Safety Management & Site Establishment Unit 10 Site Temporary - - PowerPoint PPT Presentation

safety management site
SMART_READER_LITE
LIVE PREVIEW

Safety Management & Site Establishment Unit 10 Site Temporary - - PowerPoint PPT Presentation

Safety Management & Site Establishment Unit 10 Site Temporary Works Learning Outcomes How access to heights is gained and how structures are temporarily supported in the construction process Different styles of formwork for


slide-1
SLIDE 1

Unit 10 – Site Temporary Works

Safety Management & Site Establishment

slide-2
SLIDE 2

 How access to heights is gained and how structures are temporarily supported in the construction process  Different styles of formwork for moulding concrete  Excavation and trenching and other groundwork techniques

Learning Outcomes

slide-3
SLIDE 3

 Temporary i.e. non-permanent works  Temporary Works are installed on site to help fulfil the execution of the actual (permanent) contract works  Temporary Works will be dismantled/removed from site upon fulfilment of their respective purposes.  This Unit looks at four types of temporary works:

  • Access
  • Support
  • Protection
  • Groundworks (including excavations, ground supports and

hydro-geological controls)

Introduction

slide-4
SLIDE 4

 Frequently, temporary works play multiple roles but their selection is based on the primary project requirements  This Unit details typical examples of the intertwined functions of temporary works to be expected on modern sites  It also describes the indispensable roles that they typically function in every construction project  These are roles that usually account for a significant percentage

  • f the project’s running costs

Introduction

slide-5
SLIDE 5

An example showcasing the extensive and combined utilities of temporary support and access structures.

slide-6
SLIDE 6

 Ladders should be a means

  • f access, not a working

platform  Main selection considerations will reside on suitability of work, safety/durability, cost and portability.

Easily available, ladders are essential as both the main and back-up tools of access

Ladders

slide-7
SLIDE 7

 Must be positioned so as not to tip the scaffold  Hook-on and attachable ladders must be specifically designed for use with the type of scaffold on which they are used  Have rest platforms provided at a max. of 10m vertical intervals

Portable, hook-on, and attachable ladders:

slide-8
SLIDE 8

 When positioned their bottom step is not more than 24 inches above the scaffold supporting lever.  Have rest platforms at maximum vertical intervals of 12 feet  Have a minimum step width of 16 inches, except for mobile scaffold stairway-type ladders, which shall have a minimum step width of 11½ inches.  Have slip-resistant treads on all steps and landings.  Steps and rungs of ladders and stairway-type ladders shall line up vertically with each other between rest platforms.

Stairway-type ladders:

slide-9
SLIDE 9
  • Conventional step-ladders have rectangular stiles and flat

treads that are arranged to be horizontal when in use, and are restrained in position by means of stays, chains or cords.

  • Some variants use flat-topped rungs, while others could be of

tubular construction.

Step ladders

slide-10
SLIDE 10

Scaffolding

slide-11
SLIDE 11
  • Despite being temporary structures, the design of scaffolds

follows the principles laid down for permanent structures

  • There must be no deviation from sound structural principles
  • There is generally enough variety in standard scaffold equipment

to erect a platform to suit most work requirements

  • Scaffolds are sometimes used for purposes other than access

e.g. as falsework supporting a formwork system (to be discussed later) during concreting processes

Common (independent) scaffolds

slide-12
SLIDE 12

Framed

Common (independent) scaffolds

slide-13
SLIDE 13

Tubular

Common (independent) scaffolds

slide-14
SLIDE 14

Common scaffolds Putlog A putlog scaffold consists of a single row

  • f standards, parallel to

the face of the building and set as far away from it as is necessary to accommodate a platform

  • f four or five boards

wide, with the inner edge of the platform as close to the wall as is practicable

slide-15
SLIDE 15

Common scaffolds Bird-cage

slide-16
SLIDE 16

Common scaffolds

Birdcage

  • Birdcage scaffolds are commonly used for access to soffit or

ceiling, as well as to provide heavy-duty and sturdy falsework support for horizontal slab casting.

  • Due to its modular assembly and adjustable members, the

entire mass of support components can be easily shaped to provide horizontal support to massive areas.

  • It also assists in providing a more uniformly distributed

loading pattern from the structure to the ground

slide-17
SLIDE 17

17

Tower scaffolding

  • More efficient than a ladder,
  • All towers have to be endorsed by a

professional engineer,

  • Most commercially produced towers

can be assembled without the use of tools

  • Easy to transport within short

distances due to the casters.

slide-18
SLIDE 18

18

Truss-out scaffold

  • It is useful in high-rise construction,
  • It is useful in avoiding busy sidewalk

pedestrian traffic,

  • Requires highly skilled personal to

erect and dismantle.

  • There is an extra risk on H&S due to

vibrations and heights etc.

slide-19
SLIDE 19

Common scaffolds

slide-20
SLIDE 20

Common scaffolds

slide-21
SLIDE 21

Common scaffolds

slide-22
SLIDE 22

Scaffold Class Activity:

Scaffold Types;

  • Tower scaffolds
  • Common scaffolds (independent scaffold)
  • Putlog scaffolds
  • Birdcage scaffold
  • Truss-out scaffold

Working as a group; 1. Produce a sketch drawing of the each type, highlight main elements, 2. Find 3 examples works/cases/scenarios for each, when these scaffold types would be more useful than others, 3. Identify safety and practicality concerns for each type, 4. Identify safety and practicality benefits for each type,

slide-23
SLIDE 23
  • Hoists are used to transport personnel and

materials to different working levels

  • Modern hoists operate on the rack and pinion

system

  • The hoist unit have its drive motor fitted on top
  • f the car, along with brake and gear
  • This technology enables the car to climb up

and down the mast at a controlled speed

Hoists

slide-24
SLIDE 24

Hoist Details

slide-25
SLIDE 25
  • Mobile elevating platforms are used as an alternative to scaffolds and

suspended cradles (described later in the Unit)

  • They are particularly suitable for short duration tasks requiring high

mobility of the access structures, especially so for retrofitting projects where clients are seeking short durations

  • The market offers a wide variety of these platforms, and guidance
  • n specific applications should be sought from the manufacturers
  • There are generally two categories of mobile elevating platforms:

Self-propelled and Vehicle-mounted

  • http://www.youtube.com/watch?v=_sqTICuXsMg

Mobile elevating platforms

slide-26
SLIDE 26

Self-propelled Platform Hoists

Articulated-telescopic boom Self-propelled Scissor platform

  • These can easily be manoeuvred

into position by onboard controls.

  • They are mainly available with the

following boom types, namely: scissor, telescopic and articulated

slide-27
SLIDE 27

Vehicle-mounted platform Hoists

  • These platforms come in various sizes

and capacities, from small trailer- mounted platforms to large truck- mounted types

  • Smaller platforms are commonly used

in highway and other road-related maintenance (e.g. pruning trees, servicing street-lamps etc.)

  • Larger versions are used where

access by other methods are deemed either too expensive

  • r

time- consuming

slide-28
SLIDE 28

Mast climbing platform hoists

slide-29
SLIDE 29
  • Mast climbing platforms allow access to a localised

area of a project

  • The rack and pinion drive gives an adjustable

working platform that can be positioned exactly to suit the task in hand

  • Tools and materials can be carried up to the

work site, together with the operatives

  • Mast climbing platforms are for work and access

purposes only and must not be used for transporting men and materials between levels.

  • The three main components are; Mast(s) or tower(s);

a platform capable of supporting persons & equipment and a chassis supporting the tower/mast

Mast climbing platform hoists

slide-30
SLIDE 30

Mast climbing platform hoists

slide-31
SLIDE 31
  • Two-point adjustable suspension scaffolds, also known as

‘swing-stage scaffolds’ or ‘gondolas’, are perhaps the most common type of suspended scaffold.

  • Hung by ropes or cables connected to stirrups at each end of

the platform, they are commonly seen to be used by window cleaners on skyscrapers, and play a prominent role in high- rise construction

Suspended cradle (gondola)

slide-32
SLIDE 32

Suspended cradle (gondola)

slide-33
SLIDE 33

Suspended cradle (gondola)

slide-34
SLIDE 34

Suspended cradle (gondola)

slide-35
SLIDE 35
  • Abseiling

(or industrial roped access) can provide a safe and cost-effective method of access for light work commonly

  • f

maintenance or inspection nature.

  • Modern roped access equipment

and techniques allow fully trained specialist operatives to reach highly inaccessible locations, some of extreme conditions (e.g. from narrow mineshafts to

  • verhanging

external details under apexes of skyscrapers).

Abseiling

slide-36
SLIDE 36

It is a highly feasible method to consider if

  • Ground

conditions are either unknown

  • r

unsuitable to support any vertical access (e.g. crane, scaffold & the like).

  • In situations when the heights of work locations

cannot be reached from the ground (e.g. due to safety or physical constraints) and no strong anchorage points are available for gondolas.

  • Time and cost efficient for light tasks (e.g.

maintenance of the main glass pyramid at Louvre Museum , France)

Abseiling

slide-37
SLIDE 37

BS 6100, Section 6.5,[10] defines formwork as ‘A structure, usually temporary, but in some cases wholly

  • r partly permanent, used to contain poured concrete

to mould it to the required dimensions and support it until it is able to support itself. It consists, primarily, of the face contact material and the bearers that directly support the face material.’ Kindly explain the difference between the formwork and the falsework?

Formwork

slide-38
SLIDE 38

Formwork vs Falsework The term ‘formwork’ is commonly confused and associated with another, namely ‘falsework’, the latter being a term used to described temporary support systems such as those scaffold supports as previously covered. BS 5975[12] defines falsework as ‘Any temporary structure used to support a permanent structure during its erection and until it becomes self supporting.’

slide-39
SLIDE 39
  • Selection of the formwork system is a key factor that governs the

success of a project in terms of time, cost, quality and safety

  • For high-rise buildings, the most effective plan is for the works to

achieve a very short floor cycle

  • The key to achieving this is to exploit an efficient and

appropriately designed formwork system.

  • Modern buildings are generally complex in terms of scale and

size so the design and use of the right formwork system, will contribute substantially to the overall success of a project.

Formwork

slide-40
SLIDE 40

Kindly discuss the common formwork materials and types available in

  • construction. Produce a spider diagram to include the following;
  • Common formwork materials
  • Common types of formwork,
  • Implications and uses of each category,
  • Disadvantages of each type.

Formwork

slide-41
SLIDE 41

Categories of Formwork

  • Size
  • Location of use
  • Material of construction
  • Nature of operation
  • Proprietary system
slide-42
SLIDE 42
  • Materials

used for formwork are traditionally limited due to the dilemma between cost and performance.

  • Timber in general is still the most

popular formwork material, due to its low initial cost and adaptability.

Categories of Formwork

slide-43
SLIDE 43
  • In recent years, full aluminium formwork system has been used but

the performance is being questioned by many, particularly with regards to additional costs and the need for specialised workmen -

http://www.youtube.com/watch?feature=endscreen&v=Yqu21vPBylY&NR=1

Categories of Formwork

slide-44
SLIDE 44
  • Steel in either hot-rolled or cold-formed sections and in combination

with other sheeting materials, is another popular choice of formwork material.

Categories of Formwork

slide-45
SLIDE 45

Most timber and aluminium forms can be assembled manually, due to their weight, design and construction.

  • It is labour intensive, and used in simpler jobs; or occasionally

used in very large or complex buildings to attain the benefit in flexibility

  • Some systems are equipped with a degree of mobility to ease the

erection and striking processes

  • These formworks are generally categorised as either the crane-

lifted types or the mechanised slip-form systems.

  • In the crane-lifted category large panels are fabricated either in

steel sections and sheeting, or using plywood sheeting and stiffened by metal studs and soldiers.

  • These large panels can be positioned either on a solid slab or

fixed onto brackets (e.g. should they be used for external walls or shafts).

Formwork

slide-46
SLIDE 46
  • Slip-form formwork systems use hydraulic or screw-jack systems (either

automated or manual), and these systems allow for continuous casting till the end of a typical section is reached.

  • Slip form formwork is raised vertically in a continuous process. It is a method
  • f vertically extruding a reinforced concrete section and is suitable for

construction of core walls in high-rise structures – lift shafts, stair shafts, towers, etc.

  • Slip-form system derived its name from the fact that the formwork itself

actually ‘slip off’ a previously cast structure

  • It moves when the structure has taken physical shape with both its

cementitious properties and composite bond with the reinforcements being set (i.e. harden) to a safe and acceptable level for the absence of the physical form support.

  • The process is continuous and encourages a sense of urgency in the steel-

fixers and casting crew to adhere to appropriately timed and scheduled activities in order to compliment the continuum.

