overview of today s discussion
play

Overview of Todays Discussion Brief Overview of EVM Concepts Dont - PowerPoint PPT Presentation

Overview of Todays Discussion Brief Overview of EVM Concepts Dont Let EVM Data Why you cant trust BACs or EACs Mislead You Why EVM progress is Steve Sheamer often overstated Why you need to account for schedule risk How to


  1. Overview of Today’s Discussion Brief Overview of EVM Concepts Don’t Let EVM Data Why you can’t trust BACs or EACs Mislead You Why EVM progress is Steve Sheamer often overstated Why you need to account for schedule risk How to prevent yourself from being fooled

  2. In theory, EVM data provides everything a cost estimator needs to develop an estimate BCWS $$ or Hours ACWP BCWP Time 2

  3. In theory, EVM data provides everything a cost estimator needs to develop an estimate BCWS $$ or Hours ACWP A measure of how much work has BCWP been accomplished to date. What percentage of the work is done? Time 3

  4. In theory, EVM data provides everything a cost estimator needs to develop an estimate BCWS How much it cost to complete the $$ or work that has been performed to Hours ACWP date. BCWP Time 4

  5. In theory, EVM data provides everything a cost estimator needs to develop an estimate How much work was scheduled to be completed and how much planned work remains. BCWS $$ or Hours ACWP BCWP Time 5

  6. In theory, EVM data provides everything a cost estimator needs to develop an estimate BCWS BAC The budget to complete all of the work (initial estimate of cost). $$ or Hours ACWP BCWP Time 6

  7. In addition to measures against the plan, EVM data also includes updated estimates of costs at completion EAC or BCWS LRE BAC $$ or Hours ACWP BCWP Time 7

  8. Issue #1: Budgets at Completion and Estimates at Completion (or LREs) are often significantly underestimated What a Cost Estimator is trying to determine Actual Cost at Completion

  9. Assume a company is submitting a bid on a competitive cost reimbursable contract that is over $50M for a new product Initial Cost Forecast $160M including all known Risks Program Lifecycle

  10. The company decides that some risks are unlikely to occur and they are willing to accept these risks in their estimate Initial Cost Forecast $160M including all known Risks $130M Revised Forecast with selected risks Program Lifecycle

  11. Management determines that the price needs to be lowered in order to ensure a competitive bid Initial Cost Forecast $160M including all known Risks $130M Revised Forecast with selected risks Competitive Bid $100M Price Program Lifecycle

  12. The EVM Budget at Completion is then based on a “bid to win” price with much of the known risk stripped out Initial Cost Forecast $160M including all known Risks $130M Revised Forecast with selected risks Competitive Bid $100M Price Program Lifecycle

  13. Unfortunately, the known risk that a company has accepted is nowhere to be found in EVM reporting Initial Cost Forecast $160M including all known Risks Amount of Known Risk that a company is willing to accept on a $130M Revised Forecast cost reimbursable contract. with selected risks Competitive Bid $100M Price Program Lifecycle

  14. Oftentimes a program runs into issues that were not anticipated when the budget or EACs were developed $200M Actual cost at completion including Unforeseen Risks Initial Cost Forecast $160M including all known Risks Budget at $100M Completion Program Lifecycle

  15. Below are a few examples of potential unforeseen risks that may not be accounted for in BACs / EACs Late engineering, engineering changes, Tooling, equipment, facilities, and Optimistic Estimates and scope creep process issues Man Hours Forecast Actual Time Environmental Issues (e.g., weather Material Delays / Quality Excessive Re-work / Re-testing delays, labor strikes) issues

  16. It is up to the skilled cost estimator to determine the gap between the budget and the actual cost at completion $200M Actual cost at completion including Unforeseen Risks Initial Cost Forecast $160M including all known Risks Forecasting uncertainty gap that the skilled cost estimator must close. Competitive Bid $100M Price Program Lifecycle

  17. EACs are carefully managed by program managers and often adjusted downward for political reasons Initial bottoms- up EAC BCWS BAC $$ or Hours ACWP BCWP Time 17

  18. EACs are carefully managed by program managers and often adjusted downward for political reasons Threshold of Political Viability BCWS BAC $$ or Hours ACWP BCWP Time 18

  19. Remember the Threshold of Political Viability when deciding whether or not to trust a reported EAC Threshold of Political Viability Reported BCWS EAC BAC $$ or Hours ACWP BCWP Time 19

