2013: 52 mA from IS-02


  1. Schedule, Structure, Budget, EVM, Safety, People,…

  2. 2013 : a memorable year ! First beam accelerated by the RFQ, 13.3.2013 Klystrons and modulators installed in the Linac4 Hall 22.11.2013: 3 MeV beam in the tunnel 12.12.2013: 52 mA from IS-02 28- 30.9.2013, Open Days: 2’500 visitors!

  3. to be compared to 9 months needed for PSB H- injection installation and commissioning July 2018 , LS2: start Linac4 connection work Present Linac4 commissioning schedule ends December 2016. Restart after EYETS in April 2017: need a program for Linac4 from May 2017 to July 2018.

  4. Red: tunnel closed Blue: free access New : revised yesterday, integrating comments at the Installation meeting and latest DTL schedule Milestones : - Hardware ready for 50 MeV protons (replacement Linac2) on 8.12.2014 - End of commissioning (160 MeV to dump) end 2015 2016 (or more?) for reliability run, partial transfer line commissioning, PSB half-sector test

  5. Schedule different from what discussed on Monday – to be now detailed by Julie Next step : Drift Tube Linac commissioning (see presentation by S. Ramberger) – DTL1, DTL2, DTL3 February . 3 MeV measurements – March : moving diagnostics line, installing DTL1 at end March – April : RF conditioning of DTL1 (tunnel closed, access possible during day) – May : Beam tests DTL1 (beam permit for May 1 st !) – from June 15th : moving and rearranging diagnostics line, installation CCDTL and PIMS1, DTL3 installation at end July – August : 1 st half RF conditioning DTL3 (tunnel closed, access possible during day), 2 nd half installation DTL2 – September : conditioning DTL3 (2 weeks), beam measurements – October : beam measurements until 15.10 – From October 15 th : installations (CCDTL last 2 modules, 100 MeV diagnostics line, transfer line) – December : Start HW tests 105 MeV. Windows for ion source (IS02 installation): 15.6 – 30.8 (2.5 months), 15.10 – 31.12 (2.5 months).

  6. 2016: reliability run, partial transfer line commissioning, PSB half-sector test 2017/18: three options 1. continue half-sector test and other beam measurements 2. leave Linac4 idle, run it from time to time 3. switch Linac4 to protons for injection tests at 50 MeV in the PSB, delivering 80 mA (maximum allowed by RFQ and RF – to be confirmed for the ion source) with 0.6 p mm mrad rms emittance = half the current and half the emittance than Linac2 – good for LHC, could lead to lower losses for ISOLDE and same intensity. Need switching magnet at BHZ20 position to allow injection from both linacs. P. Collier and R. Garoby have given to K. Cornelis a mandate to study the proton option:

  7. Welcome to Jeremie Bauche who replaces Thomas Zickler for the magnet WP Note that from 1.7.2014 I will leave the BE Department to be attached to F. Bordry (as EuCARD2 and not as Linac4!) and I’ll move my office to B.30 sometimes in March.

  8. Have been sent yesterday to Rpc the budget estimates (CET) for 2014, based on EVM and (in all critical cases) on your direct input. Foreseen expenditure in 2014 is 11 MCHF Good agreement in EVM between EV and AC No EVM rebaselining foreseen in 2014 (and until the end of project!) An EVM report will be prepared in June

  9. From January 1st, 2014: - Helmet and safety shoes are no longer mandatory in the surface hall B.400, but remain compulsory for: lifting interventions works where the VIC requires personal protections - Helmet and safety shoes remain compulsory in the tunnel (from the surface hall access system to the end of the tunnel). Be careful, identify clearly equipment under voltage during HW tests! A new Safety File is in preparation to obtain the approval of the Tripartite Safety Authorities to switch on the beam at energies from 12 MeV (DTL1). A visit on site will be organised in March. underground areas

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend