SCHEDULE 2017 2018 2019 SEPTEMBER SEPTEMBER NOVEMBER NOVEMBER - - PowerPoint PPT Presentation

schedule
SMART_READER_LITE
LIVE PREVIEW

SCHEDULE 2017 2018 2019 SEPTEMBER SEPTEMBER NOVEMBER NOVEMBER - - PowerPoint PPT Presentation

SCHEDULE 2017 2018 2019 SEPTEMBER SEPTEMBER NOVEMBER NOVEMBER DECEMBER DECEMBER DECEMBER FEBRUARY FEBRUARY OCTOBER OCTOBER JANUARY JANUARY AUGUST AUGUST MARCH MARCH APRIL APRIL JUNE JUNE JULY JULY MAY MAY Alternatives


slide-1
SLIDE 1

FREMONT AVENUE

BRIDGE PROJECT 2017 2018 2019 DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER Alternatives analysis Environmental documentation for preferred alternative Project Implementation Engineering Engineering

SCHEDULE

slide-2
SLIDE 2

FREMONT AVENUE

BRIDGE PROJECT

  • Both bridges reopened to traffjc as of December 2017
  • Most major construction activities on both bridges

are complete

  • Some curbs, sidewalks, and striping are temporary

treatments and will be replaced with permanent installations in the spring

  • Work remaining for 2018 includes:
  • Installing permanent curbs, sidewalks, and

striping

  • Final decorative rail installation in certain locations
  • Final concrete fjnishing and painting
  • Planting and landscaping
  • These fjnal tasks should not require full closures of

either roadway or the Greenway bike/pedestrian lanes and crews will work to keep other traffjc disruptions to a minimum

PORTLAND AND CEDAR AVENUE BRIDGES UPDATE

slide-3
SLIDE 3

FREMONT AVENUE

BRIDGE PROJECT

STAY IN TOUCH

Before you go,

SUBMIT A COMMENT CARD

Ask questions Provide feedback by March 5 Emphasize concerns or suggestions you have

VISIT THE PROJECT WEBSITE

www.hennepin.us/greenwaybridges

CONTACT

DEAN MICHALKO Project Engineer dean.michalko@hennepin.us NICK KIM Community Liaison nick.kim@hennepin.us 612-543-4255

HENNEPIN COUNTY WANTS TO HEAR FROM YOU