  20. Consider the role of the EVM analyst relative to the role of the cost estimator when analyzing EVM data Analyzed cost growth on 35 Major Defense Acquisition Programs  Develop a plan to execute within  Determine if the plan is budget (whether realistic or not) reasonable and executable  Ensure reported EACs are  Ensure EACs are accurate and acceptable to management reflect all remaining work  Strike a balance between  Evaluate risk and ensure the budgeting for risk and padding estimate includes an appropriate estimates level of risk  Explain variances to plan and  Use independent data to cross- make adjustments to the plan as check EACs and estimating needed assumptions 20

  21. Issue #2: Progress is often overstated due to unplanned work and the realization of known and unknown risks BCWS $$ or Hours ACWP BCWP Reported BCWP Actual Time 21

  22. Issue #2: Progress is often overstated due to unplanned work and the realization of known and unknown risks BAC =1,000 Hours of Work to complete 100 engineering drawings 1,000 Hours After the first 25 drawings are completed, 25% 250 Hours progress is used to calculate BCWP (250 hours)

  23. Issue #2: Progress is often overstated due to unplanned work and the realization of known and unknown risks BAC = 1,000 Hours of Work to complete 100 engineering drawings 1,000 Hours After the first 25 drawings are completed, 25% 250 Hours progress is claimed and reported as BCWP As a result of design issues, 25 new drawings 250 Hours are required at 250 hours 250 Hours

  24. Issue #2: Progress is often overstated due to unplanned work and the realization of known and unknown risks BAC = 1,000 Hours of Work to complete 100 engineering drawings 1,000 Hours After the first 25 drawings are completed, 25% 250 Hours progress is claimed and reported as BCWP As a result of design issues, 25 new drawings 250 Hours are required at 250 hours 250 Hours A bottoms-up weight analysis 250 Hours requires 50 drawings to be reworked at 10 hours each 500 Hours

  25. Issue #2: Progress is often overstated due to unplanned work and the realization of known and unknown risks 250 Hours 1,000 Hours 250 Hours 500 Hours After accounting for the additional in-scope work, the actual percent complete is ~14% instead of the reported 25%.

  26. Issue #3: Schedule risk is rarely accounted for in BACs or EACs Actual Cost at Completion The slope of ACWP is always positive. Time costs money. Always evaluate schedule risk.

  27. The following illustrates the need to account for schedule risk using an LOE control account as an example. BAC =1,000 Hours of LOE Systems Engineering Support over 10 months

  28. The following illustrates the need to account for schedule risk using an LOE control account as an example. BAC =1,000 Hours of LOE Systems Engineering Support over 10 months 50% of scheduled time has passed. BCWS = 500 Hours.

  29. The following illustrates the need to account for schedule risk using an LOE control account as an example. BAC =1,000 Hours of LOE Systems Engineering Support over 10 months 50% of scheduled time has passed. BCWS = 500 Hours Since it’s an LOE account, BCWP = BCWS = 500 Hours

  30. The following illustrates the need to account for schedule risk using an LOE control account as an example. BAC =1,000 Hours of LOE Systems Engineering Support over 10 months 50% of scheduled time has passed. BCWS = 500 Hours. Since it’s an LOE account, BCWP = BCWS = 500 Hours ACWP = 450 Hours, 90 Hours/month

  31. The following illustrates the need to account for schedule risk using an LOE control account as an example. BAC =1,000 Hours of LOE Systems Engineering Support over 10 months 50% of scheduled time has passed. BCWS = 500 Hours. Since it’s an LOE account, BCWP = BCWS = 500 Hours ACWP = 450 Hours, 90 Hours/month Using the Gold Card Formulas gives SPI = 1.0, CPI = 1.1 and EAC equal to 900 Hours.

  32. The following illustrates the need to account for schedule risk using an LOE control account as an example. BAC =1,000 Hours of LOE Systems Engineering Support over 10 months 50% of scheduled time has passed. BCWS = 500 Hours. Since it’s an LOE account, BCWP = BCWS = 500 Hours ACWP = 450 Hours, 90 Hours / month 270 Hours A schedule risk assessment indicates the schedule is likely to slip 3 months resulting in an additional 270 hours and a risk-adjusted EAC of 1,170 hours. This is 30% higher than the EAC derived from the gold card formula.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend