Sanitary Sewer #200 Area Flow Equalization
Review of Project Design Criteria and Storage Options City of Northwood Planning Commission – Preliminary Site Plan Review Meeting – December 8, 2014
1
Sanitary Sewer #200 Area Flow Equalization Review of Project Design - - PowerPoint PPT Presentation
Sanitary Sewer #200 Area Flow Equalization Review of Project Design Criteria and Storage Options City of Northwood Planning Commission Preliminary Site Plan Review Meeting December 8, 2014 1 Project History City of Oregon
Review of Project Design Criteria and Storage Options City of Northwood Planning Commission – Preliminary Site Plan Review Meeting – December 8, 2014
1
City of Oregon Agreement with Ohio EPA
Requires Various Improvements to Oregon System
District Flows limited to 5 mgd
District / City of Oregon Agreement
Renewed April 2014
Flow Rate Limitation Maintained at 5 mgd
New Requirements
Flow Control Equipment
Permanent Flow Metering
2 Million Gallons of Storage
18 months to Complete Improvements (October 2015)
2
5 mgd rate exceeded 60+ times in 18 months*
I/I Removal & Reduction
Flow Equalization Storage
*Study Period from 1/2011 to 6/2012
3
Costly – Estimated at over $20 million dollars.
Time Consuming – I/I reduction schedule in years, not months.
Results Uncertain – sealing leaks in one area often moves leak to another.
Definitions:
Inflow - Surface runoff directly entering Sanitary Sewer through illegally connected piping.
Infiltration – Groundwater water entering pipe and manhole defects.
4
5
Reduce Piping Costs
Reduce Pumping Costs
Optimize Operation – Basin requires sewer to surcharge to fill.
Existing Flow Control Structure
6
SS-200 Sanitary Sewer Service Area City of Oregon Treatment
7
8
Buried Pipeline
Buried Structure
9
2.5 MG Basin – Terra Haute, IN
10
High Tension Electric
Wetlands
Construction Methods
11
12
2.1 MG Basin Butler County, OH
13
Option 2 MG Storage Pipeline 2 MG Above Grade Basin Cost Savings Estimated Initial Project Cost $7,800,000 $5,100,000 $2,700,000 Estimated Annual O&M Cost* $37,400 $92,100 $(54,700) Estimated Annual Debt Service on Initial Project Cost (20 yrs at 3.1% APR – Ohio EPA DEFA Loan) $530,000 $340,000 $190,000 Estimated Total Annual Cost $567,400 $432,100 $135,300
*Includes Equipment Replacement Costs.
14
Option / Criteria 2 MG Storage Pipeline 2 MG Above Grade Basin Land / Site Permanent Utility Easement Lands Purchased by District Operation Fill & Draw by Gravity Pumping to Fill Access Below Grade Above Grade Cleaning Outside Contractor Flushing Equipment & District Equipment Hydraulic Level and Flow Control Devices Pump Station & Telemetry (10MGD Capacity) Electric Power Minimal New 3 Phase Power for Pumps Backup Power None Required Required for Pumps Risk from Equipment Failure Basement Flooding Due to Reduction in Sewer Freeboard Minimal, excess flows to Oregon District Pays Flow Surcharge Site Maintenance Minimal Mowing / Landscaping Building Maint. Semi-annual Internal Inspection Annual Inspection Outside Utilities Coordination Toledo Edison & Sunoco Pipelines City of Northwood, Toledo Edison & Sunoco Pipelines Insurance Buried Pipe Above Grade Structure
15
Task 2 MG Storage Pipeline* 2 MG Above Grade Basin NWSD / City Contract Effective Date April 2014 Final Design Complete October 2014 December 2014 Bidding May 2014 March 2014 Construction Commencement July 2015 June 2015 Construction Complete August 2016 January 2016 Contract Deadline for District Construction of Storage Improvements October 2015
16
All dates estimated as normal construction projects. Accelerated design and construction schedules may be possible at a cost premium. *The presented construction schedule based upon favorable pipe procurement.
17
18