Slip-form formwork

slide-47
SLIDE 47

Slip-form formwork http://www.youtube.com/watch?v=LKoj-N0-YyA http://www.youtube.com/watch?v=zrUNHQeDkXw

slide-48
SLIDE 48

Climbing-form formwork http://www.youtube.com/watch?v=xIPpBvY Sx8Q

slide-49
SLIDE 49

Custom formwork

slide-50
SLIDE 50

Custom formwork

slide-51
SLIDE 51

Custom formwork

slide-52
SLIDE 52

Repetitive sequence of work:

  • High-rise block structures usually create highly repetitive cycles of

work and may be suitable for certain kinds of formwork.

  • However, for horizontally spanned buildings, the level of

repetitiveness will be limited Physical site constraints:

  • Sites with numerous physical and contractual restrictions (e.g.

sloped grounds, minimal site access or manoeuvre space, close proximity to sensitive structures), will increase difficulties from the mobilisation stage (i.e. getting the formwork onto site and storing them) to subsequent erection.

Formwork: Construction-related factors

slide-53
SLIDE 53

Speed of work:

  • Work on low rise construction sites can be accelerated by

the introduction of additional sets of formwork to create more independent work sites.

  • This increases costs and should be considered only when

time is of the essence e.g. when the risk of imposed delay penalties exceeds the costs of having additional systems

  • For high-rise buildings, the mere increase of formwork input

cannot often fulfil the need for speed in construction, as the critical path depends on individual floor-cycles times. Therefore the selected formwork design needs to support minimal floor-cycle times.

Formwork: Construction-related factors cont’d

slide-54
SLIDE 54

Formwork: Construction-related factors cont’d

Recycling of formwork:

  • The number of times timber formwork can be reused is usually

limited to its durability after every striking process (i.e. the removal

  • f falsework, struts and wedges, followed by plywood sheetings)
  • Oil-based coatings are applied to contact surfaces of the plywood

sheetings and left to dry, prior to the erection process

  • Timber form may usually be used for up to ten casts, thus making it

economically viable as the main option for formwork

  • Though reusability of metal form is greatly superior, its high initial

and maintenance costs will often discourage its choice of use

  • Careful balance between cost, speed, performance and quality of
  • utputs should be properly maintained when making the selection
slide-55
SLIDE 55

Construction planning and management:

  • Planning i.e. phasing or sectioning arrangements, integration of

the structures, site-layout and setting up arrangements, and the hoisting and concrete placing facilities, etc., are influential factors in the selection and use of formwork. Area or volume of cast per pour:

  • The optimum volume of cast per pour will be different and in

accordance to the types of formwork used, elements of structure to be placed and specific scale of work

  • Usually volume of concrete ranging from 50m3 (non-continuous

pour from approx. 10 safely-laden ready-mixed concrete trucks) to 200m3 (continuous pour involving (e.g.) elephant concrete pumps from approx. 40 trucks of the same) per pour can be comfortably planned for most site environments.

Formwork: Construction-related factors cont’d

slide-56
SLIDE 56

Formwork: Construction-related factors cont’d Continuity of structures and construction joints:

  • Introducing a large number of construction joints in a large

structure subdivides the works into effective and workable sizes,

  • Being the weak physical links of any structure, construction-joints

are inevitable in all forms of building.

  • Design engineers conceptualise form systems and

site staff exercise common sense, in conjunction with strict adherence to design specifications, to ensure the rigidity of a structure.

  • In order to ensure rigidity of the overall system

during the casting process, form-ties are incorporated into the formwork design

  • These accessories once (partially or wholly)

removed after casting, have their locations patched with high strength grout and should not affect the overall structural integrity of their structures.

slide-57
SLIDE 57

Involvement of other construction techniques:

  • The applications of tensioning

(http://www.youtube.com/watch?v=7JsuNg5r4Is) and

prefabrication techniques are often involved in the construction of modern high-rise buildings, especially so in the Far East.

  • This may impede the casting schedules and dictate the selection

and use of formwork, especially where pre-cast elements are to be incorporated during the casting process.

  • Additional provisions of temporary supports, slot spaces and

boxed-out positions in the formwork for the pre-cast elements, or additional working spaces for the placing of stressing tendons and the onward jacking process, should be allowed in such cases.

Formwork: Construction-related factors cont’d

slide-58
SLIDE 58

Excavations and trenching

  • An excavation is any man-made cut, cavity, trench, or depression

in an earth surface that is formed by earth removal.

  • A Trench is a narrow excavation (in relation to its length) made

below the surface of the ground.

  • In general, the depth of a trench is greater than its width, and the

width (measured at the bottom) is not greater than 5m.

  • If a form or other structure installed or constructed in an

excavation reduces the distance between the form and the side of the excavation to 5m or less (measured at the bottom of the excavation), the excavation is also considered to be a trench.

Groundworks

slide-59
SLIDE 59

Safety introduction:

  • Excavating is recognized as one of the most hazardous

construction operations and this Unit will highlight various trenching methods, hazards and their preventions.

Groundworks

slide-60
SLIDE 60

Soil mechanics: An overview

  • A number of stresses and deformations can occur in an open

cut site or trench. For example, increases or decreases in moisture content can adversely affect the stability of a trench

  • r excavation.
  • The following diagrams show some of the more frequently

identified causes of trench failure.

Groundworks

slide-61
SLIDE 61

Groundworks: Soil mechanics

TENSION CRACKS. Tension cracks usually form at a horizontal distance of 0.5 to 0.75 times the depth of the trench, measured from the top of the vertical face of the trench.

Figure 9.7.1: Tension Cracks

SLIDING or sluffing may occur as a result of tension cracks.

Figure 9.7.2: Sliding

  • TOPPLING. In addition to sliding, tension

cracks can cause toppling. Toppling occurs when the trench's vertical face shears along the tension crack line and topples into the excavation.

Figure 9.7.3: Toppling

slide-62
SLIDE 62

SUBSIDENCE AND BULGING. An unsupported excavation can create an unbalanced stress in the soil, which, in turn, causes subsidence at the surface and bulging of the vertical face of the trench. If uncorrected, this condition can cause face failure and entrapment of workers in the trench.

Figure 9.7.4: Subsidence and Bulging

HEAVING OR SQUEEZING. Bottom heaving or squeezing is caused by the downward pressure created by the weight of adjoining soil. This pressure causes a bulge in the bottom of the cut, as illustrated in the drawing above. Heaving and squeezing can

  • ccur even when shoring or shielding has been

properly installed.

Figure 9.7.5: Heaving or Squeezing

BOILING is evidenced by an upward water flow into the bottom of the cut. A high water table is one of the causes of boiling. Boiling produces a "quick" condition in the bottom of the cut, and can occur even when shoring or trench boxes are used.

Figure 9.7.6: Boiling

Groundworks: Soil mechanics

slide-63
SLIDE 63

Ground shoring is the provision of a support system for trench walls, used to prevent movement of soil, underground utilities, roadways, and foundations. Shoring or shielding is used when the location or depth of the cut makes sloping back to the maximum allowable slope impractical. There are generally two types of shoring systems, each with its own sub-categories:

  • Ground shores support soil structures usually beneath ground

level and are commonly used in conjunction with trenching and sheet-piling systems to prevent the inward collapse of the surrounding earth.

  • Structural shores typically support either existing building

structures that are deemed too structurally dilapidated to be in self-support, or as a falsework in support of the erection process

  • f new structures.

Groundworks: Groundshores

slide-64
SLIDE 64

Strut shoring

  • Strut shoring is the most basic

form of ground shoring support. The system consists of posts, wales, struts, and sheeting

  • The supporting struts are the main

components that resist the push factor from the surrounding earth

  • The preferred materials for struts

are timber and aluminium, the former being cheap and readily available, with the latter being strong and light

Groundworks: Groundshores

slide-65
SLIDE 65

Hydraulic shoring

  • The modern trend is towards

the use of hydraulic shoring, a prefabricated strut and/or wale system manufactured of aluminium or steel.

  • Hydraulic shoring provides a

critical safety advantage over traditional strut shoring as workers do not have to enter the trench to install or remove the shoring components

Groundworks: Groundshores

slide-66
SLIDE 66

Groundworks: Groundshores

slide-67
SLIDE 67
  • Ground shields or trench boxes are

different from shoring.

  • Instead of shoring upwards or otherwise

supporting the trench face, they are intended primarily to protect workers from cave-ins and similar incidents.

  • The excavated area between the
  • utside of the trench box and the face of

the trench should be as small as possible.

  • The space between the trench boxes

and the excavation side are backfilled to prevent lateral movement of the box.

Groundworks: Groundshields

slide-68
SLIDE 68

Groundworks: Groundshields

slide-69
SLIDE 69

69

Trench Boxes (Shields)